Differences between revisions 250 and 309 (spanning 59 versions)
Revision 250 as of 2018-03-16 14:11:13
Size: 3629
Editor: MarkBarton
Comment:
Revision 309 as of 2018-08-08 10:49:23
Size: 2910
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 6: Line 6:
==== Report for week of 3/12 ====
 * We helped Mirapro close up the BS tank, and did last minute checks and adjustments, including using the fishing rods to reset the GAS keystones to mid-range according to the LVDTs. (The F0 had risen so far (≈7 mm) due to temperature changes that it was touching the upper keystone stop screws and defeating the vibration isolation. We operated the F0 FR manually while the tank lid was off.)
 * We installed electronic boxes in the SR3 and SRM racks. Enzo set the phases and gains on the LVDT drivers for both racks. Rack internal cabling and in-air cabling to SR3 still needs to be done.
 * Hirata-san disassembled two BFs (one SF BF with a tilted keystone and the BS Test Hang BF) and characterized all 10 available SR BF blades. He found they fell into a group of 6 strong ones and a group of 4 weak ones, so he divided the 6 into two matched sets and rebuilt the two filters. They still need final adjustment.
 * We noticed that the bottom level of SR2 suspension had developed a significant yaw (enough to foul on the security structure), probably introduced when we picked the chain up to weigh it, so we lifted the suspension again and corrected it.
 * We aligned the SR2 ready for TFs. We noticed that the IM/... section had a noticeable roll (≈20 mrad) but we were unable to correct it with the IM roll pico (the pico runs but the roll does not change, probably because there is too much friction for the mass return spring). We will see if the TFs look OK and then decide whether to try correcting the roll.
 * We gathered items for OSEM assembly by Enzo, Shoda-san and others at Mitaka next week, and for geophone assembly by Fujii-kun and Kozu-kun at Kamioka. Hirata-san ordered some M8x35 screws that we didn't have enough of.
 * Hirata-san packed up two SF caps (the original one from the SR2 SF) and a spare, for remachining by Mirapro. He also packed up the dummy BS and arranged for Ishizaki-san to take it to Mitaka for soaking off of the sapphire prisms.
 * Blade bases promised for delivery did not show up.
==== Report for week of 7/30 ====
===== SR3 ======
 * We undid the accidental misalignment of the SR3. We also switched off the BF GAS offset we had been using, let the IM rise until near zero on the BF LVDT, and adjusted the IM vertical OSEMs back to mid-range.
 * We closed control loops for the SR3 GAS filters.
===== SR2 =====
 * We installed the SR2 SF damper magnet ring but found that the magnet pattern didn't match the Cu segments due to a different in the caps between SR3 and SR2. We raised the ring but left it suspended, clamped the template to the underside and rearranged the magnets.
 * We did a vertical height budget of the SR2. It turns out to have a very similar issue to the SR3: the chain is about 5 mm longer than the CAD, with about 3 mm of that between the SF and BF. We decided to do the same fix and operate with the F0 keystone 5 mm higher. We chose an total amount of ballast to give that keystone height and secured most of it to the SF, keeping a reserve for cables and the yaw stepper.
===== SRM =====
 * We moved the SRM assembly frame into its final position, reset it to the initial configuration, double-checked the heights of the crossbars, and lowered the optical table by 3 mm (to give margin for the optic to rise during hanging, which we had kept forgetting to do). We cleaned it up with the airgun and wet-wipes. We installed the IM ring and IM.
 * We assembled the SRM metal mass. Hirata-san made a jig from a plate with 4 screws which could safely hold the delicate front Sol-Black-coated ring upside down while the rest of the components were mounted on it.
 * We moved the metal mass to the mirror box and added the prisms and magnet standoffs.
Line 16: Line 18:
==== Plan for week of 3/19 ====
 * Fujii-kun joins.
 * Mark at LVC meeting
 * Fujii-kun at Kamioka (including Wed 3/21)
 * Kozu-kun at Kamioka Mon-Tue.
 * All others at Mitaka
 * --
 * SR2 TFs and control loop development (Shoda-san and Enzo).
 * Assemble four geophone pods (Fujii-kun and Kozu-kun at Kamioka).
 * Make two sets of IM OSEMs (Shoda-san and Enzo)
 * Make last in-air pico adapter cable (Enzo).
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM (Enzo).
 * Set up dummy BS prism removal (Hirata-san).
==== Plan for week of 8/20 ====
 * Mark, Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri.
 * Terrence and TBD at f2f on Friday 8/24.
 * Kozu-kun works at Mozumi Mon, Fri.
Line 30: Line 23:
==== Plan for week of 3/26 ====
 * Tanioka-kun joins.
 * Mark vacation.
 * Shoda-san at Mitaka
 * Others at Kamioka
 * --
 * Lay SR3 in-air cabling (Enzo++).
 * Finish tuning of BFs (Hirata-san++).
 * SF check (Hirata-san++).
  * Check load capacity.
  * Check fit of caps.
  * Add cable clamps to bases.
  * Add cable clamps and Cu segments to caps (only if they fit well).
  * Cable LVDTs and steppers.
===== SR3 =====
 * Finalize optic pitch, OSEM alignment.
 * Do TFs with temporary OL.
 * Install final OL.
 * Hook LBB, add ballast mass.
 * Tune IP.

