Line 6: | Line 6: |
==== Report for week of 3/19 ==== * Fujii-kun successfully assembled and tested a geophone pod (klogs 4492, 4508). * ?? Hirata-san set up the dummy BS to soak off the sapphire prisms. * |
==== Report for week of 4/2 ==== |
Line 11: | Line 8: |
==== Plan for week of 3/26 ==== * Tanioka-kun joins. * Mark vacation. * Shoda-san at Mitaka * Others at Kamioka * -- * Lay SR3 in-air cabling (Enzo++). * Finish tuning of BFs (Hirata-san++). * SF check (Hirata-san++). * Check load capacity. * Check fit of caps. * Add cable clamps to bases. * Add cable clamps and Cu segments to caps (only if they fit well). * Cable LVDTs and steppers. ==== Plan for week of 4/2 ==== * Mark at Mitaka Mon, Kamioka from Tue. * Shoda-san at Mitaka * Others at Kamioka * -- * Glue SR3 (if available) * Build 2xIM, 2xIRM (if parts available - due 3/30) |
* We received the SR3 but found Hirose-san had applied the First Contact patterns on the wrong sides, so we took it to Yamamoto-san's lab and Toyama University and re-applied the FC properly. We also bounced a 1064 nm beam off it to verify that the HR and AR coatings were not also swapped (they were OK). * We made magnet-standoff assemblies for both SR3 and SRM, and set up for gluing the prisms and magnets. We will attach the prisms and magnet-standoffs on Monday. * Hirata-san did inventory of the SR3/SRM payload parts received last week and started on the inventory of screws. * Fujii-kun, Enzo and team finished the preparation, adjustment and calibration of the SFs and BFs. * Fujii-kun and Yamamoto-kun got the SR3 real time model running. * Enzo finished setting up the SR3 and SRM racks. (The SRM rack still lacks a front-end, and power and network connections, but the SR3 is now ready for testing.) * Shoda-san worked on getting quotes for the ballast masses, on design of the SRM metal mass, and on splitting the BS model to reduce the load on the front-end computer. |
Line 36: | Line 18: |
* Fujii-san at Mitaka * Tanioka-san at Mitaka? |
|
Line 39: | Line 23: |
* Build 1xRM | * Glue SR3 mirror |
Line 42: | Line 26: |
* Start SR3 Hang? | * Shoda-san at Mitaka * Fujii-san at Mitaka * Tanioka-san at Mitaka? * Others at Kamioka * -- * Build 1xRM * Start SR3 Hang * Align assembly frame. |
Line 45: | Line 36: |
* F0 blade prototype test | * Shoda-san at Mitaka * Fujii-san at Mitaka? * Mark, Enzo at Kamioka * Hirata-san at Mitaka * Tanioka-san at Mitaka? * -- * Clean parts (cable clamp bases, etc, etc). * Observe KAGRA Phase 1 operations, assist if problems arise. |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 4/2
- We received the SR3 but found Hirose-san had applied the First Contact patterns on the wrong sides, so we took it to Yamamoto-san's lab and Toyama University and re-applied the FC properly. We also bounced a 1064 nm beam off it to verify that the HR and AR coatings were not also swapped (they were OK).
- We made magnet-standoff assemblies for both SR3 and SRM, and set up for gluing the prisms and magnets. We will attach the prisms and magnet-standoffs on Monday.
- Hirata-san did inventory of the SR3/SRM payload parts received last week and started on the inventory of screws.
- Fujii-kun, Enzo and team finished the preparation, adjustment and calibration of the SFs and BFs.
- Fujii-kun and Yamamoto-kun got the SR3 real time model running.
- Enzo finished setting up the SR3 and SRM racks. (The SRM rack still lacks a front-end, and power and network connections, but the SR3 is now ready for testing.)
- Shoda-san worked on getting quotes for the ballast masses, on design of the SRM metal mass, and on splitting the BS model to reduce the load on the front-end computer.
Plan for week of 4/9
- Shoda-san at Mitaka
- Fujii-san at Mitaka
- Tanioka-san at Mitaka?
- Others at Kamioka
- --
- Finish IMs and IRMs
- Glue SR3 mirror
Plan for week of 4/16
- Shoda-san at Mitaka
- Fujii-san at Mitaka
- Tanioka-san at Mitaka?
- Others at Kamioka
- --
- Build 1xRM
- Start SR3 Hang
- Align assembly frame.
Plan for week of 4/23
- Shoda-san at Mitaka
- Fujii-san at Mitaka?
- Mark, Enzo at Kamioka
- Hirata-san at Mitaka
- Tanioka-san at Mitaka?
- --
- Clean parts (cable clamp bases, etc, etc).
- Observe KAGRA Phase 1 operations, assist if problems arise.
Plan for week of 4/30
- Golden Week!
To-Do Lists, Schedule
Vacation Info
- Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
- Fabian vacation, 3/26-4/27 (then gone).