2842
Comment:
|
1275
|
Deletions are marked like this. | Additions are marked like this. |
Line 6: | Line 6: |
==== Report for week of 3/26 ==== | ==== Report for week of 7/30 ==== * ==== Plan for week of 8/6 ==== * Mark, Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri. * Kozu-kun works at Mozumi Mon, Fri, and Thu afternoon. |
Line 8: | Line 12: |
BFs: | ===== SR3 ===== * Finalize optic pitch, OSEM alignment. * Do TFs with temporary OL. * Install final OL. * Hook LBB, add ballast mass, set up temporary OL (horizontal beam, pitch/yaw only). |
Line 10: | Line 18: |
* BF No. 1: * Fujii-san finished tuning. * Enzo wired the LVDT, Picomotor and StepperMotor. * We measured the keystone tilt at 4 different points and it was at 65.5, 65.5, 65.5 and 65.5. So with the differences of 0.1 mm we think we can tolarate this differences. * We added cable clamps to the base. * BF No.7: * Fujii-san disassemble the blades corresponding to the BS and we assemble the SR type blades. SFs: * Hirata-san and Tanioka-san set up the frame to check the SFs. * SF (B2-5): * Hirata-san, Fujii-san and Tanioka-san checked the optimal load with and without cap. The optimal load changes about 200[g]. * We measured the keystone tilt at x points: 65.5mm, 65.5mm, 65.5mm, and 65.5mm. * SF (B2-6): * Hirata-san, Fujii-san and Tanioka-san checked the optimal load with and without cap (On going?). * We measured the keystone tilt at x points: 65.5mm, 65.5mm, 65.5mm, and 65.5mm. SR3/SRM: * Kozu-kun and Enzo finished the SR3 in-air cabling. * Enzo prepared the SR3 and SRM rack in parallel (On going). BS: * Kozu-kun and Enzo helped Enomoto-san troubleshooting the BS Oplev issue (On going). * We finished tuning of BF No. 1. * We wired the LVDT, Picomotor and StepperMotor of BF No. 1. * We finished tuning of BF No. 7. * We wired the LVDT, Picomotor and StepperMotor of BF No. 7. * SF check (Hirata-san++). * We checked the load capacity with and without the cap. * We checked fit of caps. For the SF No. * Add cable clamps to bases. * Add cable clamps and Cu segments to caps (only if they fit well). * Cable LVDTs and steppers. * We finished the SR3 in-air cabling. ==== Plan for week of 4/2 ==== * Mark at Mitaka Mon, Kamioka from Tue. * Shoda-san at Mitaka * Others at Kamioka * -- * Glue SR3 (if available) * Build 2xIM, 2xIRM (if parts available - due 3/30) ==== Plan for week of 4/9 ==== * Shoda-san at Mitaka * Others at Kamioka * -- * Finish IMs and IRMs * Build 1xRM ==== Plan for week of 4/16 ==== * Start SR3 Hang? ==== Plan for week of 4/23 ==== * F0 blade prototype test ==== Plan for week of 4/30 ==== * Golden Week! |
===== SR2 ===== * Add estimated final ballast mass. * Do PI cable routing. * Adjust ballast/trim mass, with reserve for cables. ===== SRM ===== * Assemble metal mass. * Glue prisms, flags. * Reconfigure, align assembly frame. * Tune F0 for SRM. * Add LBB blade units, cable clamps etc. * Check PI coil connections, IP LVDT magnets. |
Line 88: | Line 32: |
* [[KAGRA/Subgroups/VIS/TypeB/March2018]] * [[KAGRA/Subgroups/VIS/TypeB/April2018]] |
|
Line 92: | Line 34: |
* [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]] | * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]] |
Line 95: | Line 37: |
* Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun) * Fabian vacation, 3/26-4/27 (then gone). |
* Terrence: 8/24-26 f2f, then returns to Hong Kong. * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile. |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 7/30
Plan for week of 8/6
- Mark, Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri.
- Kozu-kun works at Mozumi Mon, Fri, and Thu afternoon.
SR3
- Finalize optic pitch, OSEM alignment.
- Do TFs with temporary OL.
- Install final OL.
- Hook LBB, add ballast mass, set up temporary OL (horizontal beam, pitch/yaw only).
SR2
- Add estimated final ballast mass.
- Do PI cable routing.
- Adjust ballast/trim mass, with reserve for cables.
SRM
- Assemble metal mass.
- Glue prisms, flags.
- Reconfigure, align assembly frame.
- Tune F0 for SRM.
- Add LBB blade units, cable clamps etc.
- Check PI coil connections, IP LVDT magnets.
To-Do Lists, Schedule
Vacation Info
- Terrence: 8/24-26 f2f, then returns to Hong Kong.
- Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.