Differences between revisions 26 and 367 (spanning 341 versions)
Revision 26 as of 2016-06-09 14:47:55
Size: 2920
Editor: MarkBarton
Comment:
Revision 367 as of 2019-01-11 14:17:35
Size: 3962
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary
  * Fabian finished dummy BS assembly.
  * Mark and Tatsumi-san glued magnets into both types of BS optic flags, and discs into BS IM flags. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1815 |klog]] Two optic flags had to be redone because the magnets moved while the glue was drying. Hirata-san helped remove the magnets with acetone in the ultrasonic cleaner. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1818|klog]]
  * Tatsumi-san, Fabian and Mark took the dummy BS to Kashiwa and glued the flags and prisms. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1821|klog]] We will check status on Mon 6/13.
  * Hirata-san measured another filter.
  * Hirata-san washed a batch of parts.
  * Hirata-san modified the design of the parts of the assembly frame supporting the BF and SF to include bushings for smoother movement.
  * Hirata-san worked on work platforms for the installation.
  * Hirata-san looked for a crane scale for use at the site. (We decided the 500-kg version of the 200-kg one used at TAMA. It is the same price and has the same 100-g resolution for the first 250 kg.)
  * Hirata-san worked on making some guide parts for the PI installation (Misumi parts with minor additional machining from ATC).
  * We finalized a design for simple SS mirror parts for the dummy BS with Akutsu-san. They will be made by ATC.
  * Mark worked on list of items for purchase in FY2016 and on the schedule.
  * Fabian did more work on the IM assembly. It is nearly done and he will start on the RM next week.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
  * Feedthrough Adapters
   * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote.
  * Can we make SR wire breakers bigger?
   * Fukushima-san will start on machining test soon (as of 5/27).
  * Not enough crane height problem (Hirata, Saito) - no action since last week
  * Installation stuff
   * Crane scale - quote received
   * Work platforms - quote received
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
  * Clean bag - expected 6/8.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
=== Type B (Mark) ===
==== Report for week of 12/17 ====
 * BS
  * We opened the top of the BS tank after the vent.
  * We inspected the BS F0 blades for cracks but still didn't find any.
  * We removed the arc weights and geophones, and added new longer studs for the arc weights and new cables for the geophones. We then put back the original arc weights and new geophones.
  * We measured the geometry of the various IP items to check the IP diagonalization matrices.
  * We installed the new double-sided F0 FR. We were not close to needing to add the optional !CuBe spring. Unfortunately the FR had rather less friction but still didn't work. After checking a bunch of possibilities and comparing against SRM (also non-working) and SR2/SR3 (working), we suspect the carriage may be assembled upside down, with the metal plate below and the PEEK plate above. We will try changing it next week.
 * We adjusted the F0 keystone trim mass and were able to get it to sit at CAD nominal height at nominal temperature (24.9°C) with mid-range FR and modest extra mass (413 g). Interestingly, we noticed that removing the arc weights and/or geophones reduced the load capacity by a few hundred grams.
 * We measured the total range of the IP FRs in steps and set them to mid-range in preparation for tuning the IP frequency and (re-)centering the IP.
 * SRM
  * We borrowed an LED from SR2 and set the pitch of the SRM optic.
  * We found the SRM front end had crashed and could not be properly reset by cycling the power from the web interface. Yamamoto-san eventually got it working for us, although it didn't seem to take more than restarting the user and IOP models.
  * We sealed and retested the new geophones originally intended for SRM, but decided to use them on BS instead.
  * We installed the two OL viewports. We also tried to install the camera viewport but we couldn't get the Cu gasket to sit in the recess, so we gave up and will probably reallocate the camera viewport to SR3 for now (where it will go on a different type of flange which we've had success with. Saito-san says that we can get help with the SRM flange from Mirapro on 1/28.
 * SR3
  * We opened the top of the tank briefly to inspect the configuration of the F0 FR, but didn't do any significant work.
  * Hirose-san inspected inside the bottom part of the chamber and found some dust, so he recommended we wipe with Vectra-Alpha wipes (IPA-resistant type) and IPA. he gave us a powerful LED flashlight array and asked us to use it to look for dust in all the chambers.
 * Etc
  * We gave Simon a list of items we still need for the SRM OL. He seemed to think that they should be in stock at Kamioka and will help us look for them next Tue 1/15.
  * Mark and Enzo booked flights for the KAGRA International Workshop.
  * Mark had to schedule a trip to Australia for the week of 1/21 to attend to family business.
==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]

