Line 6: | Line 6: |
==== Report for week of 3/19 ==== * Fujii-kun successfully assembled and tested a geophone pod (klogs 4492, 4508). * Hirata-san set up the dummy BS to soak off the sapphire prisms. (In process) * Shoda-san, Hirata-san and Enzo finished the assembly of 12 OSEMs. We still need to measure the maximum output (In process) * We will send the OSEMs to Kamioka today. |
==== Report for week of 3/26 ==== BFs: * BF No. 1: * Fujii-san finished tuning. * Enzo wired the LVDT, Picomotor and Steppermotor. * We measured the keystone tilt at 4 different points and it was at 65.5, 65.5, 65.5 and 65.5. So with the differences of 0.1 mm we think we can tolarate this differences. * We added cable clamps to the base. * BF No.7: * Fujii-san disassemble the blades corresponding to the BS and we assemble the SR type blades. SFs: * Hirata-san and Tanioka-san set up the frame to check the SFs. * SF (B2-5): * Hirata-san, Fujii-san and Tanioka-san checked the optimal load with and without cap. The optimal load changes about 200[g]. * We measured the keystone tilt at x points: 65.5mm, 65.5mm, 65.5mm, and 65.5mm. * SF (B2-6): * Hirata-san, Fujii-san and Tanioka-san checked the optimal load with and without cap (On going?). * We measured the keystone tilt at x points: 65.5mm, 65.5mm, 65.5mm, and 65.5mm. SR3/SRM: * Kozu-kun and Enzo finished the SR3 in-air cabling. * Enzo prepared the SR3 and SRM rack in parallel (On going). BS: * Kozu-kun and Enzo helped Enomoto-san troubleshooting the BS Oplev issue (On going). Others: * We finished tuning of BF No. 1. * We wired the LVDT, Picomotor and StepperMotor of BF No. 1. * We finished tuning of BF No. 7. * We wired the LVDT, Picomotor and StepperMotor of BF No. 7. |
Line 14: | Line 54: |
==== Plan for week of 3/26 ==== * Tanioka-kun joins. * Mark vacation. * Shoda-san at Mitaka * Others at Kamioka * -- * Lay SR3 in-air cabling (Enzo++). * Finish tuning of BFs (Hirata-san++). |
|
Line 23: | Line 55: |
* Check load capacity. * Check fit of caps. |
* We checked the load capacity with and without the cap. * We checked fit of caps. For the SF No. |
Line 28: | Line 60: |
* We finished the SR3 in-air cabling. |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 3/26
BFs:
- BF No. 1:
- Fujii-san finished tuning.
- Enzo wired the LVDT, Picomotor and Steppermotor.
- We measured the keystone tilt at 4 different points and it was at 65.5, 65.5, 65.5 and 65.5.
- So with the differences of 0.1 mm we think we can tolarate this differences.
- We added cable clamps to the base.
- BF No.7:
- Fujii-san disassemble the blades corresponding to the BS and we assemble the SR type blades.
SFs:
- Hirata-san and Tanioka-san set up the frame to check the SFs.
- SF (B2-5):
- Hirata-san, Fujii-san and Tanioka-san checked the optimal load with and without cap. The optimal load changes about 200[g].
- We measured the keystone tilt at x points: 65.5mm, 65.5mm, 65.5mm, and 65.5mm.
- SF (B2-6):
- Hirata-san, Fujii-san and Tanioka-san checked the optimal load with and without cap (On going?).
- We measured the keystone tilt at x points: 65.5mm, 65.5mm, 65.5mm, and 65.5mm.
SR3/SRM:
- Kozu-kun and Enzo finished the SR3 in-air cabling.
- Enzo prepared the SR3 and SRM rack in parallel (On going).
BS:
- Kozu-kun and Enzo helped Enomoto-san troubleshooting the BS Oplev issue (On going).
Others:
- We finished tuning of BF No. 1.
We wired the LVDT, Picomotor and StepperMotor of BF No. 1.
- We finished tuning of BF No. 7.
We wired the LVDT, Picomotor and StepperMotor of BF No. 7.
- SF check (Hirata-san++).
- We checked the load capacity with and without the cap.
- We checked fit of caps. For the SF No.
- Add cable clamps to bases.
- Add cable clamps and Cu segments to caps (only if they fit well).
- Cable LVDTs and steppers.
- We finished the SR3 in-air cabling.
Plan for week of 4/2
- Mark at Mitaka Mon, Kamioka from Tue.
- Shoda-san at Mitaka
- Others at Kamioka
- --
- Glue SR3 (if available)
- Build 2xIM, 2xIRM (if parts available - due 3/30)
Plan for week of 4/9
- Shoda-san at Mitaka
- Others at Kamioka
- --
- Finish IMs and IRMs
- Build 1xRM
Plan for week of 4/16
- Start SR3 Hang?
Plan for week of 4/23
- F0 blade prototype test
Plan for week of 4/30
- Golden Week!
To-Do Lists, Schedule
Vacation Info
- Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
- Fabian vacation, 3/26-4/27 (then gone).