 * Type B Past Week Summary
  * Fabian finished dummy BS assembly.
  * Mark and Tatsumi-san glued magnets into both types of BS optic flags, and discs into BS IM flags. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1815 |klog]] Two optic flags had to be redone because the magnets moved while the glue was drying. Hirata-san helped remove the magnets with acetone in the ultrasonic cleaner. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1818|klog]]
  * Tatsumi-san, Fabian and Mark took the dummy BS to Kashiwa and glued the flags and prisms. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1821|klog]] We will check status on Mon 6/13.
  * Hirata-san moved in another filter for testing (but didn't get to measure it).
  * Hirata-san washed a batch of parts.
  * Hirata-san modified the design of the parts of the assembly frame supporting the BF and SF to include bushings for smoother movement.
  * Hirata-san researched and ordered a crane scale for use at the site. (We decided the 500-kg version of the 200-kg one used at TAMA. It is the same price and has the same 100-g resolution for the first 250 kg.)
  * Hirata-san worked on making some guide parts for the PI installation (Misumi parts with minor additional machining from ATC).
  * We finalized a design for simple SS mirror parts for the dummy BS with Akutsu-san. They will be made by ATC.
  * Mark worked on list of items for purchase in FY2016 and on the schedule.
  * Fabian did more work on the IM assembly. It is nearly done and he will start on the RM next week. There were some issues with crimping connectors to wires for making pico adapter cables.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
  * Feedthrough Adapters
   * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote.
  * Can we make SR wire breakers bigger?
   * Fukushima-san will start on machining test soon (as of 5/27).
  * Not enough crane height problem (Hirata, Saito) - no action since last week
  * Installation stuff
   * Crane scale - quote received
   * Work platforms - quote received
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
  * Clean bag - expected 6/8.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
=== Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Ohishi-san, Enzo, Yoshioka-kun, Kozu-kun):
 * We finished installing the RM OSEMs and installed the new Type5-2.2 and 5-2.4 OSEM cables.
 * We hung the RM and set its pitch.
 * We doubled-checked the BS and RM pitch, tightened the clamps and removed the winch system.
 * We installed the bottom section of the security structure to protect the RM/BS.
 * We lifted the IM/RM/BS section and weighed it. It was about 1.25 kg too heavy for the new BF, so we improvised a lighter set of ballast masses.
 * We installed the section of the security structure up to the BF ring, and the BF crossbars and jacks of the assembly frame.
 * We brought in the new BF.
 * We installed the BF-IRM rods and IRM top plate.
 * We reinstalled the IM flags and other items that had been taken off to use the winch system.
 * We hooked the BF-IM rod (with hex cable clamp). (We did not unlock the BF keystone.)
 * We cabled and tested the IM-PIT, IM-ROL and IM-YAW picos and the BF FR stepper (but not, yet, the BF LVDT).

==== Plan for week of 8/14 ====
Site closure: Mon, Tue<<BR>>
Vacation: Fabian (Mon-Fri)<<BR>>
Kamioka: Mark (Wed-Fri), Enzo (Wed-Fri), Yoshioka-kun (Wed, Fri), Ohishi (Thu-Fri).<<BR>>
 * Remove LBB blade units from PI, then remove blades and send for remachining.
 * Remove LBB rings from chamber and send for recleaning.
 * Unlock BF, adjust ballast masses on IM/RM/BS to correct pitch/roll/vertical.
 * Test, calibrate BF LVDT.
Mitaka: Hirata-san (Mon-Fri)<<BR>>
 * SR Stuff

==== Plan for week of 8/21 ====
Vacation: Fabian (Mon)<<BR>>
Kamioka: Mark, Ohishi, Fabian (Tue-Fri), Enzo, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun.

Vacation Info:
Fabian: Fri 8/4 through Mon 8/21
Mark: TBD Mid-Oct

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Ohishi-san, Enzo, Yoshioka-kun, Kozu-kun):

  • We finished installing the RM OSEMs and installed the new Type5-2.2 and 5-2.4 OSEM cables.
  • We hung the RM and set its pitch.
  • We doubled-checked the BS and RM pitch, tightened the clamps and removed the winch system.
  • We installed the bottom section of the security structure to protect the RM/BS.
  • We lifted the IM/RM/BS section and weighed it. It was about 1.25 kg too heavy for the new BF, so we improvised a lighter set of ballast masses.
  • We installed the section of the security structure up to the BF ring, and the BF crossbars and jacks of the assembly frame.
  • We brought in the new BF.
  • We installed the BF-IRM rods and IRM top plate.
  • We reinstalled the IM flags and other items that had been taken off to use the winch system.
  • We hooked the BF-IM rod (with hex cable clamp). (We did not unlock the BF keystone.)
  • We cabled and tested the IM-PIT, IM-ROL and IM-YAW picos and the BF FR stepper (but not, yet, the BF LVDT).

Plan for week of 8/14

Site closure: Mon, Tue
Vacation: Fabian (Mon-Fri)
Kamioka: Mark (Wed-Fri), Enzo (Wed-Fri), Yoshioka-kun (Wed, Fri), Ohishi (Thu-Fri).

  • Remove LBB blade units from PI, then remove blades and send for remachining.
  • Remove LBB rings from chamber and send for recleaning.
  • Unlock BF, adjust ballast masses on IM/RM/BS to correct pitch/roll/vertical.
  • Test, calibrate BF LVDT.

Mitaka: Hirata-san (Mon-Fri)

  • SR Stuff

Plan for week of 8/21

Vacation: Fabian (Mon)
Kamioka: Mark, Ohishi, Fabian (Tue-Fri), Enzo, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun.

Vacation Info: Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct