Differences between revisions 245 and 275 (spanning 30 versions)
Revision 245 as of 2018-03-07 11:56:30
Size: 2552
Editor: MarkBarton
Comment:
Revision 275 as of 2018-04-06 14:20:35
Size: 2606
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 6: Line 6:
==== Report for week of 3/5 ====
 * We removed the non-vacuum-compatible ballast mass from the BS tank.
 * We secured all the PR2 feedthrough connections with screws.
 * We grabbed an extra empty rack for SRM and set it up next to the one for SR3 (we will stuff them next week).
 * We calibrated the SR2 SF LVDT and FR.
 * We put the SF cap on and lifted and weighed the SF/... section.
 * We moved the filter building bench and tools into the SRM area and started the rebuild of the two remaining BFs (the one from the BS Test Hang and the one with the tilted keystone).
 * Mark finished -v2 of the schedule ([[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779| L1807779]]).
 * Mark worked on slides for the ASJ and LVC meetings.
 * Sawada-san postponed the SRM mushroom work to next week and offloaded it to Mirapro.
 * ?? Finish recovering IM OSEM alignment.
==== Report for week of 4/2 ====
Line 18: Line 8:
==== Plan for week of 3/12 ====
 * Shoda-san at Mitaka.
 * Mark at ASJ (Chiba) Fri, then Mitaka.
 * Hirata-san vacation Mon 3/5; Kamioka Tue-Thu; Mitaka Fri
 * Others Kamioka Mon-Thu
 * F2F VIS Meeting and Farewell Party for Fabian at Mitaka on Friday.
 * --
 * Install boxes in SR3 and SRM racks.
 * Lay SR3 in-air cabling.
 * Continue rebuild of BFs.
 * Fujii-kun and Yamamoto-kun got the SR3 real time model running.
 * We received the SR3.
 * However Mark and Tanioka-kun found Hirose-san had applied the First Contact patterns on the wrong sides, so we took it to Yamamoto-san's lab and Toyama University and re-applied the FC properly. We also bounced a 1064 nm beam off it to verify that the HR and AR coatings were not also swapped (they were OK).
 * We made magnet-standoff assemblies for both SR3 and SRM, and set up for gluing the prisms and magnets. We will attach the prisms and magnet-standoffs on Monday.
 * Hirata-san did inventory of the SR3/SRM payload parts received last week and started on the inventory of screws.
 * Fujii-kun, Enzo and team finished the preparation, adjustment of the SFs and BFs.
 * They calibrated one SF and BF. (The remaining one SF and BF will take about another day. Also, the FR stops need to be checked.)
 * Enzo and Kozu-kun finished setting up the SR3 and SRM racks. (The SRM rack still lacks a front-end, and power and network connections, but the SR3 is now ready for testing.)
 * Shoda-san worked on getting quotes for the ballast masses, on design of the SRM metal mass, and on splitting the BS model to reduce the load on the front-end computer.
Line 29: Line 18:
==== Plan for week of 3/19 ====
 * Mark at LVC meeting
 * All others at Mitaka
 * --
 * Make two sets of IM OSEMs
 * Make last in-air pico adapter cable
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM.
 * Set up Dummy BS prism removal.

==== Plan for week of 3/26 ====
 * Mark vacation.
==== Plan for week of 4/9 ====
Line 41: Line 20:
 * Fujii-san at Mitaka
 * Tanioka-san at Kamioka, but possibly doing PEM stuff.
Line 43: Line 24:
 * F0 Prototype Blade Test
  * Characterize blades.
  * Choose best set of three.
  * Remove cracked blades from filter in SRM area.
  * Set up test weights in SRM area, first floor.
  * Remove floor panel in SRM area, second floor.
  * Install chosen blades.
  * Measure load capacity.
 * Finish SRM BF and SF calibration
 * Finish IMs and IRMs
 * Glue SR3 mirror

==== Plan for week of 4/16 ====
 * Shoda-san at Mitaka
 * Fujii-san at Mitaka
 * Tanioka-san at Mitaka?
 * Others at Kamioka
 * --
 * Build 1xRM
 * Start SR3 Hang
  * Align assembly frame.

==== Plan for week of 4/23 ====
 * Shoda-san at Mitaka
 * Fujii-san at Mitaka?
 * Mark, Enzo at Kamioka
 * Hirata-san at Mitaka
 * Tanioka-san at Mitaka?
 * --
 * Clean parts (cable clamp bases, etc, etc).
 * Observe KAGRA Phase 1 operations, assist if problems arise.

==== Plan for week of 4/30 ====
  * Golden Week!
Line 60: Line 59:
 * Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
 * Hirata-san vacation, Mon 3/5.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 4/2

  • Fujii-kun and Yamamoto-kun got the SR3 real time model running.
  • We received the SR3.
  • However Mark and Tanioka-kun found Hirose-san had applied the First Contact patterns on the wrong sides, so we took it to Yamamoto-san's lab and Toyama University and re-applied the FC properly. We also bounced a 1064 nm beam off it to verify that the HR and AR coatings were not also swapped (they were OK).
  • We made magnet-standoff assemblies for both SR3 and SRM, and set up for gluing the prisms and magnets. We will attach the prisms and magnet-standoffs on Monday.
  • Hirata-san did inventory of the SR3/SRM payload parts received last week and started on the inventory of screws.
  • Fujii-kun, Enzo and team finished the preparation, adjustment of the SFs and BFs.
  • They calibrated one SF and BF. (The remaining one SF and BF will take about another day. Also, the FR stops need to be checked.)
  • Enzo and Kozu-kun finished setting up the SR3 and SRM racks. (The SRM rack still lacks a front-end, and power and network connections, but the SR3 is now ready for testing.)
  • Shoda-san worked on getting quotes for the ballast masses, on design of the SRM metal mass, and on splitting the BS model to reduce the load on the front-end computer.

Plan for week of 4/9

  • Shoda-san at Mitaka
  • Fujii-san at Mitaka
  • Tanioka-san at Kamioka, but possibly doing PEM stuff.
  • Others at Kamioka
  • --
  • Finish SRM BF and SF calibration
  • Finish IMs and IRMs
  • Glue SR3 mirror

Plan for week of 4/16

  • Shoda-san at Mitaka
  • Fujii-san at Mitaka
  • Tanioka-san at Mitaka?
  • Others at Kamioka
  • --
  • Build 1xRM
  • Start SR3 Hang
    • Align assembly frame.

Plan for week of 4/23

  • Shoda-san at Mitaka
  • Fujii-san at Mitaka?
  • Mark, Enzo at Kamioka
  • Hirata-san at Mitaka
  • Tanioka-san at Mitaka?
  • --
  • Clean parts (cable clamp bases, etc, etc).
  • Observe KAGRA Phase 1 operations, assist if problems arise.

Plan for week of 4/30

  • Golden Week!

To-Do Lists, Schedule

Vacation Info

  • Fabian vacation, 3/26-4/27 (then gone).

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)