==== Report for week of 3/5 ====
 * Mark finished -v2 of the schedule ([[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779| L1807779]]).
 * We removed the non-vacuum-compatible ballast mass from the BS tank.
 * We secured all the PR2 feedthrough connections with screws.
 * We grabbed an extra empty rack for SRM and set it up next to the one for SR3 (we will add boxes next week).
 * We calibrated the SR2 SF LVDT sensing and actuation, and the FR.
 * We measured the bounce frequencies of the SF with and without the cap, and the bounce frequency of the BF.
 * We put the SF cap on and lifted and weighed the SF/... section.
 * However we were unhappy with how the cap had to be forced on and off and how it lowered the load capacity (≈-433 g) and resonance frequency (0.271 Hz-> 0.23 Hz).
 * We tried the cap left over from B2-3 used in one of the PRs, which was slightly better but still not great.
 * We measured diameter of the original cap (B2-2) and the new one (B2-3). The original cap was almost exactly 700 mm in internal diameter, and the new one was about 0.2 mm wider.
 * We moved the filter building bench and tools into the SRM area and started the rebuild of the two remaining BFs (the one from the BS Test Hang and the one with the tilted keystone).
 * Mark worked on slides for the ASJ and LVC meetings.
 * The SRM mushroom work was postponed due to other demands on the time of Sawada-san-tachi and Mirapro.
==== Report for week of 9/17 ====
 * Monday 9/17 was holiday.
 * We optimized the trim mass on the SF to get more balance torque with less total mass. We now have a reserve of 480 g for the yaw pico.
 * We set the SF damper gap to 6 mm.
 * We set the SR2 pitch with the optic lever, aligned the IRM and set all the OSEMs to have good clearance and midrange output.
 * We locked the SR2 suspension (except for the SF) and craned it into the tank.
 * We moved the vacuum feedthroughs over to the tank.
 * With help from Ohishi-san, we removed the First Contact from SR2.
 * Mark did an audit of all the electronics boxes and updated the item list and S-number file cards on JGWDoc.
 * Mark did an inventory of some thin arc weights and finalized the number to order (8*38 mm + 9*10 mm).
 * Panwei copied control filters over from the SR3.
 
==== Plan for week of 9/24 ====
 * Monday 9/17 is holiday (Respect for the Aged Day).
 * Enzo on vacation.
 * Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri.
===== SR2 =====
 * Remove First Contact.
 * Move SR2 in-air cables.
 * Unlock and realign suspension.
===== SRM =====
 * Set pitch of SRM and RM, tighten clamps, remove winch system.
 * Weigh IM/... section.
 * Build up SS to BF level.
 * Add BF.
Line 21: Line 32:
==== Plan for week of 3/12 ====
 * Shoda-san at Mitaka.
 * Mark at ASJ (Chiba) Fri, then Mitaka.
 * Others Kamioka Mon-Thu
 * F2F VIS Meeting and Farewell Party for Fabian at Mitaka on Friday.
 * --
 * Install boxes in SR3 and SRM racks.
 * Lay SR3 in-air cabling.
 * Continue rebuild of BFs.
 * Ship dummy BS to Mitaka.

==== Plan for week of 3/19 ====
 * Fujii-kun and Tanioka-kun join.
 * Mark at LVC meeting
 * Fujii-kun at Kamioka
 * All others at Mitaka
 * --
 * Put four geophones in pods.
 * Make two sets of IM OSEMs
 * Make last in-air pico adapter cable
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM.
 * Set up Dummy BS prism removal.


==== Plan for week of 3/26 ====
 * Mark vacation.
 * Shoda-san at Mitaka
 * Others at Kamioka
 * --
 * SF Check
  * Check load capacity.
  * Check fit of caps.
  * Add cable clamps to bases.
  * Add cable clamps and Cu segments to caps (only if they fit well).
  * Cable LVDTs and steppers.
==== Plan for week of 9/24 ====
 * Monday 9/24 is holiday (Autumn Equinox).
 * Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri.
 * Suspend IM and tweak height/balance.
===== SRM =====
 * Cable/test BF.
 * Install IRM.
 * Install/cable/test IM OSEMs.
Line 58: Line 42:
 * [[KAGRA/Subgroups/VIS/TypeB/March2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/April2018]]
Line 62: Line 44:
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]  * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]
Line 65: Line 47:
 * Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
 * Hirata-san vacation, Mon 3/5.
 * Fabian vacation, 3/26-4/27 (then gone).
 * Mark: 9/10-14 (job interview in US).
 * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 9/17

  • Monday 9/17 was holiday.
  • We optimized the trim mass on the SF to get more balance torque with less total mass. We now have a reserve of 480 g for the yaw pico.
  • We set the SF damper gap to 6 mm.
  • We set the SR2 pitch with the optic lever, aligned the IRM and set all the OSEMs to have good clearance and midrange output.
  • We locked the SR2 suspension (except for the SF) and craned it into the tank.
  • We moved the vacuum feedthroughs over to the tank.
  • With help from Ohishi-san, we removed the First Contact from SR2.
  • Mark did an audit of all the electronics boxes and updated the item list and S-number file cards on JGWDoc.
  • Mark did an inventory of some thin arc weights and finalized the number to order (8*38 mm + 9*10 mm).
  • Panwei copied control filters over from the SR3.

Plan for week of 9/24

  • Monday 9/17 is holiday (Respect for the Aged Day).
  • Enzo on vacation.
  • Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri.

SR2
  • Remove First Contact.
  • Move SR2 in-air cables.
  • Unlock and realign suspension.

SRM
  • Set pitch of SRM and RM, tighten clamps, remove winch system.
  • Weigh IM/... section.
  • Build up SS to BF level.
  • Add BF.

Plan for week of 9/24

  • Monday 9/24 is holiday (Autumn Equinox).
  • Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri.
  • Suspend IM and tweak height/balance.

SRM
  • Cable/test BF.
  • Install IRM.
  • Install/cable/test IM OSEMs.

To-Do Lists, Schedule

Vacation Info

  • Mark: 9/10-14 (job interview in US).
  • Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.