1923
Comment:
|
2260
|
Deletions are marked like this. | Additions are marked like this. |
Line 6: | Line 6: |
==== Report for week of 3/19 ==== * Fujii-kun successfully assembled and tested a geophone pod (klogs 4492, 4508). * Hirata-san set up the dummy BS to soak off the sapphire prisms (ongoing). * Shoda-san, Hirata-san and Enzo finished the assembly of 12 OSEMs. We still need to measure the maximum output (ongoing). * We will send the OSEMs to Kamioka today. * Enzo made 2 in-air picomotor cable. |
==== Report for week of 9/17 ==== * Monday 9/17 was holiday. * We optimized the trim mass on the SF to get more balance torque with less total mass. We now have a reserve of 480 g for the yaw pico. * We set the SF damper gap to 6 mm. * We set the SR2 pitch with the optic lever, aligned the IRM and set all the OSEMs to have good clearance and midrange output. * We locked the SR2 suspension (except for the SF) and craned it into the tank. * We moved the vacuum feedthroughs over to the tank. * With help from Ohishi-san, we removed the First Contact from SR2. * Mark did an audit of all the electronics boxes and updated the item list and S-number file cards on JGWDoc. * Mark did an inventory of some thin arc weights and finalized the number to order (8*38 mm + 9*10 mm). * Panwei copied control filters over from the SR3. ==== Plan for week of 9/24 ==== * Monday 9/24 is holiday (Autumn Equinox). * Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri. ===== SR2 ===== * Remove First Contact. * Move SR2 in-air cables. * Unlock and realign suspension. ===== SRM ===== * Set pitch of SRM and RM, tighten clamps, remove winch system. * Weigh IM/... section. * Build up SS to BF level. * Add BF. * Suspend IM and tweak height/balance. |
Line 13: | Line 32: |
==== Plan for week of 10/1 ==== * Mark, Hirata-san, Fabian, Panwei at Kamioka Mon-Fri. ===== SRM ===== * Cable/test BF. * Install IRM. * Install/cable/test IM OSEMs. |
|
Line 14: | Line 39: |
==== Plan for week of 3/26 ==== * Tanioka-kun joins. * Mark vacation. * Shoda-san at Mitaka * Others at Kamioka * -- * Lay SR3 in-air cabling (Enzo++). * Finish tuning of BFs (Hirata-san++). * SF check (Hirata-san++). * Check load capacity. * Check fit of caps. * Add cable clamps to bases. * Add cable clamps and Cu segments to caps (only if they fit well). * Cable LVDTs and steppers. ==== Plan for week of 4/2 ==== * Mark at Mitaka Mon, Kamioka from Tue. * Shoda-san at Mitaka * Others at Kamioka * -- * Glue SR3 (if available) * Build 2xIM, 2xIRM (if parts available - due 3/30) ==== Plan for week of 4/9 ==== * Shoda-san at Mitaka * Others at Kamioka * -- * Finish IMs and IRMs * Build 1xRM ==== Plan for week of 4/16 ==== * Start SR3 Hang? ==== Plan for week of 4/23 ==== * F0 blade prototype test ==== Plan for week of 4/30 ==== * Golden Week! |
==== Plan for week of 10/8 ==== * Monday 10/8 is Sports Day. * Mark and Terrence (plus TBD) at Kamioka Mon-Fri. * Hirata-san, Fabian and Panwei at Kamioka Tue-Fri. ===== SR2 ===== * Terrence to set up LEN half of SR3 OL and, time permitting, TILT and LEN for SR2. ===== SRM ===== |
Line 54: | Line 48: |
* [[KAGRA/Subgroups/VIS/TypeB/March2018]] * [[KAGRA/Subgroups/VIS/TypeB/April2018]] |
|
Line 58: | Line 50: |
* [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]] | * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]] |
Line 60: | Line 52: |
==== Vacation Info ==== * Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun) * Fabian vacation, 3/26-4/27 (then gone). |
==== Vacation/Visitor Info ==== * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile. * Terrence: 10/8-12, 10/29-11/2 at Kamioka. |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 9/17
- Monday 9/17 was holiday.
- We optimized the trim mass on the SF to get more balance torque with less total mass. We now have a reserve of 480 g for the yaw pico.
- We set the SF damper gap to 6 mm.
- We set the SR2 pitch with the optic lever, aligned the IRM and set all the OSEMs to have good clearance and midrange output.
- We locked the SR2 suspension (except for the SF) and craned it into the tank.
- We moved the vacuum feedthroughs over to the tank.
- With help from Ohishi-san, we removed the First Contact from SR2.
- Mark did an audit of all the electronics boxes and updated the item list and S-number file cards on JGWDoc.
- Mark did an inventory of some thin arc weights and finalized the number to order (8*38 mm + 9*10 mm).
- Panwei copied control filters over from the SR3.
Plan for week of 9/24
- Monday 9/24 is holiday (Autumn Equinox).
- Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri.
SR2
- Remove First Contact.
- Move SR2 in-air cables.
- Unlock and realign suspension.
SRM
- Set pitch of SRM and RM, tighten clamps, remove winch system.
- Weigh IM/... section.
- Build up SS to BF level.
- Add BF.
- Suspend IM and tweak height/balance.
Plan for week of 10/1
- Mark, Hirata-san, Fabian, Panwei at Kamioka Mon-Fri.
SRM
- Cable/test BF.
- Install IRM.
- Install/cable/test IM OSEMs.
Plan for week of 10/8
- Monday 10/8 is Sports Day.
- Mark and Terrence (plus TBD) at Kamioka Mon-Fri.
- Hirata-san, Fabian and Panwei at Kamioka Tue-Fri.
SR2
- Terrence to set up LEN half of SR3 OL and, time permitting, TILT and LEN for SR2.
SRM
To-Do Lists, Schedule
Vacation/Visitor Info
- Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.
- Terrence: 10/8-12, 10/29-11/2 at Kamioka.