===== SR2 =====
 * Do vertical height budget.
 * Choose F0 keystone height.
 * Add estimated final ballast mass.
 * Do PI cable routing.
 * Adjust ballast/trim mass, with reserve for cables.
 * Stage LBB damper rings in tank.
 
===== SRM =====
 * Assemble metal mass.
 * Glue prisms, flags.
 * Reconfigure, align assembly frame.
Line 46: Line 44:
 * [[KAGRA/Subgroups/VIS/TypeB/March2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/April2018]]
Line 50: Line 46:
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]  * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]
Line 53: Line 49:
 * Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
 * Fabian vacation, 3/26-4/27 (then gone).
 * Terrence: 8/24-26 f2f, then returns to Hong Kong.
 * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 7/30

===== SR3 ======

  • We undid the accidental misalignment of the SR3. We also switched off the BF GAS offset we had been using, let the IM rise until near zero on the BF LVDT, and adjusted the IM vertical OSEMs back to mid-range.
  • We closed control loops for the SR3 GAS filters.

SR2
  • We installed the SR2 SF damper magnet ring but found that the magnet pattern didn't match the Cu segments due to a different in the caps between SR3 and SR2. We raised the ring but left it suspended, clamped the template to the underside and rearranged the magnets.
  • We did a vertical height budget of the SR2. It turns out to have a very similar issue to the SR3: the chain is about 5 mm longer than the CAD, with about 3 mm of that between the SF and BF. We decided to do the same fix and operate with the F0 keystone 5 mm higher. We chose an total amount of ballast to give that keystone height and secured most of it to the SF, keeping a reserve for cables and the yaw stepper.

SRM
  • We moved the SRM assembly frame into its final position, reset it to the initial configuration, double-checked the heights of the crossbars, and lowered the optical table by 3 mm (to give margin for the optic to rise during hanging, which we had kept forgetting to do). We cleaned it up with the airgun and wet-wipes. We installed the IM ring and IM.
  • We assembled the SRM metal mass. Hirata-san made a jig from a plate with 4 screws which could safely hold the delicate front Sol-Black-coated ring upside down while the rest of the components were mounted on it.
  • We moved the metal mass to the mirror box and added the prisms and magnet standoffs.

Plan for week of 8/20

  • Mark, Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri.
  • Terrence and TBD at f2f on Friday 8/24.
  • Kozu-kun works at Mozumi Mon, Fri.

SR3
  • Finalize optic pitch, OSEM alignment.
  • Do TFs with temporary OL.
  • Install final OL.
  • Hook LBB, add ballast mass.
  • Tune IP.

SR2
  • Do vertical height budget.
  • Choose F0 keystone height.
  • Add estimated final ballast mass.
  • Do PI cable routing.
  • Adjust ballast/trim mass, with reserve for cables.
  • Stage LBB damper rings in tank.

SRM
  • Assemble metal mass.
  • Glue prisms, flags.
  • Reconfigure, align assembly frame.

To-Do Lists, Schedule

Vacation Info

  • Terrence: 8/24-26 f2f, then returns to Hong Kong.
  • Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)