Size: 2920
Comment:
|
Size: 1671
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 5: | Line 5: |
* Type B Past Week Summary * Fabian finished dummy BS assembly. * Mark and Tatsumi-san glued magnets into both types of BS optic flags, and discs into BS IM flags. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1815 |klog]] Two optic flags had to be redone because the magnets moved while the glue was drying. Hirata-san helped remove the magnets with acetone in the ultrasonic cleaner. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1818|klog]] * Tatsumi-san, Fabian and Mark took the dummy BS to Kashiwa and glued the flags and prisms. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1821|klog]] We will check status on Mon 6/13. * Hirata-san measured another filter. * Hirata-san washed a batch of parts. * Hirata-san modified the design of the parts of the assembly frame supporting the BF and SF to include bushings for smoother movement. * Hirata-san worked on work platforms for the installation. * Hirata-san looked for a crane scale for use at the site. (We decided the 500-kg version of the 200-kg one used at TAMA. It is the same price and has the same 100-g resolution for the first 250 kg.) * Hirata-san worked on making some guide parts for the PI installation (Misumi parts with minor additional machining from ATC). * We finalized a design for simple SS mirror parts for the dummy BS with Akutsu-san. They will be made by ATC. * Mark worked on list of items for purchase in FY2016 and on the schedule. * Fabian did more work on the IM assembly. It is nearly done and he will start on the RM next week. * Type B ongoing issues * Wires * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco. * OSEMs * Feedthrough Adapters * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote. * Can we make SR wire breakers bigger? * Fukushima-san will start on machining test soon (as of 5/27). * Not enough crane height problem (Hirata, Saito) - no action since last week * Installation stuff * Crane scale - quote received * Work platforms - quote received * Ballast masses for payload * Initial batch received - ordered extra smaller ones to allow for adjustments. * Lower breadboard stuff * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss. * Breadboard springs (in manufacture, expected end of July) * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order. * Clean bag - expected 6/8. * Documents * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] |
=== Type B (Mark) === ==== Report for week of 4/9 ==== * We packed away the SRM SF and BF. * After several failed attempts with one secondary prism, Mark finished the SR3 prism/magnet gluing. * Tanioka-kun built two IRMs (less OSEMs). * Enzo built an RM. * Kozu-kun and Enzo calibrated one set of 6 IM OSEMs for SR3. (6 OSEMs for SRM remain to be done.) * Hirata-san aligned the assembly frame, installed the interface bars and IM ring, and installed the IM. * Eleonora and Izumi-san revisited the BS length to tilt coupling, which had degraded, and got it working again. ==== Plan for week of 4/23 ==== * Shoda-san at Mitaka. * Hirata-san at Kamioka Mon-Wed, then Mitaka. * Kozu-kun at Kamioka Wed-Fri (but may be working with PEM on Fri). * Others (Mark, Enzo, Tanioka-kun) at Kamioka full week * -- * Continue SR3 Hang * Hang optic. * Hang RM. * Cable RM OSEMs. ==== Plan for week of 4/30 ==== * Shoda-san at Mitaka. * Mark, Enzo at Kamioka Mon-Wed or TBD. * Others having fun doing Golden Week stuff. * -- * Observe KAGRA Phase 1 operations, assist if problems arise. * Do BF TFs. * Continue SR3 hang. ==== To-Do Lists, Schedule ==== * [[KAGRA/Subgroups/VIS/TypeB/March2018]] * [[KAGRA/Subgroups/VIS/TypeB/April2018]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]] ==== Vacation Info ==== * Fabian vacation, 3/26-4/27 (then gone). |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 4/9
- We packed away the SRM SF and BF.
- After several failed attempts with one secondary prism, Mark finished the SR3 prism/magnet gluing.
- Tanioka-kun built two IRMs (less OSEMs).
- Enzo built an RM.
- Kozu-kun and Enzo calibrated one set of 6 IM OSEMs for SR3. (6 OSEMs for SRM remain to be done.)
- Hirata-san aligned the assembly frame, installed the interface bars and IM ring, and installed the IM.
- Eleonora and Izumi-san revisited the BS length to tilt coupling, which had degraded, and got it working again.
Plan for week of 4/23
- Shoda-san at Mitaka.
- Hirata-san at Kamioka Mon-Wed, then Mitaka.
- Kozu-kun at Kamioka Wed-Fri (but may be working with PEM on Fri).
- Others (Mark, Enzo, Tanioka-kun) at Kamioka full week
- --
- Continue SR3 Hang
- Hang optic.
- Hang RM.
- Cable RM OSEMs.
Plan for week of 4/30
- Shoda-san at Mitaka.
- Mark, Enzo at Kamioka Mon-Wed or TBD.
- Others having fun doing Golden Week stuff.
- --
- Observe KAGRA Phase 1 operations, assist if problems arise.
- Do BF TFs.
- Continue SR3 hang.
To-Do Lists, Schedule
Vacation Info
- Fabian vacation, 3/26-4/27 (then gone).