Differences between revisions 243 and 330 (spanning 87 versions)
Revision 243 as of 2018-03-02 15:38:06
Size: 2520
Editor: MarkBarton
Comment:
Revision 330 as of 2018-09-28 13:27:48
Size: 2209
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 6: Line 6:
==== Report for week of 2/26 ====
 * We routed all the cables from the BF level up via the flying saucer to the SF.
 * Hirata-san tried filing the SF cap to improve the fit, but without much success.
 * Hirata-san installed the Cu segments and cable clamps on the SF cap and the SF LVDT and FR cables.
 * We cabled and tested the BF cap picos and the SF LVDT and FR. (The LVDT still needs a full calibration.)
 * We worked on recovering the IM OSEM alignment.
==== Report for week of 9/24 ====
 * Monday 9/24 was a holiday (Autumn Equinox).
===== SR2 =====
 * We moved all the SR2 feedthrough and in-vacuum and in-air cables.
 * We tested all the OSEMs and most of the LVDTs. We still need to run power to the pico drivers, and test them and the steppers.
 * We unlocked and mostly realigned the suspension. The IM is sitting lower than before but can be brought up to nominal height with BF GAS offset, without any signs of anything touching. The IM also has a moderately large pitch (2.8 mrad according to the OSEMs, about 1 mrad according to the OL) and some roll, which we expect to be able to correct with some pico adjustment. The horizontal IM OSEMs are well-centered (so there is no yaw misalignment).
Line 13: Line 13:
==== Plan for week of 3/5 ====
 * Shoda-san at Mitaka.
 * Hirata-san vacation Mon 3/5, then Kamioka
 * Fabian Mitaka Mon-Tue (COMSOL training), Kamioka Wed-Fri.
 * Others at Kamioka.
 * -
 * '''Remove LBB temporary ballast masses from BS chamber.'''
 * Finish recovering IM OSEM alignment.
 * Calibrate SF LVDT.
 * Lift SF/... section and check total mass and balance.
 * Get SRM tank mushroom section installed (Hirata-san, Kimura-san)
 * Set up for rebuilding of two BFs.
===== SRM =====
 * We made another attempt to set the pitch of the SRM, but weren't satisfied with how close we were able to get (target 20 mm low, achieved 23 mm), so we didn't tighten the clamps or continue to setting the pitch of the RM.
Line 26: Line 16:
==== Plan for week of 3/12 ====
 * Shoda-san at Mitaka.
 * Mark at ASJ (Chiba) Fri, then Mitaka.
 * Hirata-san vacation Mon 3/5; Kamioka Tue-Thu; Mitaka Fri
 * Others Kamioka Mon-Thu
 * Install boxes in SR3 and SRM racks.
 * Lay SR3 in-air cabling.
 * Continue rebuild of BFs.
==== Plan for week of 10/1 ====
 * Mark, Hirata-san, Fabian, Panwei at Kamioka Mon-Fri.
===== SRM =====
 * Set pitch of SRM and RM, tighten clamps, remove winch system.
 * Weigh IM/... section.
 * Build up SS to BF level.
 * Add BF.
 * Suspend IM and tweak height/balance.
 * Cable/test BF.
 * Install IRM.
 * Install/cable/test IM OSEMs.
Line 35: Line 28:
==== Plan for week of 3/19 ====
 * Mark at LVC meeting
 * All others at Mitaka
 * Make two sets of IM OSEMs
 * Make last in-air pico adapter cable
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM.
 * Set up Dummy BS prism removal.

==== Plan for week of 3/26 ====
 * Mark vacation.
 * Shoda-san at Mitaka
 * Others at Kamioka
 * --
 * F0 Prototype Blade Test
  * Characterize blades.
  * Choose best set of three.
  * Remove cracked blades from filter in SRM area.
  * Set up test weights in SRM area, first floor.
  * Remove floor panel in SRM area, second floor.
  * Install chosen blades.
  * Measure load capacity.
==== Plan for week of 10/8 ====
 * Monday 10/8 is Sports Day.
 * Enzo returns Tuesday 10/9.
 * Mark and Terrence (plus TBD) at Kamioka Mon-Fri.
 * Enzo, Hirata-san, Fabian and Panwei at Kamioka Tue-Fri.
===== SR2/SR3 =====
 * Terrence to set up LEN half of SR3 OL and, time permitting, TILT and LEN for SR2.
===== SRM =====
 * Continue installation.
Line 58: Line 39:
 * [[KAGRA/Subgroups/VIS/TypeB/March2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/April2018]]
Line 62: Line 41:
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]  * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]
Line 64: Line 43:
==== Vacation Info ====
 * Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
 * Hirata-san vacation, Mon 3/5.
 * Fabian vacation, 3/26-4/27 (then gone).
==== Vacation/Visitor Info ====
 * Enzo: 9/15 through 10/8 vacation in Chile.
 * Terrence: 10/8-12, 10/29-11/2 at Kamioka.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 9/24

  • Monday 9/24 was a holiday (Autumn Equinox).

SR2
  • We moved all the SR2 feedthrough and in-vacuum and in-air cables.
  • We tested all the OSEMs and most of the LVDTs. We still need to run power to the pico drivers, and test them and the steppers.
  • We unlocked and mostly realigned the suspension. The IM is sitting lower than before but can be brought up to nominal height with BF GAS offset, without any signs of anything touching. The IM also has a moderately large pitch (2.8 mrad according to the OSEMs, about 1 mrad according to the OL) and some roll, which we expect to be able to correct with some pico adjustment. The horizontal IM OSEMs are well-centered (so there is no yaw misalignment).

SRM
  • We made another attempt to set the pitch of the SRM, but weren't satisfied with how close we were able to get (target 20 mm low, achieved 23 mm), so we didn't tighten the clamps or continue to setting the pitch of the RM.

Plan for week of 10/1

  • Mark, Hirata-san, Fabian, Panwei at Kamioka Mon-Fri.

SRM
  • Set pitch of SRM and RM, tighten clamps, remove winch system.
  • Weigh IM/... section.
  • Build up SS to BF level.
  • Add BF.
  • Suspend IM and tweak height/balance.
  • Cable/test BF.
  • Install IRM.
  • Install/cable/test IM OSEMs.

Plan for week of 10/8

  • Monday 10/8 is Sports Day.
  • Enzo returns Tuesday 10/9.
  • Mark and Terrence (plus TBD) at Kamioka Mon-Fri.
  • Enzo, Hirata-san, Fabian and Panwei at Kamioka Tue-Fri.

SR2/SR3
  • Terrence to set up LEN half of SR3 OL and, time permitting, TILT and LEN for SR2.

SRM
  • Continue installation.

To-Do Lists, Schedule

Vacation/Visitor Info

  • Enzo: 9/15 through 10/8 vacation in Chile.
  • Terrence: 10/8-12, 10/29-11/2 at Kamioka.