 * Type B Past Week Summary
  * Fabian finished dummy BS assembly.
  * Mark and Tatsumi-san glued magnets into both types of BS optic flags, and discs into BS IM flags. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1815 |klog]] Two optic flags had to be redone because the magnets moved while the glue was drying. Hirata-san helped remove the magnets with acetone in the ultrasonic cleaner. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1818|klog]]
  * Tatsumi-san, Fabian and Mark took the dummy BS to Kashiwa and glued the flags and prisms. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1821|klog]] We will check status on Mon 6/13.
  * Hirata-san measured another filter.
  * Hirata-san washed a batch of parts.
  * Hirata-san modified the design of the parts of the assembly frame supporting the BF and SF to include bushings for smoother movement.
  * Hirata-san worked on work platforms for the installation.
  * Hirata-san looked for a crane scale for use at the site. (We decided the 500-kg version of the 200-kg one used at TAMA. It is the same price and has the same 100-g resolution for the first 250 kg.)
  * Hirata-san worked on making some guide parts for the PI installation (Misumi parts with minor additional machining from ATC).
  * We finalized a design for simple SS mirror parts for the dummy BS with Akutsu-san. They will be made by ATC.
  * Mark worked on list of items for purchase in FY2016 and on the schedule.
  * Fabian did more work on the IM assembly. It is nearly done and he will start on the RM next week.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
  * Feedthrough Adapters
   * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote.
  * Can we make SR wire breakers bigger?
   * Fukushima-san will start on machining test soon (as of 5/27).
  * Not enough crane height problem (Hirata, Saito) - no action since last week
  * Installation stuff
   * Crane scale - quote received
   * Work platforms - quote received
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
  * Clean bag - expected 6/8.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
=== Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Enzo, Hirata-san, Yoshioka-kun):
 * We lubricated the stuck screw at the top of the security structure with stuck and were able to remove it.
 * Enzo disconnected and removed or coiled many in-vac cables at the PI level to free it.
 * We craned the PI. There was a minor safety incident - see below.
 * Hirata-san set up the filter service area, and we moved in a BF intended for one of the SRs (BF#3).
 * Fabian and Hirata-san worked out a method for characterizing a single spring, and Fabian finished characterizing the first one.
 * We did a big tidy-up and clean-up of the area, especially the corner where we intended to do the gluing.
 * We set up the BS gluing jigs and applied the glue. We will check the results on Monday.

==== Plan for week of 7/24 ====
Full team at Kamioka from Mon-Fri, except Hirata-san (Tue-Fri) and Enzo (vacation).
 * Check results of gluing.
 * Finish disassembly.
 * Finish BF rebuild.
 * Remove LBB rings.
 * Recheck alignment of assembly frame and centering of optical table.
 * Install IM, suspend BS and RM.

==== Plan for week of 7/31 ====
Full team at Kamioka from Mon-Fri, except Fabian (Mon-Thu) and Enzo (vacation).
 * Weigh/trim BS/RM/IM.
 * Bring in rebuilt BF.

Vacation Info:
Hirata-san: Thu 7/20 through Mon 7/24
Enzo: Sat 7/22 through Sun 8/6
Fabian: Fri 8/4 through Mon 8/21
Mark: TBD Mid-Oct

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Enzo, Hirata-san, Yoshioka-kun):

  • We lubricated the stuck screw at the top of the security structure with stuck and were able to remove it.
  • Enzo disconnected and removed or coiled many in-vac cables at the PI level to free it.
  • We craned the PI. There was a minor safety incident - see below.
  • Hirata-san set up the filter service area, and we moved in a BF intended for one of the SRs (BF#3).
  • Fabian and Hirata-san worked out a method for characterizing a single spring, and Fabian finished characterizing the first one.
  • We did a big tidy-up and clean-up of the area, especially the corner where we intended to do the gluing.
  • We set up the BS gluing jigs and applied the glue. We will check the results on Monday.

Plan for week of 7/24

Full team at Kamioka from Mon-Fri, except Hirata-san (Tue-Fri) and Enzo (vacation).

  • Check results of gluing.
  • Finish disassembly.
  • Finish BF rebuild.
  • Remove LBB rings.
  • Recheck alignment of assembly frame and centering of optical table.
  • Install IM, suspend BS and RM.

Plan for week of 7/31

Full team at Kamioka from Mon-Fri, except Fabian (Mon-Thu) and Enzo (vacation).

  • Weigh/trim BS/RM/IM.
  • Bring in rebuilt BF.

Vacation Info: Hirata-san: Thu 7/20 through Mon 7/24 Enzo: Sat 7/22 through Sun 8/6 Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct