==== Report for week of 3/12 ====
 * We helped Mirapro close up the BS tank, and did last minute checks and adjustments, including using the fishing rods to reset the GAS keystones to mid-range according to the LVDTs. (The F0 had risen so far (≈7 mm) due to temperature changes that it was touching the upper keystone stop screws and defeating the vibration isolation. We operated the F0 FR manually while the tank lid was off.)
 * We installed electronic boxes in the SR3 and SRM racks. Enzo set the phases and gains on the LVDT drivers for both racks. Rack internal cabling and in-air cabling to SR3 still needs to be done.
 * Hirata-san disassembled two BFs (one SF BF with a tilted keystone and the BS Test Hang BF) and characterized all 10 available SR BF blades. He found they fell into a group of 6 strong ones and a group of 4 weak ones, so he divided the 6 into two matched sets and rebuilt the two filters.
 * We noticed that the bottom level of SR2 suspension had developed a significant yaw (enough to foul on the security structure), probably introduced when we picked the chain up to weigh it, so we lifted the suspension again and corrected it.
 * We aligned the SR2 ready for TFs. We noticed that the IM/... section had a noticeable roll (≈20 mrad) but we were unable to correct it with the IM roll pico (the pico runs but the roll does not change, probably because there is too much friction for the mass return spring). We will see if the TFs look OK and then decide whether to try correcting the roll.
 * We gathered items for OSEM assembly by Enzo, Shoda-san and others at Mitaka next week, and for geophone assembly by Fujii-kun and Kozu-kun at Kamioka. Hirata-san ordered some M8x35 screws that we didn't have enough of.
 * We took delivery of the blade bases for the LBB dampers.
 * Hirata-san packed up two SF caps (the original one from the SR2 SF) and a spare, for remachining by Mirapro. He also packed up the dummy BS and arranged for Ishizaki-san to take it to Mitaka for soaking off of the sapphire prisms.
==== Report for week of 10/8 ====
 * This was Panwei's last week (for now at least) - thanks for all the help!
 * Thanks also to Terrence for visiting again for the week.
===== SR3 =====
 * Terrence and Mark finished setting up the LEN half of the OL (Simon had roughly placed the components). They ran a new cable for LEN in the cable tray and relaid the cable for TILT to get it off the floor.
 * Terrence worked on diagonalizing the LEN OL. A report is forthcoming.
===== SRM =====
 * Mark installed a pair of power supplies in the SRM and copied settings across to the SRM real-time model.
 * Fabian did lots of rack cabling, including installing and connecting BIO cards.
 * Mark and Hirata-san checked and adjusted the pitch of the BF (with a bubble level) and the IM/... section (with the OL).
 * Mark and Panwei installed the sides of the IRM and the IM OSEMs.
 * Hirata-san hung the dummy load from the F0 and started compressing the blade. There was a significant lateral offset (≈2-3 mm towards the blade at 5:30) at first but Takahashi-san advised that it would probably improve with compression, and it did.
 * Mark and Hirata-san cleared off most of two optical tables and a set of shelves in the OMMT area that Type B had been using but were now required by Somiya-san and Ohishi-san. We still need to remove the geophone and OSEM testing setups.
Line 16: Line 20:
==== Plan for week of 3/19 ====
 * Fujii-kun and Tanioka-kun join.
 * Mark at LVC meeting
 * Fujii-kun at Kamioka (including Wed 3/21)
 * Kozu-kun at Kamioka Mon-Tue.
 * All others at Mitaka
 * --
 * SR2 TFs and control loop development (Shoda-san and Enzo).
 * Assemble four geophone pods (Fujii-kun and Kozu-kun at Kamioka).
 * Make two sets of IM OSEMs (Shoda-san and Enzo)
 * Make last in-air pico adapter cable (Enzo).
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM (Enzo).
 * Set up dummy BS prism removal (Hirata-san).
===== SR2 =====
 * Mark, Enzo and Hirata-san all inspected the lower section of the SR2 to see if there were any interference points that might explain some unexpected peaks in the TFs (especially the RM pitch made appearing in longitudinal) that weren't present before installation. There were no stops touching, but some TM OSEM cables were rubbing against each other, which we fixed. The problem turned out to be swapped cables in the coil actuation.
 * We removed the tank lid, and Enzo and Panwei inspected the cabling that had been done during Enzo's vacation and installed some new cables that had arrived. They also unlocked the IP.
Line 30: Line 24:
==== Plan for week of 3/26 ====
 * Mark vacation.
 * Shoda-san at Mitaka
 * Others at Kamioka
 * --
 * Lay SR3 in-air cabling (Enzo +1).
 * Finish rebuild of second BF (Hirata-san).
 * SF Check (Hirata-san).
  * Check load capacity.
  * Check fit of caps.
  * Add cable clamps to bases.
  * Add cable clamps and Cu segments to caps (only if they fit well).
  * Cable LVDTs and steppers.
==== Plan for week of 10/15 ====
 * Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.
===== SR2 =====
 * Continue shakedown of PI section.
===== SRM =====
 * Align IRM with IM.
 * Suspend/weigh/balance the BF/... section.
 * Build up the AF and SS to the SF level.
 * Install the SF.
Line 45: Line 35:
 * [[KAGRA/Subgroups/VIS/TypeB/March2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/April2018]]
Line 49: Line 37:
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]  * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]
Line 51: Line 39:
==== Vacation Info ====
 * Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
 * Hirata-san vacation, Mon 3/5.
 * Fabian vacation, 3/26-4/27 (then gone).
==== Vacation/Visitor Info ====
 * Terrence: 10/29-11/2 at Kamioka.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 10/8

  • This was Panwei's last week (for now at least) - thanks for all the help!
  • Thanks also to Terrence for visiting again for the week.

SR3
  • Terrence and Mark finished setting up the LEN half of the OL (Simon had roughly placed the components). They ran a new cable for LEN in the cable tray and relaid the cable for TILT to get it off the floor.
  • Terrence worked on diagonalizing the LEN OL. A report is forthcoming.

SRM
  • Mark installed a pair of power supplies in the SRM and copied settings across to the SRM real-time model.
  • Fabian did lots of rack cabling, including installing and connecting BIO cards.
  • Mark and Hirata-san checked and adjusted the pitch of the BF (with a bubble level) and the IM/... section (with the OL).
  • Mark and Panwei installed the sides of the IRM and the IM OSEMs.
  • Hirata-san hung the dummy load from the F0 and started compressing the blade. There was a significant lateral offset (≈2-3 mm towards the blade at 5:30) at first but Takahashi-san advised that it would probably improve with compression, and it did.
  • Mark and Hirata-san cleared off most of two optical tables and a set of shelves in the OMMT area that Type B had been using but were now required by Somiya-san and Ohishi-san. We still need to remove the geophone and OSEM testing setups.

SR2
  • Mark, Enzo and Hirata-san all inspected the lower section of the SR2 to see if there were any interference points that might explain some unexpected peaks in the TFs (especially the RM pitch made appearing in longitudinal) that weren't present before installation. There were no stops touching, but some TM OSEM cables were rubbing against each other, which we fixed. The problem turned out to be swapped cables in the coil actuation.
  • We removed the tank lid, and Enzo and Panwei inspected the cabling that had been done during Enzo's vacation and installed some new cables that had arrived. They also unlocked the IP.

Plan for week of 10/15

  • Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.

SR2
  • Continue shakedown of PI section.

SRM
  • Align IRM with IM.
  • Suspend/weigh/balance the BF/... section.
  • Build up the AF and SS to the SF level.
  • Install the SF.