 * Type B Past Week Summary
  * Fabian finished dummy BS assembly.
  * Mark and Tatsumi-san glued magnets into both types of BS optic flags, and discs into BS IM flags. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1815 |klog]] Two optic flags had to be redone because the magnets moved while the glue was drying. Hirata-san helped remove the magnets with acetone in the ultrasonic cleaner. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1818|klog]]
  * Tatsumi-san, Fabian and Mark took the dummy BS to Kashiwa and glued the flags and prisms. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1821|klog]] We will check status on Mon 6/13.
  * Hirata-san moved in another filter for testing (but didn't get to measure it).
  * Hirata-san washed a batch of parts.
  * Hirata-san modified the design of the parts of the assembly frame supporting the BF and SF to include bushings for smoother movement.
  * Hirata-san researched and ordered a crane scale for use at the site. (We decided the 500-kg version of the 200-kg one used at TAMA. It is the same price and has the same 100-g resolution for the first 250 kg.)
  * Hirata-san worked on making some guide parts for the PI installation (Misumi parts with minor additional machining from ATC).
  * We finalized a design for simple SS mirror parts for the dummy BS with Akutsu-san. They will be made by ATC.
  * Mark worked on list of items for purchase in FY2016 and on the schedule.
  * Fabian did more work on the IM assembly. It is nearly done and he will start on the RM next week. There were some issues with crimping connectors to wires for making pico adapter cables.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
  * Feedthrough Adapters
   * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote.
  * Can we make SR wire breakers bigger?
   * Fukushima-san will start on machining test soon (as of 5/27).
  * Not enough crane height problem (Hirata, Saito) - no action since last week
  * Installation stuff
   * Crane scale - quote received
   * Work platforms - quote received
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
  * Clean bag - expected 6/8.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
=== Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Fabian, Hirata-san, Yoshioka-kun):
 * We reconfigured the top of the assembly frame.
 * We cleaned the assembly frame, blowing dust out of the grooves and wiping all surfaces.
 * We recentered the optic table in the bottom of the frame and adjusted the frame until the top was centered over the optic table. We also recentered the trolleys.
 * We re-installed, centered and leveled the IM.
 * We solved two issues with the new wire clamps:
  * Some holes were not properly threaded - Hirata-san retapped them.
  * Some locating pins were loose - we glued them.
 * We mounted the BS mirror box on the trolley and brought it under the IM.
 * We installed the winch system and the 300 µm wires for the BS.
 * We set up the optical lever.
 * Hirata-san finished the new BF. We moved the old BF out of the cleanbooth and the new one in.

==== Plan for week of 8/7 ====
Site closure: Friday<<BR>>
Kamioka: Mark (Mon-Thu), Enzo (Tue-Thu), Yoshioka-kun (Tue, Wed), Ohishi (TBD).<<BR>>
Mitaka: Hirata-san (Mon-Fri)<<BR>>
Vacation: Enzo (Mon), Fabian (Mon-Fri)<<BR>>
 * Finish hanging BS
 * Hang RM.
 * Weigh/trim BS/RM/IM.
 * Suspend BS/RM/IM, add IRM.
 * Lay new in-air OSEM cables.

==== Plan for week of 8/14 ====
Site closure: Mon, Tue<<BR>>
Kamioka: Mark (Wed-Fri), Enzo (Wed-Fri), Yoshioka-kun (Wed, Fri), Ohishi (TBD).<<BR>>
Mitaka: Hirata-san (Mon-Fri)<<BR>>
Vacation: Fabian (Mon-Fri)

Vacation Info:
Enzo: Sat 7/22 through Sun 8/6
Fabian: Fri 8/4 through Mon 8/21
Mark: TBD Mid-Oct

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Fabian, Hirata-san, Yoshioka-kun):

  • We reconfigured the top of the assembly frame.
  • We cleaned the assembly frame, blowing dust out of the grooves and wiping all surfaces.
  • We recentered the optic table in the bottom of the frame and adjusted the frame until the top was centered over the optic table. We also recentered the trolleys.
  • We re-installed, centered and leveled the IM.
  • We solved two issues with the new wire clamps:
    • Some holes were not properly threaded - Hirata-san retapped them.
    • Some locating pins were loose - we glued them.
  • We mounted the BS mirror box on the trolley and brought it under the IM.
  • We installed the winch system and the 300 µm wires for the BS.
  • We set up the optical lever.
  • Hirata-san finished the new BF. We moved the old BF out of the cleanbooth and the new one in.

Plan for week of 8/7

Site closure: Friday
Kamioka: Mark (Mon-Thu), Enzo (Tue-Thu), Yoshioka-kun (Tue, Wed), Ohishi (TBD).
Mitaka: Hirata-san (Mon-Fri)
Vacation: Enzo (Mon), Fabian (Mon-Fri)

  • Finish hanging BS
  • Hang RM.
  • Weigh/trim BS/RM/IM.
  • Suspend BS/RM/IM, add IRM.
  • Lay new in-air OSEM cables.

Plan for week of 8/14

Site closure: Mon, Tue
Kamioka: Mark (Wed-Fri), Enzo (Wed-Fri), Yoshioka-kun (Wed, Fri), Ohishi (TBD).
Mitaka: Hirata-san (Mon-Fri)
Vacation: Fabian (Mon-Fri)

Vacation Info: Enzo: Sat 7/22 through Sun 8/6 Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct