2458
Comment:
|
2620
|
Deletions are marked like this. | Additions are marked like this. |
Line 6: | Line 6: |
==== Report for week of 2/26 ==== * We routed all the cables from the BF level up via the flying saucer to the SF. * Hirata-san tried filing the SF cap to improve the fit, but without much success. * Hirata-san installed the Cu segments and cable clamps on the SF cap and the SF LVDT and FR cables. * We cabled and tested the BF cap picos and the SF LVDT and FR. (The LVDT still needs a full calibration.) * We worked on recovering the IM OSEM alignment. |
==== Report for week of 3/26 ==== |
Line 13: | Line 8: |
==== Plan for week of 3/5 ==== * Shoda-san at Mitaka. * Hirata-san vacation Mon 3/5, then Kamioka * Others at Kamioka. * - * '''Remove LBB temporary ballast masses from BS chamber.''' * Finish recovering IM OSEM alignment. * Calibrate SF LVDT. * Lift SF/... section and check total mass and balance. * Get SRM tank mushroom section installed (Hirata-san, Kimura-san) * Set up for rebuilding of two BFs. |
BFs: |
Line 25: | Line 10: |
==== Plan for week of 3/12 ==== * Shoda-san at Mitaka. * Mark at ASJ (Chiba) Fri, then Mitaka. * Hirata-san vacation Mon 3/5; Kamioka Tue-Thu; Mitaka Fri * Others Kamioka Mon-Thu * Install boxes in SR3 and SRM racks. * Lay SR3 in-air cabling. * Continue rebuild of BFs. |
* BF No. 1: * Fujii-san finished tuning. Optimal load: 52.15[kg]. Resonance frequency: 0.36[Hz]. Optimal height: 64.7[mm]. * We wired the LVDT, Picomotor and Steppermotor. * We measured the keystone tilt at different points and the diferences are within 0.1[mm] * We added cable clamps to the base. |
Line 34: | Line 16: |
==== Plan for week of 3/19 ==== * Mark at LVC meeting * All others at Mitaka * Make two sets of IM OSEMs * Make last in-air pico adapter cable * Make three in-air stepper splitter cables for SR2, SR3 and SRM. * Set up Dummy BS prism removal. |
* BF No.7: * Fujii-san replaced the blades corresponding to the BS and for the SR type blades. * The yoke position was corrected. * The fishing rod was assembled. * Compression tuning is ongoing. |
Line 42: | Line 22: |
==== Plan for week of 3/26 ==== * Mark vacation. |
SFs: * Hirata-san and Tanioka-san set up the frame to check the SFs. * SF (B2-5): * Hirata-san, Fujii-san and Tanioka-san checked the optimal load with and without cap. The optimal load changes about 250[g]. * We measured the keystone tilt at different points, and the diferences are within 0.1[mm] * SF (B2-6): * Hirata-san, Fujii-san and Tanioka-san checked the optimal load with and without cap (On going?). * We measured the keystone tilt at different points, and the diferences are within 0.3[mm] SR3/SRM: * Kozu-kun and Enzo finished the SR3 in-air cabling. * Enzo prepared the SR3 and SRM rack in parallel (On going). BS: * Kozu-kun and Enzo helped Enomoto-san troubleshooting the BS Oplev issue (On going). * We finished the SR3 in-air cabling. ==== Plan for week of 4/2 ==== * Mark at Mitaka Mon, Kamioka from Tue. |
Line 47: | Line 52: |
* F0 Prototype Blade Test * Characterize blades. * Choose best set of three. * Remove cracked blades from filter in SRM area. * Set up test weights in SRM area, first floor. * Remove floor panel in SRM area, second floor. * Install chosen blades. * Measure load capacity. |
* Finish BFs tasks (cabling +calibration) * Finish SFs tasks (cabling +calibration) * Add cable clamps to bases. * Add cable clamps and Cu segments to caps (only if they fit well). * Build 2xIM, 2xIRM * Glue SR3 mirror? ==== Plan for week of 4/9 ==== * Shoda-san at Mitaka * Others at Kamioka * -- * Finish IMs and IRMs * Build 1xRM ==== Plan for week of 4/16 ==== * Start SR3 Hang? ==== Plan for week of 4/23 ==== * F0 blade prototype test ==== Plan for week of 4/30 ==== * Golden Week! |
Line 65: | Line 84: |
* Hirata-san vacation, Mon 3/5. |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 3/26
BFs:
- BF No. 1:
- Fujii-san finished tuning. Optimal load: 52.15[kg]. Resonance frequency: 0.36[Hz]. Optimal height: 64.7[mm].
- We wired the LVDT, Picomotor and Steppermotor.
- We measured the keystone tilt at different points and the diferences are within 0.1[mm]
- We added cable clamps to the base.
- BF No.7:
- Fujii-san replaced the blades corresponding to the BS and for the SR type blades.
- The yoke position was corrected.
- The fishing rod was assembled.
- Compression tuning is ongoing.
SFs:
- Hirata-san and Tanioka-san set up the frame to check the SFs.
- SF (B2-5):
- Hirata-san, Fujii-san and Tanioka-san checked the optimal load with and without cap. The optimal load changes about 250[g].
- We measured the keystone tilt at different points, and the diferences are within 0.1[mm]
- SF (B2-6):
- Hirata-san, Fujii-san and Tanioka-san checked the optimal load with and without cap (On going?).
- We measured the keystone tilt at different points, and the diferences are within 0.3[mm]
SR3/SRM:
- Kozu-kun and Enzo finished the SR3 in-air cabling.
- Enzo prepared the SR3 and SRM rack in parallel (On going).
BS:
- Kozu-kun and Enzo helped Enomoto-san troubleshooting the BS Oplev issue (On going).
- We finished the SR3 in-air cabling.
Plan for week of 4/2
- Mark at Mitaka Mon, Kamioka from Tue.
- Shoda-san at Mitaka
- Others at Kamioka
- --
- Finish BFs tasks (cabling +calibration)
- Finish SFs tasks (cabling +calibration)
- Add cable clamps to bases.
- Add cable clamps and Cu segments to caps (only if they fit well).
- Build 2xIM, 2xIRM
- Glue SR3 mirror?
Plan for week of 4/9
- Shoda-san at Mitaka
- Others at Kamioka
- --
- Finish IMs and IRMs
- Build 1xRM
Plan for week of 4/16
- Start SR3 Hang?
Plan for week of 4/23
- F0 blade prototype test
Plan for week of 4/30
- Golden Week!
To-Do Lists, Schedule
Vacation Info
- Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
- Fabian vacation, 3/26-4/27 (then gone).