Differences between revisions 262 and 298 (spanning 36 versions)
Revision 262 as of 2018-03-29 22:04:57
Size: 2849
Editor: EnzoTapia
Comment:
Revision 298 as of 2018-06-22 13:35:18
Size: 3497
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 6: Line 6:
==== Report for week of 3/26 ==== ==== Report for week of 6/18 ====
 * Mark checked the health of the suspensions after an earthquake on Monday morning. The BS watchdog tripped and there was a few µrad change in the pointing, but otherwise it was fine. SR3 and SR2 were also fine.
 * Mark, Enzo and Terrence finalized the trim mass on the BF to set the SF keystone height and BF pitch/roll.
 * They weighed the SF/... section. With no internal trim mass in the SF but with the flying saucer and rod, but with 2 Promec masses for rough balance, it was 255.4 kg, so allowing 1 kg for cables and fine trim mass, we would like a PI load capacity of 256.4 kg.
 * Enzo and Terrence cabled and tested the SF fishing rod, and reversed the connections on the SF LVDT actuation to bring it to standard polarity.
 * Mark and Enzo made many improvements to the Type B MEDM screens.
 * Enzo and Mark measured the BF and SF bounce frequencies (with the other keystone locked).
 * Enzo replaced a HPCD that seemed to have failed during the bounce test (but had just had a watchdog trip), and then replaced the replacement, which really did fail. It turns out we need to avoid applying more than about 25000 counts of GAS actuation.
 * Enzo offloaded the BF LVDT actuator with the BF FR to remove the need for a 10000 ct offset.
 * Hirata-san and Kozu-kun struggled to tune the top filter for SR3 - see klogs 5310, 5324, 5337, xxxx. At first the results were somewhat unrepeatable, with high frequency and low load capacity. This was improved by using a torque wrench (set to 50 N.m) to tighten the blade base clamp screws, retightening the blade tip screws (which had worked loose) and tightening the collar on the end of the shaft of the magic wand. Eventually we decided on a compression of 30 mm, which should give a frequency of around 0.5 Hz if we remove one Cu damper segment from the SF. Hirata-san applied the 30 mm compression but we skipped another round of testing with the dummy load and will go straight to hanging the SF/... section on the assembly frame.
 * We wrapped PI #1 (for SR2) and craned it from behind SR3 to behind SRM. We can now wrap PI #3 (for SR3) and crane it straight to the assembly frame.
 
==== Plan for week of 6/25 ====
 * Mark, Enzo, Hirata-san, Terrence at Kamioka Mon-Fri.
 * Kozu-kun at Kamioka except Thu.
 * --
 * Shutdown Type B controls (as far as possible) in preparation for risk of accidental power outage during electrical work on 6/26.
 * Prepare SF damper magnet ring and rods.
 * Install PI #3 in SR3 AF.
 * Suspend SF/... section.
 * Lots of cable routing and testing.
 * Move PI #1 (for SR2) over SRM tank to work area, install blades and tune.
Line 8: Line 29:
BFs:

 * BF No. 1:
  * Fujii-san finished tuning.
  * Enzo wired the LVDT, Picomotor and Steppermotor.
  * We measured the keystone tilt at 4 different points and it was at 65.5, 65.5, 65.5 and 65.5.
    So with the differences of 0.1 mm we think we can tolarate this differences.
  * We added cable clamps to the base.

 * BF No.7:
  * Fujii-san disassemble the blades corresponding to the BS and we assemble the SR type blades.

SFs:

 * Hirata-san and Tanioka-san set up the frame to check the SFs.

 * SF (B2-5):
  * Hirata-san, Fujii-san and Tanioka-san checked the optimal load with and without cap. The optimal load changes about 200[g].
  * We measured the keystone tilt at x points: 65.5mm, 65.5mm, 65.5mm, and 65.5mm.

 * SF (B2-6):
  * Hirata-san, Fujii-san and Tanioka-san checked the optimal load with and without cap (On going?).
  * We measured the keystone tilt at x points: 65.5mm, 65.5mm, 65.5mm, and 65.5mm.

SR3/SRM:

 * Kozu-kun and Enzo finished the SR3 in-air cabling.

 * Enzo prepared the SR3 and SRM rack in parallel (On going).

BS:

 * Kozu-kun and Enzo helped Enomoto-san troubleshooting the BS Oplev issue (On going).


Others:

 * We finished tuning of BF No. 1.
  * We wired the LVDT, Picomotor and StepperMotor of BF No. 1.
  

 * We finished tuning of BF No. 7.
  * We wired the LVDT, Picomotor and StepperMotor of BF No. 7.



 * SF check (Hirata-san++).
  * We checked the load capacity with and without the cap.
  * We checked fit of caps. For the SF No.
  * Add cable clamps to bases.
  * Add cable clamps and Cu segments to caps (only if they fit well).
  * Cable LVDTs and steppers.

