Differences between revisions 26 and 291 (spanning 265 versions)
Revision 26 as of 2016-06-09 14:47:55
Size: 2920
Editor: MarkBarton
Comment:
Revision 291 as of 2018-06-08 13:31:14
Size: 2355
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary
  * Fabian finished dummy BS assembly.
  * Mark and Tatsumi-san glued magnets into both types of BS optic flags, and discs into BS IM flags. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1815 |klog]] Two optic flags had to be redone because the magnets moved while the glue was drying. Hirata-san helped remove the magnets with acetone in the ultrasonic cleaner. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1818|klog]]
  * Tatsumi-san, Fabian and Mark took the dummy BS to Kashiwa and glued the flags and prisms. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1821|klog]] We will check status on Mon 6/13.
  * Hirata-san measured another filter.
  * Hirata-san washed a batch of parts.
  * Hirata-san modified the design of the parts of the assembly frame supporting the BF and SF to include bushings for smoother movement.
  * Hirata-san worked on work platforms for the installation.
  * Hirata-san looked for a crane scale for use at the site. (We decided the 500-kg version of the 200-kg one used at TAMA. It is the same price and has the same 100-g resolution for the first 250 kg.)
  * Hirata-san worked on making some guide parts for the PI installation (Misumi parts with minor additional machining from ATC).
  * We finalized a design for simple SS mirror parts for the dummy BS with Akutsu-san. They will be made by ATC.
  * Mark worked on list of items for purchase in FY2016 and on the schedule.
  * Fabian did more work on the IM assembly. It is nearly done and he will start on the RM next week.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
  * Feedthrough Adapters
   * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote.
  * Can we make SR wire breakers bigger?
   * Fukushima-san will start on machining test soon (as of 5/27).
  * Not enough crane height problem (Hirata, Saito) - no action since last week
  * Installation stuff
   * Crane scale - quote received
   * Work platforms - quote received
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
  * Clean bag - expected 6/8.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
=== Type B (Mark) ===
==== Report for week of 5/28 ====
 * Enzo and Mark debugged the BS BIO connections and finally got it working. There were a total of four issues identified:
  * A wrong block used in the BS real-time model.
  * The real-time model deciding to treat the cards as numbered backwards from the slot order or the jumper settings.
  * Two unlabeled cables that may have been swapped.
  * The GAS coil driver and associated cables had been labeled HPCD #1 whereas it had been #0 in the diagram.
 * Hirata-san and Kozu-kun received the final F0 blades, characterized 6 of them and, with help from Takahashi-san, installed a matched set of 3 into PI #3. It appears to be 6 kg short of the load capacity that was targeted, but still with 4 kg of margin. It is close to having a good frequency but needs another round of tuning.
 * Mark and Terrence fixed an issue with the security structure - due to a screenshot of the CAD not updated from the BS procedure to the SR one, the BF ring had been placed 180° off in yaw. We suspended the BF from the load gauge adapter, reconfigured the BF jacks to support the ring instead of the BF, and rotated the ring. Mark corrected the procedure.

==== Plan for week of 6/11 ====
 * Mark Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Tue-Fri (Mon is compensation day for f2f.)
 * --
 * Route cables through SF-BF flying saucer up to bottom of SF.
 * Add minimal ballast mass to SF (rough balance only) and weigh SF/... section.
 * Adjust BF trim mass.
 * Readjust payload.
 * Take TFs.
 * Cable, test SF LVDT and FR.
 * Add calculated ballast to SF.
 * Finish tuning F0 #3 for SR3.
 * Park F0 #1 (for SR2) in top of SR3 assembly frame.
 * Move F0 #3 behind SR3.
 * Move F0 #1 to "factory" area (in front of SRM) and start rebuild.

==== Plan for week of 6/18 ====
 * Mark Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Mon-Fri.
 * --
 * Install PI.
 * Suspend SF/... section.
 * Lots of cabling.

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]

==== Vacation Info ====

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 5/28

  • Enzo and Mark debugged the BS BIO connections and finally got it working. There were a total of four issues identified:
    • A wrong block used in the BS real-time model.
    • The real-time model deciding to treat the cards as numbered backwards from the slot order or the jumper settings.
    • Two unlabeled cables that may have been swapped.
    • The GAS coil driver and associated cables had been labeled HPCD #1 whereas it had been #0 in the diagram.
  • Hirata-san and Kozu-kun received the final F0 blades, characterized 6 of them and, with help from Takahashi-san, installed a matched set of 3 into PI #3. It appears to be 6 kg short of the load capacity that was targeted, but still with 4 kg of margin. It is close to having a good frequency but needs another round of tuning.
  • Mark and Terrence fixed an issue with the security structure - due to a screenshot of the CAD not updated from the BS procedure to the SR one, the BF ring had been placed 180° off in yaw. We suspended the BF from the load gauge adapter, reconfigured the BF jacks to support the ring instead of the BF, and rotated the ring. Mark corrected the procedure.

Plan for week of 6/11

  • Mark Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Tue-Fri (Mon is compensation day for f2f.)
  • --
  • Route cables through SF-BF flying saucer up to bottom of SF.
  • Add minimal ballast mass to SF (rough balance only) and weigh SF/... section.
  • Adjust BF trim mass.
  • Readjust payload.
  • Take TFs.
  • Cable, test SF LVDT and FR.
  • Add calculated ballast to SF.
  • Finish tuning F0 #3 for SR3.
  • Park F0 #1 (for SR2) in top of SR3 assembly frame.
  • Move F0 #3 behind SR3.
  • Move F0 #1 to "factory" area (in front of SRM) and start rebuild.

Plan for week of 6/18

  • Mark Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Mon-Fri.
  • --
  • Install PI.
  • Suspend SF/... section.
  • Lots of cabling.

To-Do Lists, Schedule

Vacation Info

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)