Differences between revisions 263 and 265 (spanning 2 versions)
Revision 263 as of 2018-03-29 22:35:47
Size: 3049
Editor: EnzoTapia
Comment:
Revision 265 as of 2018-03-30 09:23:48
Size: 2896
Editor: EnzoTapia
Comment:
Deletions are marked like this. Additions are marked like this.
Line 13: Line 13:
  * We measured the keystone tilt at 4 different points and it was at 65.5, 65.5, 65.5 and 65.5.
    So with
the differences of 0.1 mm we think we can tolarate this differences.
  * We measured the keystone tilt at different points and the diferences are within 0.1[mm]
Line 46: Line 45:
Others:

 * We finished tuning of BF No. 1.
  * We wired the LVDT, Picomotor and StepperMotor of BF No. 1.
  

 * We finished tuning of BF No. 7.
  * We wired the LVDT, Picomotor and StepperMotor of BF No. 7.
Line 71: Line 62:
 * Glue SR3 (if available)
 * Build 2xIM, 2xIRM (if parts available - due 3/30)
 * Finish BFs tasks (cabling +calibration)
 * Finish SFs tasks (cabling +calibration)
 * Add cable clamps to bases.
 * Glue SR3 mirror?
 * Add cable clamps and Cu segments to caps (only if they fit well).
 * Build 2xIM, 2xIRM
Line 88: Line 83:
  * Golden Week!   * Golden Week!!

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 3/26

BFs:

  • BF No. 1:
    • Fujii-san finished tuning. Optimal load: 52.15[kg]. Resonance frequency: 0.36[Hz]. Optimal height: 64.7[mm].
    • We wired the LVDT, Picomotor and Steppermotor.
    • We measured the keystone tilt at different points and the diferences are within 0.1[mm]
    • We added cable clamps to the base.
  • BF No.7:
    • Fujii-san replaced the blades corresponding to the BS and for the SR type blades.
    • The yoke position was corrected.
    • The fishing rod was assembled.
    • Compression tuning is ongoing.

SFs:

  • Hirata-san and Tanioka-san set up the frame to check the SFs.
  • SF (B2-5):
    • Hirata-san, Fujii-san and Tanioka-san checked the optimal load with and without cap. The optimal load changes about 250[g].
    • We measured the keystone tilt at different points, and the diferences are within 0.1[mm]
  • SF (B2-6):
    • Hirata-san, Fujii-san and Tanioka-san checked the optimal load with and without cap (On going?).
    • We measured the keystone tilt at different points, and the diferences are within 0.3[mm]

SR3/SRM:

  • Kozu-kun and Enzo finished the SR3 in-air cabling.
  • Enzo prepared the SR3 and SRM rack in parallel (On going).

BS:

  • Kozu-kun and Enzo helped Enomoto-san troubleshooting the BS Oplev issue (On going).
  • SF check (Hirata-san++).
    • We checked the load capacity with and without the cap.
    • We checked fit of caps. For the SF No.
    • Add cable clamps to bases.
    • Add cable clamps and Cu segments to caps (only if they fit well).
    • Cable LVDTs and steppers.
  • We finished the SR3 in-air cabling.

Plan for week of 4/2

  • Mark at Mitaka Mon, Kamioka from Tue.
  • Shoda-san at Mitaka
  • Others at Kamioka
  • --
  • Finish BFs tasks (cabling +calibration)
  • Finish SFs tasks (cabling +calibration)
  • Add cable clamps to bases.
  • Glue SR3 mirror?
  • Add cable clamps and Cu segments to caps (only if they fit well).
  • Build 2xIM, 2xIRM

Plan for week of 4/9

  • Shoda-san at Mitaka
  • Others at Kamioka
  • --
  • Finish IMs and IRMs
  • Build 1xRM

Plan for week of 4/16

  • Start SR3 Hang?

Plan for week of 4/23

  • F0 blade prototype test

Plan for week of 4/30

  • Golden Week!!

To-Do Lists, Schedule

Vacation Info

  • Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
  • Fabian vacation, 3/26-4/27 (then gone).

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)