==== Report for week of 3/5 ====
 * Mark finished -v2 of the schedule ([[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779| L1807779]]).
 * We removed the non-vacuum-compatible ballast mass from the BS tank.
 * We secured all the PR2 feedthrough connections with screws.
 * We grabbed an extra empty rack for SRM and set it up next to the one for SR3 (we will add boxes next week).
 * We calibrated the SR2 SF LVDT sensing and actuation, and the FR.
 * We measured the bounce frequencies of the SF with and without the cap, and the bounce frequency of the BF.
 * We put the SF cap on and lifted and weighed the SF/... section.
 * However we were unhappy with how the cap had to be forced on and off and how it lowered the load capacity (≈-433 g) and resonance frequency (0.271 Hz-> 0.23 Hz).
 * We tried the cap left over from B2-3 used in one of the PRs, which was slightly better but still not great.
 * We measured diameter of the original cap (B2-2) and the new one (B2-3). The original cap was almost exactly 700 mm in internal diameter, and the new one was about 0.2 mm wider.
 * We moved the filter building bench and tools into the SRM area and started the rebuild of the two remaining BFs (the one from the BS Test Hang and the one with the tilted keystone).
 * Mark worked on slides for the ASJ and LVC meetings.
 * The SRM mushroom work was postponed due to other demands on the time of Sawada-san-tachi and Mirapro.
==== Report for week of 4/23 ====
 * We hung the optic and set its pitch. The winch system had a lot of slop in it but the technique of relaxing the wires by lifting the optic on the EQ stops was effective in getting consistent results.
 * We tightened the clamps using a torque wrench, using settings of 5 N.m for the primary clamps and 20 N.m for the secondary.
 * We hung the RM and set its pitch. The RM winches were a lot more consistent.
 * However when tightening the clamps, the wire on the +Y side broke at the bottom edge of primary clamp. The wire on the -Y held, so the RM dropped a few mm onto the trolley on the +Y side.
 * We raised the RM trolley to support the RM and left the optic hanging inside it overnight as a safety test.
 * We then reversed the usual installation procedure to remove the RM and get the mirror box around the optic. We used clamp pieces as spacers to bridge the gaps created by the fact that the optic had been raised 3 mm during hanging and could not safely be lowered. We then cut the wires, leaving the op
 * Shoda-san made SRM model (Dropbox/Largefiles/Subsystems/VIS/Design/SR/Model/SRM-MetalMass_180426)
 * Shoda-san made 2D drawings of LBB ballast masses
 * Hirata-san washed parts.
==== Control Issues ====
 * Resonant frequency table is ready for BS ([[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/TypeB/BSdetail|BS suspension details]])
 * We found the inconsistency between local damping measurement and interferometer measurement. ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=4811|klog4811]])
  The TF gains from IML to TML, and from TML to TML are different from the interferometer measurement.
Line 21: Line 21:
==== Plan for week of 3/12 ====   * I checked the TML gain, which are calculated from TMP and TMY measurements, and found EUL2COIL matrix was different from what I supposed.
   --> Fixed it and updated the state space model. Might be OK now for TF from TML to TML. (Komori-kun will check it.)
  * I checked the calibration gain of OSEMs and found that the measured values are not used. But it makes only small difference.
  * Compare the TFs from BFGAS to BFGAS and BFGAS to IMV, and they are inconsistent for BS and PR2. (No data found for PR3)([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=4807|klog4807]])
  * Comparing TFs from IMP to TMP and from IMY to TMY also helps to check the OSEM calibration by comparing OSEM signals and Oplev signals.
   Found the matrix to convert OSEM signals (um) to pitch (urad) is different from what I calculated. To be checked.
   The measurement will be done after phase-I.

 * Constructing the tool to implement the current filterbank information to state space model.

==== Plan for week of 4/30 ====
Line 23: Line 33:
 * Mark at ASJ (Chiba) Fri, then Mitaka.
 * Others Kamioka Mon-Thu
 * F2F VIS Meeting and Farewell Party for Fabian at Mitaka on Friday.
 * Mark, Enzo at Kamioka Mon-Wed or TBD.
 * Others having fun doing Golden Week stuff.
Line 27: Line 36:
 * Install boxes in SR3 and SRM racks.
 * Lay SR3 in-air cabling.
 * Continue rebuild of BFs.
 * Ship dummy BS to Mitaka.
 * Observe KAGRA Phase 1 operations, assist if problems arise.
 * Do BF TFs.
Line 32: Line 39:
==== Plan for week of 3/19 ====
 * Fujii-kun and Tanioka-kun join.
 * Mark at LVC meeting
 * Fujii-kun at Kamioka
 * All others at Mitaka
==== Plan for week of 5/7 ====
 * Shoda-san at Mitaka.
 * E
nzo at Kamioka from Tue.
 * Mark, Hirata-san at Kamioka full week.
 * Kozu-kun at Kamioka??
 * Tanioka-kun at Kamioka Mon, Tue.
Line 38: Line 46:
 * Put four geophones in pods.
 * Make two sets of IM OSEMs
 * Make last in-air pico adapter cable
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM.
 * Set up Dummy BS prism removal.
 * Continue SR3 Hang
  * Inspect clamps and decide whether to reuse or swap in clamps from SRM IM.
  * Rehang optic.
  * Rehang RM.
  * Cable RM OSEMs.
 * Prepare for filter testing
  * Remove cracked blades from F0 #1 and #3.
  * Remove floor panel in SR3 area.
  * Set up filter building trolley with crossbars, jacks and F0 test masses.
 
