==== Report for week of 2/26 ====
 * We routed all the cables from the BF level up via the flying saucer to the SF.
 * Hirata-san tried filing the SF cap to improve the fit, but without much success.
 * Hirata-san installed the Cu segments and cable clamps on the SF cap and the SF LVDT and FR cables.
 * We cabled and tested the BF cap picos and the SF LVDT and FR. (The LVDT still needs a full calibration.)
 * We worked on recovering the IM OSEM alignment.

==== Plan for week of 3/5 ====
 * Shoda-san at Mitaka.
 * Hirata-san vacation Mon 3/5, then Kamioka
 * Fabian Mitaka Mon-Tue (COMSOL training), Kamioka Wed-Fri.
 * Others at Kamioka.
 * -
 * '''Remove LBB temporary ballast masses from BS chamber.'''
 * Finish recovering IM OSEM alignment.
 * Calibrate SF LVDT.
 * Lift SF/... section and check total mass and balance.
 * Get SRM tank mushroom section installed (Hirata-san, Kimura-san)
 * Set up for rebuilding of two BFs.
==== Report for week of 3/5 ====
 * Mark finished -v2 of the schedule ([[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779| L1807779]]).
 * We removed the non-vacuum-compatible ballast mass from the BS tank.
 * We secured all the PR2 feedthrough connections with screws.
 * We grabbed an extra empty rack for SRM and set it up next to the one for SR3 (we will add boxes next week).
 * We calibrated the SR2 SF LVDT sensing and actuation, and the FR.
 * We measured the bounce frequencies of the SF with and without the cap, and the bounce frequency of the BF.
 * We put the SF cap on and lifted and weighed the SF/... section.
 * However we were unhappy with how the cap had to be forced on and off and how it lowered the load capacity (≈-433 g) and resonance frequency (0.271 Hz-> 0.23 Hz).
 * We tried the cap left over from B2-3 used in one of the PRs, which was slightly better but still not great.
 * We measured diameter of the original cap (B2-2) and the new one (B2-3). The original cap was almost exactly 700 mm in internal diameter, and the new one was about 0.2 mm wider.
 * We moved the filter building bench and tools into the SRM area and started the rebuild of the two remaining BFs (the one from the BS Test Hang and the one with the tilted keystone).
 * Mark worked on slides for the ASJ and LVC meetings.
 * The SRM mushroom work was postponed due to other demands on the time of Sawada-san-tachi and Mirapro.
Line 29: Line 24:
 * Hirata-san vacation Mon 3/5; Kamioka Tue-Thu; Mitaka Fri
Line 31: Line 25:
 * F2F VIS Meeting and Farewell Party for Fabian at Mitaka on Friday.
 * --
Line 34: Line 30:
 * Ship dummy BS to Mitaka.
Line 36: Line 33:
 * Fujii-kun and Tanioka-kun join.
Line 37: Line 35:
 * Fujii-kun at Kamioka
Line 38: Line 37:
 * --
 * Put four geophones in pods.
Line 42: Line 43:
Line 48: Line 50:
 * F0 Prototype Blade Test
  * Characterize blades.
  * Choose best set of three.
  * Remove cracked blades from filter in SRM area.
  * Set up test weights in SRM area, first floor.
  * Remove floor panel in SRM area, second floor.
  * Install chosen blades.
  * Measure load capacity.
 * SF Check
  * Check load capacity.
  * Check fit of caps.
  * Add cable clamps to bases.
  * Add cable clamps and Cu segments to caps (only if they fit well).
  * Cable LVDTs and steppers.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 3/5

  • Mark finished -v2 of the schedule (L1807779).

  • We removed the non-vacuum-compatible ballast mass from the BS tank.
  • We secured all the PR2 feedthrough connections with screws.
  • We grabbed an extra empty rack for SRM and set it up next to the one for SR3 (we will add boxes next week).
  • We calibrated the SR2 SF LVDT sensing and actuation, and the FR.
  • We measured the bounce frequencies of the SF with and without the cap, and the bounce frequency of the BF.
  • We put the SF cap on and lifted and weighed the SF/... section.
  • However we were unhappy with how the cap had to be forced on and off and how it lowered the load capacity (≈-433 g) and resonance frequency (0.271 Hz-> 0.23 Hz).

  • We tried the cap left over from B2-3 used in one of the PRs, which was slightly better but still not great.
  • We measured diameter of the original cap (B2-2) and the new one (B2-3). The original cap was almost exactly 700 mm in internal diameter, and the new one was about 0.2 mm wider.
  • We moved the filter building bench and tools into the SRM area and started the rebuild of the two remaining BFs (the one from the BS Test Hang and the one with the tilted keystone).
  • Mark worked on slides for the ASJ and LVC meetings.
  • The SRM mushroom work was postponed due to other demands on the time of Sawada-san-tachi and Mirapro.

Plan for week of 3/12

  • Shoda-san at Mitaka.
  • Mark at ASJ (Chiba) Fri, then Mitaka.
  • Others Kamioka Mon-Thu
  • F2F VIS Meeting and Farewell Party for Fabian at Mitaka on Friday.
  • --
  • Install boxes in SR3 and SRM racks.
  • Lay SR3 in-air cabling.
  • Continue rebuild of BFs.
  • Ship dummy BS to Mitaka.

Plan for week of 3/19

  • Fujii-kun and Tanioka-kun join.
  • Mark at LVC meeting
  • Fujii-kun at Kamioka
  • All others at Mitaka
  • --
  • Put four geophones in pods.
  • Make two sets of IM OSEMs
  • Make last in-air pico adapter cable
  • Make three in-air stepper splitter cables for SR2, SR3 and SRM.
  • Set up Dummy BS prism removal.

Plan for week of 3/26

  • Mark vacation.
  • Shoda-san at Mitaka
  • Others at Kamioka
  • --
  • SF Check
    • Check load capacity.
    • Check fit of caps.
    • Add cable clamps to bases.
    • Add cable clamps and Cu segments to caps (only if they fit well).
    • Cable LVDTs and steppers.

To-Do Lists, Schedule

Vacation Info

  • Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
  • Hirata-san vacation, Mon 3/5.
  • Fabian vacation, 3/26-4/27 (then gone).