Size: 1124
Comment:
|
Size: 1519
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 6: | Line 6: |
==== Report for week of 3/19 ==== * Fujii-kun successfully assembled and tested a geophone pod (klogs 4492, 4508). |
==== Report for week of 4/9 ==== * We packed away the SRM SF and BF. * After several failed attempts with one secondary prism, Mark finished the SR3 prism/magnet gluing. * Tanioka-kun built two IRMs (less OSEMs). * Enzo built an RM. * Kozu-kun and Enzo calibrated one set of 6 IM OSEMs for SR3. (6 OSEMs for SRM remain to be done.) * Hirata-san aligned the assembly frame, installed the interface bars and IM ring, and installed the IM. |
Line 9: | Line 14: |
==== Plan for week of 3/26 ==== * Tanioka-kun joins. * Mark vacation. * Shoda-san at Mitaka * Others at Kamioka |
==== Plan for week of 4/23 ==== * Hirata-san at Mitaka Mon-Tue, then Kamioka. * Tanioka-san at Kamioka Tue-Thu * Kozu-kun at Kamioka Wed-Fri (but working with PEM on Fri). * Others at Kamioka full week |
Line 15: | Line 20: |
* Lay SR3 in-air cabling (Enzo++). * Finish tuning of BFs (Hirata-san++). * SF check (Hirata-san++). * Check load capacity. * Check fit of caps. * Add cable clamps to bases. * Add cable clamps and Cu segments to caps (only if they fit well). * Cable LVDTs and steppers. |
* Start SR3 Hang * Hang optic. * Hang RM. * Cable RM OSEMs. ==== Plan for week of 4/30 ==== * Shoda-san at Mitaka. * Mark, Enzo at Kamioka Mon-Wed or TBD. * Others doing Golden Week stuff. * -- * Observe KAGRA Phase 1 operations, assist if problems arise. * Do BF TFs. * Continue SR3 hang. |
Line 32: | Line 42: |
* Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun) |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 4/9
- We packed away the SRM SF and BF.
- After several failed attempts with one secondary prism, Mark finished the SR3 prism/magnet gluing.
- Tanioka-kun built two IRMs (less OSEMs).
- Enzo built an RM.
- Kozu-kun and Enzo calibrated one set of 6 IM OSEMs for SR3. (6 OSEMs for SRM remain to be done.)
- Hirata-san aligned the assembly frame, installed the interface bars and IM ring, and installed the IM.
Plan for week of 4/23
- Hirata-san at Mitaka Mon-Tue, then Kamioka.
- Tanioka-san at Kamioka Tue-Thu
- Kozu-kun at Kamioka Wed-Fri (but working with PEM on Fri).
- Others at Kamioka full week
- --
- Start SR3 Hang
- Hang optic.
- Hang RM.
- Cable RM OSEMs.
Plan for week of 4/30
- Shoda-san at Mitaka.
- Mark, Enzo at Kamioka Mon-Wed or TBD.
- Others doing Golden Week stuff.
- --
- Observe KAGRA Phase 1 operations, assist if problems arise.
- Do BF TFs.
- Continue SR3 hang.
To-Do Lists, Schedule
Vacation Info
- Fabian vacation, 3/26-4/27 (then gone).