==== Report for week of 3/12 ====
 * We helped Mirapro close up the BS tank, and did last minute checks and adjustments, including using the fishing rods to reset the GAS keystones to mid-range according to the LVDTs. (The F0 had risen so far (≈7 mm) due to temperature changes that it was touching the upper keystone stop screws and defeating the vibration isolation. We operated the F0 FR manually while the tank lid was off.)
 * We installed electronic boxes in the SR3 and SRM racks. Rack internal cabling and in-air cabling to SR3 still needs to be done.
 * Hirata-san disassembled two BFs (one SF BF with a tilted keystone and the BS Test Hang BF) and characterized all 10 available SR BF blades. He found they fell into a group of 6 strong ones and a group of 4 weak ones, so he divided the 6 into two matched sets and rebuilt the two filters.
 * We noticed that the bottom level of SR2 suspension had developed a significant yaw (enough to foul on the security structure), probably introduced when we picked the chain up to weigh it, so we lifted the suspension again and corrected it.
 * We aligned the SR2 ready for TFs. We noticed that the IM/... section had a noticeable roll (≈20 mrad) but we were unable to correct it with the IM roll pico (the pico runs but the roll does not change, probably because there is too much friction for the mass return spring). We will see if the TFs look OK and then decide whether to try correcting the roll.
 * We gathered items for OSEM assembly by Enzo, Shoda-san and others at Mitaka next week, and for geophone assembly by Fujii-kun and Kozu-kun at Kamioka. Hirata-san ordered some M8x35 screws that we didn't have enough of.
 * We took delivery of the blade bases for the LBB dampers.
 * Hirata-san packed up two SF caps (the original one from the SR2 SF) and a spare, for remachining by Mirapro. He also packed up the dummy BS for shipment to Mitaka for soaking off the sapphire prisms.
==== Report for week of 4/2 ====
Line 16: Line 8:
==== Plan for week of 3/19 ====
 * Fujii-kun and Tanioka-kun join.
 * Mark at LVC meeting
 * Fujii-kun at Kamioka (including Wed 3/21)
 * Kozu-kun at Kamioka Mon-Tue.
 * All others at Mitaka
 * --
 * Put four geophones in pods.
 * Make two sets of IM OSEMs
 * Make last in-air pico adapter cable
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM.
 * Set up Dummy BS prism removal.
 * Fujii-kun and Yamamoto-kun got the SR3 real time model running.
 * We received the SR3.
 * However Mark and Tanioka-kun found Hirose-san had applied the First Contact patterns on the wrong sides, so we took it to Yamamoto-san's lab and Toyama University and re-applied the FC properly. We also bounced a 1064 nm beam off it to verify that the HR and AR coatings were not also swapped (they were OK).
 * We made magnet-standoff assemblies for both SR3 and SRM, and set up for gluing the prisms and magnets. We will attach the prisms and magnet-standoffs on Monday.
 * Hirata-san did inventory of the SR3/SRM payload parts received last week and started on the inventory of screws.
 * Fujii-kun, Enzo and team finished the preparation, adjustment of the SFs and BFs.
 * They calibrated one SF and BF. (The remaining one SF and BF will take about another day. Also, the FR stops need to be checked.)
 * Enzo and Kozu-kun finished setting up the SR3 and SRM racks. (The SRM rack still lacks a front-end, and power and network connections, but the SR3 is now ready for testing.)
 * Shoda-san worked on getting quotes for the ballast masses, on design of the SRM metal mass, and on splitting the BS model to reduce the load on the front-end computer.
Line 29: Line 18:
==== Plan for week of 3/26 ====
 * Mark vacation.
==== Plan for week of 4/9 ====
Line 32: Line 20:
 * Fujii-san at Mitaka
 * Tanioka-san at Kamioka, but possibly doing PEM stuff.
Line 34: Line 24:
 * Lay SR3 in-air cabling.
 * Finish rebuild of second BF.
 * SF Check
  * Check load capacity.
  * Check fit of caps.
  * Add cable clamps to bases.
  * Add cable clamps and Cu segments to caps (only if they fit well).
  * Cable LVDTs and steppers.
 * Finish SRM BF and SF calibration
 * Finish IMs and IRMs
 * Glue SR3 mirror

==== Plan for week of 4/16 ====
 * Shoda-san at Mitaka
 * Fujii-san at Mitaka
 * Tanioka-san at Mitaka?
 * Others at Kamioka
 * --
 * Build 1xRM
 * Start SR3 Hang
  * Align assembly frame.

==== Plan for week of 4/23 ====
 * Shoda-san at Mitaka
 * Fujii-san at Mitaka?
 * Mark, Enzo at Kamioka
 * Hirata-san at Mitaka
 * Tanioka-san at Mitaka?
 * --
 * Clean parts (cable clamp bases, etc, etc).
 * Observe KAGRA Phase 1 operations, assist if problems arise.

==== Plan for week of 4/30 ====
  * Golden Week!
Line 51: Line 59:
 * Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
 * Hirata-san vacation, Mon 3/5.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 4/2

  • Fujii-kun and Yamamoto-kun got the SR3 real time model running.
  • We received the SR3.
  • However Mark and Tanioka-kun found Hirose-san had applied the First Contact patterns on the wrong sides, so we took it to Yamamoto-san's lab and Toyama University and re-applied the FC properly. We also bounced a 1064 nm beam off it to verify that the HR and AR coatings were not also swapped (they were OK).
  • We made magnet-standoff assemblies for both SR3 and SRM, and set up for gluing the prisms and magnets. We will attach the prisms and magnet-standoffs on Monday.
  • Hirata-san did inventory of the SR3/SRM payload parts received last week and started on the inventory of screws.
  • Fujii-kun, Enzo and team finished the preparation, adjustment of the SFs and BFs.
  • They calibrated one SF and BF. (The remaining one SF and BF will take about another day. Also, the FR stops need to be checked.)
  • Enzo and Kozu-kun finished setting up the SR3 and SRM racks. (The SRM rack still lacks a front-end, and power and network connections, but the SR3 is now ready for testing.)
  • Shoda-san worked on getting quotes for the ballast masses, on design of the SRM metal mass, and on splitting the BS model to reduce the load on the front-end computer.

Plan for week of 4/9

  • Shoda-san at Mitaka
  • Fujii-san at Mitaka
  • Tanioka-san at Kamioka, but possibly doing PEM stuff.
  • Others at Kamioka
  • --
  • Finish SRM BF and SF calibration
  • Finish IMs and IRMs
  • Glue SR3 mirror

Plan for week of 4/16

  • Shoda-san at Mitaka
  • Fujii-san at Mitaka
  • Tanioka-san at Mitaka?
  • Others at Kamioka
  • --
  • Build 1xRM
  • Start SR3 Hang
    • Align assembly frame.

Plan for week of 4/23

  • Shoda-san at Mitaka
  • Fujii-san at Mitaka?
  • Mark, Enzo at Kamioka
  • Hirata-san at Mitaka
  • Tanioka-san at Mitaka?
  • --
  • Clean parts (cable clamp bases, etc, etc).
  • Observe KAGRA Phase 1 operations, assist if problems arise.

Plan for week of 4/30

  • Golden Week!

To-Do Lists, Schedule

Vacation Info

  • Fabian vacation, 3/26-4/27 (then gone).