Line 6: | Line 6: |
* Fabian finished dummy BS assembly. * Mark and Tatsumi-san glued magnets into both types of BS optic flags, and discs into BS IM flags. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1815 |klog]] Two optic flags had to be redone because the magnets moved while the glue was drying. Hirata-san helped remove the magnets with acetone in the ultrasonic cleaner. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1818|klog]] * Tatsumi-san, Fabian and Mark took the dummy BS to Kashiwa and glued the flags and prisms. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1821|klog]] We will check status on Mon 6/13. * Hirata-san measured another filter. * Hirata-san washed a batch of parts. * Hirata-san modified the design of the parts of the assembly frame supporting the BF and SF to include bushings for smoother movement. * Hirata-san worked on work platforms for the installation. * Hirata-san looked for a crane scale for use at the site. (We decided the 500-kg version of the 200-kg one used at TAMA. It is the same price and has the same 100-g resolution for the first 250 kg.) * Hirata-san worked on making some guide parts for the PI installation (Misumi parts with minor additional machining from ATC). * We finalized a design for simple SS mirror parts for the dummy BS with Akutsu-san. They will be made by ATC. * Mark worked on list of items for purchase in FY2016 and on the schedule. * Fabian did more work on the IM assembly. It is nearly done and he will start on the RM next week. |
* Mark and Fabian worked at Kamioka: * All the parts for the security structure were located. The clamp pieces for the IM are being taken back to Mitaka to have extra screw holes added. * The BS/PR2/SR2 area was cleaned and tidied to allow floor removal and assembly frame construction. * 21 "Type 1" cables (PI-Flange, Signal) and 15 "Type 5" cables (OSEM) were tested. They all passed. Sufficient tested "Type 2" cables (PI-Flange, Motor) were located in the PR3 area. * Hirata-san worked on the Inventor assembly, adding views (originally defined by Mark) of the different phases of construction. * Hirata-san shipped 7 SFs and some parts to Kamioka. * Hirata-san made assembly drawings of the damper rings and cable clamps for SR. * Hirata-san liaised with Mirapro about the frame assembly. |
Line 22: | Line 18: |
* Akutsu-san is working to get wide-mouth OSEMs * Longer cables for BF->PI and SF->PI. * Takahashi-san has ordered extra connectors (due any day) and will get a company to make the cables. |
|
Line 26: | Line 25: |
* Not enough crane height problem (Hirata, Saito) - no action since last week | |
Line 28: | Line 26: |
* Crane scale - ordered * Work platforms - ordered |
* Crane scale - RECEIVED |
Line 33: | Line 30: |
* '''Need to be incorporated into the procedure document. Discuss with Takahashi (Mark)''' | * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss. |
Line 36: | Line 33: |
* Clean bag - expected 6/8. |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
- Type B Past Week Summary
- Mark and Fabian worked at Kamioka:
- All the parts for the security structure were located. The clamp pieces for the IM are being taken back to Mitaka to have extra screw holes added.
- The BS/PR2/SR2 area was cleaned and tidied to allow floor removal and assembly frame construction.
- 21 "Type 1" cables (PI-Flange, Signal) and 15 "Type 5" cables (OSEM) were tested. They all passed. Sufficient tested "Type 2" cables (PI-Flange, Motor) were located in the PR3 area.
- Hirata-san worked on the Inventor assembly, adding views (originally defined by Mark) of the different phases of construction.
- Hirata-san shipped 7 SFs and some parts to Kamioka.
- Hirata-san made assembly drawings of the damper rings and cable clamps for SR.
- Hirata-san liaised with Mirapro about the frame assembly.
- Mark and Fabian worked at Kamioka:
- Type B ongoing issues
- Wires
- Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
- OSEMs
- Akutsu-san is working to get wide-mouth OSEMs
Longer cables for BF->PI and SF->PI.
- Takahashi-san has ordered extra connectors (due any day) and will get a company to make the cables.
- Feedthrough Adapters
- Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote.
- Can we make SR wire breakers bigger?
- Fukushima-san will start on machining test soon (as of 5/27).
- Installation stuff
- Crane scale - RECEIVED
- Ballast masses for payload
- Initial batch received - ordered extra smaller ones to allow for adjustments.
- Lower breadboard stuff
- Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
- Breadboard springs (in manufacture, expected end of July)
- Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
- Documents
BS Assembly Procedure E1504235, E1504235 draft
- Wires