Size: 1671
Comment:
|
Size: 1445
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 6: | Line 6: |
==== Report for week of 3/19 ==== * Fujii-kun successfully assembled and tested a geophone pod (klogs 4492, 4508). |
==== Report for week of 5/28 ==== * Enzo redid the SR3 BIO connections to match the now-working BS setup. He also fixed PR2, which had a similar problem. * Enzo replaced LPCDs with HPCDs in the SR3. * Hirata-san and Kozu-kun continued tuning the filter in PI #3. Un |
Line 9: | Line 11: |
==== Plan for week of 6/11 ==== * Mark Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Tue-Fri (Mon is compensation day for f2f.) * -- * Route cables through SF-BF flying saucer up to bottom of SF. * Add minimal ballast mass to SF (rough balance only) and weigh SF/... section. * Adjust BF trim mass. * Readjust payload. * Take TFs. * Cable, test SF LVDT and FR. * Add calculated ballast to SF. * Finish tuning F0 #3 for SR3. * Park F0 #1 (for SR2) in top of SR3 assembly frame. * Move F0 #3 behind SR3. * Move F0 #1 to "factory" area (in front of SRM) and start rebuild. |
|
Line 10: | Line 26: |
==== Plan for week of 3/19 ==== * Fujii-kun joins. * Mark at LVC meeting * Fujii-kun at Kamioka (including Wed 3/21) * Kozu-kun at Kamioka Mon-Tue. * All others at Mitaka |
==== Plan for week of 6/18 ==== * Mark Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Mon-Fri. |
Line 17: | Line 29: |
* SR2 TFs and control loop development (Shoda-san and Enzo). * Assemble four geophone pods (Fujii-kun and Kozu-kun at Kamioka). * Make two sets of IM OSEMs (Shoda-san and Enzo) * Make last in-air pico adapter cable (Enzo). * Make three in-air stepper splitter cables for SR2, SR3 and SRM (Enzo). * Set up dummy BS prism removal (Hirata-san). ==== Plan for week of 3/26 ==== * Tanioka-kun joins. * Mark vacation. * Shoda-san at Mitaka * Others at Kamioka * -- * Lay SR3 in-air cabling (Enzo++). * Finish tuning of BFs (Hirata-san++). * SF check (Hirata-san++). * Check load capacity. * Check fit of caps. * Add cable clamps to bases. * Add cable clamps and Cu segments to caps (only if they fit well). * Cable LVDTs and steppers. |
* Install PI. * Suspend SF/... section. * Lots of cabling. |
Line 40: | Line 34: |
* [[KAGRA/Subgroups/VIS/TypeB/March2018]] * [[KAGRA/Subgroups/VIS/TypeB/April2018]] |
|
Line 47: | Line 39: |
* Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun) * Fabian vacation, 3/26-4/27 (then gone). |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 5/28
- Enzo redid the SR3 BIO connections to match the now-working BS setup. He also fixed PR2, which had a similar problem.
- Enzo replaced LPCDs with HPCDs in the SR3.
- Hirata-san and Kozu-kun continued tuning the filter in PI #3. Un
Plan for week of 6/11
- Mark Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Tue-Fri (Mon is compensation day for f2f.)
- --
- Route cables through SF-BF flying saucer up to bottom of SF.
- Add minimal ballast mass to SF (rough balance only) and weigh SF/... section.
- Adjust BF trim mass.
- Readjust payload.
- Take TFs.
- Cable, test SF LVDT and FR.
- Add calculated ballast to SF.
- Finish tuning F0 #3 for SR3.
- Park F0 #1 (for SR2) in top of SR3 assembly frame.
- Move F0 #3 behind SR3.
- Move F0 #1 to "factory" area (in front of SRM) and start rebuild.
Plan for week of 6/18
- Mark Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Mon-Fri.
- --
- Install PI.
- Suspend SF/... section.
- Lots of cabling.
To-Do Lists, Schedule