 * Etc
  * Test prototype SR3 safety bar, and set up second safety bar.
  * Negotiate with Mirapro to get SRM mushroom installed, avoiding 5/15.
Line 44: Line 60:

==== Plan for week of 3/26 ====
 * Mark vacation.
 * Shoda-san at Mitaka
 * Others at Kamioka
 * --
 * SF Check
  * Check load capacity.
  * Check fit of caps.
  * Add cable clamps to bases.
  * Add cable clamps and Cu segments to caps (only if they fit well).
  * Cable LVDTs and steppers.
Line 65: Line 69:
 * Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
 * Hirata-san vacation, Mon 3/5.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 4/23

  • We hung the optic and set its pitch. The winch system had a lot of slop in it but the technique of relaxing the wires by lifting the optic on the EQ stops was effective in getting consistent results.
  • We tightened the clamps using a torque wrench, using settings of 5 N.m for the primary clamps and 20 N.m for the secondary.
  • We hung the RM and set its pitch. The RM winches were a lot more consistent.
  • However when tightening the clamps, the wire on the +Y side broke at the bottom edge of primary clamp. The wire on the -Y held, so the RM dropped a few mm onto the trolley on the +Y side.
  • We raised the RM trolley to support the RM and left the optic hanging inside it overnight as a safety test.
  • We then reversed the usual installation procedure to remove the RM and get the mirror box around the optic. We used clamp pieces as spacers to bridge the gaps created by the fact that the optic had been raised 3 mm during hanging and could not safely be lowered. We then cut the wires, leaving the op
  • Shoda-san made SRM model (Dropbox/Largefiles/Subsystems/VIS/Design/SR/Model/SRM-MetalMass_180426)

  • Shoda-san made 2D drawings of LBB ballast masses
  • Hirata-san washed parts.

Control Issues

  • Resonant frequency table is ready for BS (BS suspension details)

  • We found the inconsistency between local damping measurement and interferometer measurement. (klog4811)

    • The TF gains from IML to TML, and from TML to TML are different from the interferometer measurement.
    • I checked the TML gain, which are calculated from TMP and TMY measurements, and found EUL2COIL matrix was different from what I supposed.
      • --> Fixed it and updated the state space model. Might be OK now for TF from TML to TML. (Komori-kun will check it.)

    • I checked the calibration gain of OSEMs and found that the measured values are not used. But it makes only small difference.
    • Compare the TFs from BFGAS to BFGAS and BFGAS to IMV, and they are inconsistent for BS and PR2. (No data found for PR3)(klog4807)

    • Comparing TFs from IMP to TMP and from IMY to TMY also helps to check the OSEM calibration by comparing OSEM signals and Oplev signals.
      • Found the matrix to convert OSEM signals (um) to pitch (urad) is different from what I calculated. To be checked. The measurement will be done after phase-I.
  • Constructing the tool to implement the current filterbank information to state space model.

Plan for week of 4/30

  • Shoda-san at Mitaka.
  • Mark, Enzo at Kamioka Mon-Wed or TBD.
  • Others having fun doing Golden Week stuff.
  • --
  • Observe KAGRA Phase 1 operations, assist if problems arise.
  • Do BF TFs.

Plan for week of 5/7

  • Shoda-san at Mitaka.
  • Enzo at Kamioka from Tue.
  • Mark, Hirata-san at Kamioka full week.
  • Kozu-kun at Kamioka??
  • Tanioka-kun at Kamioka Mon, Tue.
  • --
  • Continue SR3 Hang
    • Inspect clamps and decide whether to reuse or swap in clamps from SRM IM.
    • Rehang optic.
    • Rehang RM.
    • Cable RM OSEMs.
  • Prepare for filter testing
    • Remove cracked blades from F0 #1 and #3.
    • Remove floor panel in SR3 area.
    • Set up filter building trolley with crossbars, jacks and F0 test masses.
  • Etc
    • Test prototype SR3 safety bar, and set up second safety bar.
    • Negotiate with Mirapro to get SRM mushroom installed, avoiding 5/15.

To-Do Lists, Schedule

Vacation Info

  • Fabian vacation, 3/26-4/27 (then gone).