 * We finished the SR3 in-air cabling.

==== Plan for week of 4/2 ====
 * Mark at Mitaka Mon, Kamioka from Tue.
 * Shoda-san at Mitaka
 * Others at Kamioka
==== Plan for week of 7/2 ====
 * Mark, Hirata-san, Terrence at Kamioka Mon-Fri.
 * Enzo at Kamioka Mon-Wed.
 * Kozu-kun at Kamioka except Wed.
Line 68: Line 34:
 * Glue SR3 (if available)
 * Build 2xIM, 2xIRM (if parts available - due 3/30)

==== Plan for week of 4/9 ====
 * Shoda-san at Mitaka
 * Others at Kamioka
 * --
 * Finish IMs and IRMs
 * Build 1xRM

==== Plan for week of 4/16 ====
 * Start SR3 Hang?

==== Plan for week of 4/23 ====
 * F0 blade prototype test

==== Plan for week of 4/30 ====
  * Golden Week!
 * Lock suspension.
 * Remove tank lid and raise LBB damper rings.
 * Crane suspension into tank.
Line 88: Line 39:
 * [[KAGRA/Subgroups/VIS/TypeB/March2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/April2018]]
Line 92: Line 41:
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]  * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]
Line 95: Line 44:
 * Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
 * Fabian vacation, 3/26-4/27 (then gone).
 * Kozu-kun: 7/4 Tokyo.
 * Enzo: 7/5-6 NAOJ Party, Mitaka.
 * Terrence: 8/24-26 f2f, then returns to Hong Kong.
 * Enzo: 9/14 JPS, 9/15 through 10/18 vacation in Chile.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 6/18

  • Mark checked the health of the suspensions after an earthquake on Monday morning. The BS watchdog tripped and there was a few µrad change in the pointing, but otherwise it was fine. SR3 and SR2 were also fine.
  • Mark, Enzo and Terrence finalized the trim mass on the BF to set the SF keystone height and BF pitch/roll.
  • They weighed the SF/... section. With no internal trim mass in the SF but with the flying saucer and rod, but with 2 Promec masses for rough balance, it was 255.4 kg, so allowing 1 kg for cables and fine trim mass, we would like a PI load capacity of 256.4 kg.
  • Enzo and Terrence cabled and tested the SF fishing rod, and reversed the connections on the SF LVDT actuation to bring it to standard polarity.
  • Mark and Enzo made many improvements to the Type B MEDM screens.
  • Enzo and Mark measured the BF and SF bounce frequencies (with the other keystone locked).
  • Enzo replaced a HPCD that seemed to have failed during the bounce test (but had just had a watchdog trip), and then replaced the replacement, which really did fail. It turns out we need to avoid applying more than about 25000 counts of GAS actuation.
  • Enzo offloaded the BF LVDT actuator with the BF FR to remove the need for a 10000 ct offset.
  • Hirata-san and Kozu-kun struggled to tune the top filter for SR3 - see klogs 5310, 5324, 5337, xxxx. At first the results were somewhat unrepeatable, with high frequency and low load capacity. This was improved by using a torque wrench (set to 50 N.m) to tighten the blade base clamp screws, retightening the blade tip screws (which had worked loose) and tightening the collar on the end of the shaft of the magic wand. Eventually we decided on a compression of 30 mm, which should give a frequency of around 0.5 Hz if we remove one Cu damper segment from the SF. Hirata-san applied the 30 mm compression but we skipped another round of testing with the dummy load and will go straight to hanging the SF/... section on the assembly frame.
  • We wrapped PI #1 (for SR2) and craned it from behind SR3 to behind SRM. We can now wrap PI #3 (for SR3) and crane it straight to the assembly frame.

Plan for week of 6/25

  • Mark, Enzo, Hirata-san, Terrence at Kamioka Mon-Fri.
  • Kozu-kun at Kamioka except Thu.
  • --
  • Shutdown Type B controls (as far as possible) in preparation for risk of accidental power outage during electrical work on 6/26.
  • Prepare SF damper magnet ring and rods.
  • Install PI #3 in SR3 AF.
  • Suspend SF/... section.
  • Lots of cable routing and testing.
  • Move PI #1 (for SR2) over SRM tank to work area, install blades and tune.

Plan for week of 7/2

  • Mark, Hirata-san, Terrence at Kamioka Mon-Fri.
  • Enzo at Kamioka Mon-Wed.
  • Kozu-kun at Kamioka except Wed.
  • --
  • Lock suspension.
  • Remove tank lid and raise LBB damper rings.
  • Crane suspension into tank.

To-Do Lists, Schedule

Vacation Info

  • Kozu-kun: 7/4 Tokyo.
  • Enzo: 7/5-6 NAOJ Party, Mitaka.
  • Terrence: 8/24-26 f2f, then returns to Hong Kong.
  • Enzo: 9/14 JPS, 9/15 through 10/18 vacation in Chile.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)