==== Report for week of 3/5 ====
 * We removed the non-vacuum-compatible ballast mass from the BS tank.
 * We secured all the PR2 feedthrough connections with screws.
 * We grabbed an extra empty rack for SRM and set it up next to the one for SR3 (we will stuff them next week).
 * We calibrated the SR2 SF LVDT and FR.
 * We put the SF cap on and lifted and weighed the SF/... section.
 * We moved the filter building bench and tools into the SRM area and started the rebuild of the two remaining BFs (the one from the BS Test Hang and the one with the tilted keystone).
 * Mark finished -v2 of the schedule ([[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779| L1807779]]).
 * Mark worked on slides for the ASJ and LVC meetings.
 * Sawada-san postponed the SRM mushroom work to next week and offloaded it to Mirapro.
==== Report for weeks of 5/14, 5/21 ====
 * We weighted the IM/... section of the SR3.
 * We set up for the F0 blade prototype test.
 * Takahashi-san characterized the F0 prototype blades, and ordered final blades based on the BS and SR mass budgets.
 * Hirata-san characterized the LBB blades and identified three sets with blades of similar strength, plus two weaker ones. However he realized that M12x50 Bumax screws for the blade sets had not been ordered, so he got a new quote and ordered them for delivery 6/11.
 * Mirapro installed the mushroom section of the SRM tank.
 * We craned in the BF and cabled and tested the yaw pico, the FR stepper and the LVDT.
 * We hung the IM/... section from the BF, removed ≈200 g of trim mass and rearranged the rest to get the desired height, pitch and roll.
 * We added the sides of the IRM and the IM OSEMs, cabled the OSEMs, and adjusted everything to get good lateral and in/out alignment of the OSEMs.
 * Hirata-san organized getting the LBB damper rings into the SR3 tank. He joined the halves of the Cu and magnet rings and got them ready for craning (which will happen later when we have rebuilt the SR3 IP and have somewhere to park the lid of the vacuum chamber). However he encountered a problem with the top ring: one of the screw holes in the top of the tank is not fully threaded, so one of the pillars to support half of the ring cannot be attached. He is considering various options.
Line 17: Line 17:
==== Plan for week of ====
 * Shoda-san at Mitaka.
 * Hirata-san vacation Mon 3/5, then Kamioka
 * Fabian Mitaka Mon-Tue (COMSOL training), Kamioka Wed-Fri.
 * Others at Kamioka.
 * -
 * '''Remove LBB temporary ballast masses from BS chamber.'''
 * Finish recovering IM OSEM alignment.
 * Calibrate SF LVDT.
 * Lift SF/... section and check total mass and balance.
 * Get SRM tank mushroom section installed (Hirata-san, Kimura-san)
 * Set up for rebuilding of two BFs.

==== Plan for week of 3/12 ====
 * Shoda-san at Mitaka.
 * Mark at ASJ (Chiba) Fri, then Mitaka.
 * Hirata-san vacation Mon 3/5; Kamioka Tue-Thu; Mitaka Fri
 * Others Kamioka Mon-Thu
 * Install boxes in SR3 and SRM racks.
 * Lay SR3 in-air cabling.
 * Continue rebuild of BFs.

==== Plan for week of 3/19 ====
 * Mark at LVC meeting
 * All others at Mitaka
 * Make two sets of IM OSEMs
 * Make last in-air pico adapter cable
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM.
 * Set up Dummy BS prism removal.

==== Plan for week of 3/26 ====
 * Mark vacation.
 * Shoda-san at Mitaka
 * Others at Kamioka
 * --
 * F0 Prototype Blade Test
  * Characterize blades.
  * Choose best set of three.
  * Remove cracked blades from filter in SRM area.
  * Set up test weights in SRM area, first floor.
  * Remove floor panel in SRM area, second floor.
  * Install chosen blades.
  * Measure load capacity.
==== Plan for week of 5/28 ====
 * Mark, Enzo at Kamioka Mon-Fri.
 * Hirata-san at Kamioka Tue-Fri. (Mon is monthly Mitaka day.)
 * Kozu-kun at Kamioka Mon only. (Rest of week is job interviews.)
 
 * TBD.
==== Plan for week of 6/4 ====
 * Mark, Enzo, Hirata-san, Kozu-kun at Kamioka Tue-Fri. (Mon is medical checkup at Mitaka.)
 
 * TBD.
Line 69: Line 36:
 * Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
 * Hirata-san vacation, Mon 3/5.
 * Fabian vacation, 3/26-4/27 (then gone).

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for weeks of 5/14, 5/21

  • We weighted the IM/... section of the SR3.
  • We set up for the F0 blade prototype test.
  • Takahashi-san characterized the F0 prototype blades, and ordered final blades based on the BS and SR mass budgets.
  • Hirata-san characterized the LBB blades and identified three sets with blades of similar strength, plus two weaker ones. However he realized that M12x50 Bumax screws for the blade sets had not been ordered, so he got a new quote and ordered them for delivery 6/11.
  • Mirapro installed the mushroom section of the SRM tank.
  • We craned in the BF and cabled and tested the yaw pico, the FR stepper and the LVDT.
  • We hung the IM/... section from the BF, removed ≈200 g of trim mass and rearranged the rest to get the desired height, pitch and roll.
  • We added the sides of the IRM and the IM OSEMs, cabled the OSEMs, and adjusted everything to get good lateral and in/out alignment of the OSEMs.
  • Hirata-san organized getting the LBB damper rings into the SR3 tank. He joined the halves of the Cu and magnet rings and got them ready for craning (which will happen later when we have rebuilt the SR3 IP and have somewhere to park the lid of the vacuum chamber). However he encountered a problem with the top ring: one of the screw holes in the top of the tank is not fully threaded, so one of the pillars to support half of the ring cannot be attached. He is considering various options.

Plan for week of 5/28

  • Mark, Enzo at Kamioka Mon-Fri.
  • Hirata-san at Kamioka Tue-Fri. (Mon is monthly Mitaka day.)
  • Kozu-kun at Kamioka Mon only. (Rest of week is job interviews.)
  • TBD.

Plan for week of 6/4

  • Mark, Enzo, Hirata-san, Kozu-kun at Kamioka Tue-Fri. (Mon is medical checkup at Mitaka.)
  • TBD.

To-Do Lists, Schedule

Vacation Info

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)