==== Plan for week of 1/7 ====
 * Make sure BS is floating, recenter OL to capture current yaw position.
 * Vent BS.
 * Inspect BS F0 blades for cracks.
 * Install new BS F0 FR, and (if necessary) auxiliary CuBe spring.
 * Confirm geometry of LVDTs, geophones, FRs etc and update T1707205 if necessary.
 * Replace geophone preamps and cables (to fix noise, offset, pinout flip issues).
 * Add more mass to IP to get lower frequency.
 * Adjust all GAS filters to near mid-range (using keystone mass for F0 as much as possible, and FR+LVDT for SF and BF).

==== Vacation/Etc Info ====
 * Mark and Enzo: KAGRA International Workshop in Perugia, 2/14-16.
 * Terrence: back at Kamioka from 1/7.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 12/17

  • BS
    • We opened the top of the BS tank after the vent.
    • We inspected the BS F0 blades for cracks but still didn't find any.
    • We removed the arc weights and geophones, and added new longer studs for the arc weights and new cables for the geophones. We then put back the original arc weights and new geophones.
    • We measured the geometry of the various IP items to check the IP diagonalization matrices.
    • We installed the new double-sided F0 FR. We were not close to needing to add the optional CuBe spring. Unfortunately the FR had rather less friction but still didn't work. After checking a bunch of possibilities and comparing against SRM (also non-working) and SR2/SR3 (working), we suspect the carriage may be assembled upside down, with the metal plate below and the PEEK plate above. We will try changing it next week.

  • We adjusted the F0 keystone trim mass and were able to get it to sit at CAD nominal height at nominal temperature (24.9°C) with mid-range FR and modest extra mass (413 g). Interestingly, we noticed that removing the arc weights and/or geophones reduced the load capacity by a few hundred grams.
  • We measured the total range of the IP FRs in steps and set them to mid-range in preparation for tuning the IP frequency and (re-)centering the IP.
  • SRM
    • We borrowed an LED from SR2 and set the pitch of the SRM optic.
    • We found the SRM front end had crashed and could not be properly reset by cycling the power from the web interface. Yamamoto-san eventually got it working for us, although it didn't seem to take more than restarting the user and IOP models.
    • We sealed and retested the new geophones originally intended for SRM, but decided to use them on BS instead.
    • We installed the two OL viewports. We also tried to install the camera viewport but we couldn't get the Cu gasket to sit in the recess, so we gave up and will probably reallocate the camera viewport to SR3 for now (where it will go on a different type of flange which we've had success with. Saito-san says that we can get help with the SRM flange from Mirapro on 1/28.
  • SR3
    • We opened the top of the tank briefly to inspect the configuration of the F0 FR, but didn't do any significant work.
    • Hirose-san inspected inside the bottom part of the chamber and found some dust, so he recommended we wipe with Vectra-Alpha wipes (IPA-resistant type) and IPA. he gave us a powerful LED flashlight array and asked us to use it to look for dust in all the chambers.
  • Etc
    • We gave Simon a list of items we still need for the SRM OL. He seemed to think that they should be in stock at Kamioka and will help us look for them next Tue 1/15.
    • Mark and Enzo booked flights for the KAGRA International Workshop.
    • Mark had to schedule a trip to Australia for the week of 1/21 to attend to family business.

To-Do Lists, Schedule

Plan for week of 1/7

  • Make sure BS is floating, recenter OL to capture current yaw position.
  • Vent BS.
  • Inspect BS F0 blades for cracks.
  • Install new BS F0 FR, and (if necessary) auxiliary CuBe spring.

  • Confirm geometry of LVDTs, geophones, FRs etc and update T1707205 if necessary.
  • Replace geophone preamps and cables (to fix noise, offset, pinout flip issues).
  • Add more mass to IP to get lower frequency.
  • Adjust all GAS filters to near mid-range (using keystone mass for F0 as much as possible, and FR+LVDT for SF and BF).

Vacation/Etc Info

  • Mark and Enzo: KAGRA International Workshop in Perugia, 2/14-16.
  • Terrence: back at Kamioka from 1/7.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)