Size: 1124
Comment:
|
Size: 1275
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 6: | Line 6: |
==== Report for week of 3/19 ==== * Fujii-kun successfully assembled and tested a geophone pod (klogs 4492, 4508). |
==== Report for week of 7/30 ==== * ==== Plan for week of 8/6 ==== * Mark, Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri. * Kozu-kun works at Mozumi Mon, Fri, and Thu afternoon. |
Line 9: | Line 12: |
==== Plan for week of 3/26 ==== * Tanioka-kun joins. * Mark vacation. * Shoda-san at Mitaka * Others at Kamioka * -- * Lay SR3 in-air cabling (Enzo++). * Finish tuning of BFs (Hirata-san++). * SF check (Hirata-san++). * Check load capacity. * Check fit of caps. * Add cable clamps to bases. * Add cable clamps and Cu segments to caps (only if they fit well). * Cable LVDTs and steppers. |
===== SR3 ===== * Finalize optic pitch, OSEM alignment. * Do TFs with temporary OL. * Install final OL. * Hook LBB, add ballast mass, set up temporary OL (horizontal beam, pitch/yaw only). ===== SR2 ===== * Add estimated final ballast mass. * Do PI cable routing. * Adjust ballast/trim mass, with reserve for cables. ===== SRM ===== * Assemble metal mass. * Glue prisms, flags. * Reconfigure, align assembly frame. * Tune F0 for SRM. * Add LBB blade units, cable clamps etc. * Check PI coil connections, IP LVDT magnets. |
Line 25: | Line 32: |
* [[KAGRA/Subgroups/VIS/TypeB/March2018]] * [[KAGRA/Subgroups/VIS/TypeB/April2018]] |
|
Line 29: | Line 34: |
* [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]] | * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]] |
Line 32: | Line 37: |
* Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun) * Fabian vacation, 3/26-4/27 (then gone). |
* Terrence: 8/24-26 f2f, then returns to Hong Kong. * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile. |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 7/30
Plan for week of 8/6
- Mark, Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri.
- Kozu-kun works at Mozumi Mon, Fri, and Thu afternoon.
SR3
- Finalize optic pitch, OSEM alignment.
- Do TFs with temporary OL.
- Install final OL.
- Hook LBB, add ballast mass, set up temporary OL (horizontal beam, pitch/yaw only).
SR2
- Add estimated final ballast mass.
- Do PI cable routing.
- Adjust ballast/trim mass, with reserve for cables.
SRM
- Assemble metal mass.
- Glue prisms, flags.
- Reconfigure, align assembly frame.
- Tune F0 for SRM.
- Add LBB blade units, cable clamps etc.
- Check PI coil connections, IP LVDT magnets.
To-Do Lists, Schedule
Vacation Info
- Terrence: 8/24-26 f2f, then returns to Hong Kong.
- Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.