==== Report for week of 3/5 ====
 * Mark finished -v2 of the schedule ([[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779| L1807779]]).
 * We removed the non-vacuum-compatible ballast mass from the BS tank.
 * We secured all the PR2 feedthrough connections with screws.
 * We grabbed an extra empty rack for SRM and set it up next to the one for SR3 (we will add boxes next week).
 * We calibrated the SR2 SF LVDT sensing and actuation, and the FR.
 * We measured the bounce frequencies of the SF with and without the cap, and the bounce frequency of the BF.
 * We put the SF cap on and lifted and weighed the SF/... section.
 * However we were unhappy with how the cap had to be forced on and off and how it lowered the load capacity (≈-433 g) and resonance frequency (0.271 Hz-> 0.23 Hz).
 * We tried the cap left over from B2-3 used in one of the PRs, which was slightly better but still not great.
 * We measured diameter of the original cap (B2-2) and the new one (B2-3). The original cap was almost exactly 700 mm in internal diameter, and the new one was about 0.2 mm wider.
 * We moved the filter building bench and tools into the SRM area and started the rebuild of the two remaining BFs (the one from the BS Test Hang and the one with the tilted keystone).
 * Mark worked on slides for the ASJ and LVC meetings.
 * The SRM mushroom work was postponed due to other demands on the time of Sawada-san-tachi and Mirapro.

==== Plan for week of 3/12 ====
 * Shoda-san at Mitaka.
 * Mark at ASJ (Chiba) Fri, then Mitaka.
 * Others Kamioka Mon-Thu
 * F2F VIS Meeting and Farewell Party for Fabian at Mitaka on Friday.
 * --
 * Install boxes in SR3 and SRM racks.
 * Lay SR3 in-air cabling.
 * Continue rebuild of BFs.
 * Ship dummy BS to Mitaka.

==== Plan for week of 3/19 ====
 * Fujii-kun and Tanioka-kun join.
 * Mark at LVC meeting
 * Fujii-kun at Kamioka
 * All others at Mitaka
 * --
 * Put four geophones in pods.
 * Make two sets of IM OSEMs
 * Make last in-air pico adapter cable
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM.
 * Set up Dummy BS prism removal.
==== Report for week of 6/18 ====
 * We powered down the Type B racks as a precaution against possible loss of power during work on Tuesday, and later powered them up again.
 * We put a flange cover over the hole in the floor near the filter tuning area as a temporary safety measure. We later managed to entirely close the part of the hole that was not covered by the filter, by moving the filter towards the outside and using short floor panels from SR2 on the tank side.
 * We removed the SR3 PI from the filter tuning area and brought in the SR2 one.
 * We put magnets on the SR damper magnet ring to match the two Cu segments we were using.
 * We craned the SR3 PI into the AF, connected it to the security structure, and hooked the SF/... section and the SF damper magnet ring.
 * At first the F0 did not rise, and we realized that we had 2 kg less margin than we originally thought because we had not allowed for the PI-SF rod receptacle, the top disk which holds the yaw stepper mechanism, or the stepper itself.
 * However we were able to try the redesigned PI fishing rod, parts for which had just arrived. The optional strong CuBe spring in the new arrangement gave plenty of extra lift, so that we now have about 5 kg of margin. We did have to move the yoke to work around the problem that the CuBe spring tends to tilt the keystone, but we got it moving freely. We will also have to compress the blades some more to compensate for the extra stiffness, which caused the frequency to rise from 0.5 Hz to 0.9 Hz.
Line 45: Line 16:
==== Plan for week of 3/26 ====
 * Mark vacation.
 * Shod
a-san at Mitaka
 * Oth
ers at Kamioka
==== Plan for week of 7/2 ====
 * Mark, Hirata-san, Terrence at Kamioka Mon-Fri.
 * Enzo at Kamioka Mon-Wed.
 * Kozu-kun at Kamioka except Wed.
Line 50: Line 21:
 * SF Check
  * Check load capacity.
  * Check fit of caps.
  * Add cable clamps to bases.
  * Add cable clamps and Cu segments to caps (only if they fit well).
  * Cable LVDTs and steppers.
 * Continued tuning of filter in PI #3 for SR3.
 * Building and tuning of filter in PI #1 for SR2 (time permitting).
 * Lots of cable routing and testing.
 * Install geophones and arc weights.

==== Plan for week of 7/9 ====
 * Mark, Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Mon-Fri.
 * --
 * Lock suspension.
 * Remove tank lid and raise LBB damper rings.
 * Crane suspension into tank.
Line 58: Line 34:
 * [[KAGRA/Subgroups/VIS/TypeB/March2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/April2018]]
Line 62: Line 36:
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]  * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]
Line 65: Line 39:
 * Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
 * Hirata-san vacation, Mon 3/5.
 * Fabian vacation, 3/26-4/27 (then gone).
 * Kozu-kun: 7/4 Tokyo.
 * Enzo: 7/5-6 NAOJ Party, Mitaka.
 * Terrence: 8/24-26 f2f, then returns to Hong Kong.
 * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 6/18

  • We powered down the Type B racks as a precaution against possible loss of power during work on Tuesday, and later powered them up again.
  • We put a flange cover over the hole in the floor near the filter tuning area as a temporary safety measure. We later managed to entirely close the part of the hole that was not covered by the filter, by moving the filter towards the outside and using short floor panels from SR2 on the tank side.
  • We removed the SR3 PI from the filter tuning area and brought in the SR2 one.
  • We put magnets on the SR damper magnet ring to match the two Cu segments we were using.
  • We craned the SR3 PI into the AF, connected it to the security structure, and hooked the SF/... section and the SF damper magnet ring.
  • At first the F0 did not rise, and we realized that we had 2 kg less margin than we originally thought because we had not allowed for the PI-SF rod receptacle, the top disk which holds the yaw stepper mechanism, or the stepper itself.
  • However we were able to try the redesigned PI fishing rod, parts for which had just arrived. The optional strong CuBe spring in the new arrangement gave plenty of extra lift, so that we now have about 5 kg of margin. We did have to move the yoke to work around the problem that the CuBe spring tends to tilt the keystone, but we got it moving freely. We will also have to compress the blades some more to compensate for the extra stiffness, which caused the frequency to rise from 0.5 Hz to 0.9 Hz.

Plan for week of 7/2

  • Mark, Hirata-san, Terrence at Kamioka Mon-Fri.
  • Enzo at Kamioka Mon-Wed.
  • Kozu-kun at Kamioka except Wed.
  • --
  • Continued tuning of filter in PI #3 for SR3.
  • Building and tuning of filter in PI #1 for SR2 (time permitting).
  • Lots of cable routing and testing.
  • Install geophones and arc weights.

Plan for week of 7/9

  • Mark, Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Mon-Fri.
  • --
  • Lock suspension.
  • Remove tank lid and raise LBB damper rings.
  • Crane suspension into tank.

To-Do Lists, Schedule

Vacation Info

  • Kozu-kun: 7/4 Tokyo.
  • Enzo: 7/5-6 NAOJ Party, Mitaka.
  • Terrence: 8/24-26 f2f, then returns to Hong Kong.
  • Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.