Differences between revisions 27 and 190 (spanning 163 versions)
Revision 27 as of 2016-06-10 11:41:20
Size: 3001
Editor: MarkBarton
Comment:
Revision 190 as of 2017-09-14 20:08:31
Size: 2060
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary
  * Fabian finished dummy BS assembly.
  * Mark and Tatsumi-san glued magnets into both types of BS optic flags, and discs into BS IM flags. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1815 |klog]] Two optic flags had to be redone because the magnets moved while the glue was drying. Hirata-san helped remove the magnets with acetone in the ultrasonic cleaner. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1818|klog]]
  * Tatsumi-san, Fabian and Mark took the dummy BS to Kashiwa and glued the flags and prisms. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1821|klog]] We will check status on Mon 6/13.
  * Hirata-san moved in another filter for testing (but didn't get to measure it).
  * Hirata-san washed a batch of parts.
  * Hirata-san modified the design of the parts of the assembly frame supporting the BF and SF to include bushings for smoother movement.
  * Hirata-san researched and ordered a crane scale for use at the site. (We decided the 500-kg version of the 200-kg one used at TAMA. It is the same price and has the same 100-g resolution for the first 250 kg.)
  * Hirata-san worked on making some guide parts for the PI installation (Misumi parts with minor additional machining from ATC).
  * We finalized a design for simple SS mirror parts for the dummy BS with Akutsu-san. They will be made by ATC.
  * Mark worked on list of items for purchase in FY2016 and on the schedule.
  * Fabian did more work on the IM assembly. It is nearly done and he will start on the RM next week. There were some issues with crimping connectors to wires for making pico adapter cables.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
  * Feedthrough Adapters
   * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote.
  * Can we make SR wire breakers bigger?
   * Fukushima-san will start on machining test soon (as of 5/27).
  * Not enough crane height problem (Hirata, Saito) - no action since last week
  * Installation stuff
   * Crane scale - quote received
   * Work platforms - quote received
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
  * Clean bag - expected 6/8.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
=== Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):
 * We disconnected the SF/... section and reinstalled the F0-SF rod with the hex cable clamp attached.
 * We debugged an issue with the actuation (the real-time model needed rebooting).
 * We routed all the SF/... cables up to the bottom of the PI, and then to the feedthroughs.
 * We unlocked the F0 keystone and experimented to find the amount of mass needed on the SF (≈845 g).
 * We attached the SF trim mass, adjusting it laterally so that the SF was level in pitch and roll.
 * We corrected some errors on the MEDM screens (some broken links and Take/Restore Safe.snap buttons).
 * We cabled all the PI items through to the rack and did very basic testing.
 * We disconnected the security structure from the assembly frame and adjusted the PI till the SS was vertical.
 * We unlocked the IP and adjusted the PI jacks and FRs till the IP was centered.
 * We passed the halves of the LBB Cu damping ring (less the Cu) into the chamber and joined them.
 * We put the magnets on the LBB damper ring using the template.
 * We locked various combinations of keystones and measured the vertical resonance frequencies of the unlocked filters.
 * We spent time on getting the geophones working. The original descrambler adapters had gone missing, so Enzo created three new ones. We borrowed a cable to replace one that had broken. The geophone distributor (S1402167) failed (no power on the negative rail), and a replacement borrowed from SR3 (S1605513) kept switching off.

==== Plan for week of 9/13 ====
==== Plan for week of 9/19 ====
No work Mon 9/18 (敬老の日)<<BR>>
Mark, Fabian, Enzo, Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Thu, Fri), Kozu-kun
 * Install LBB damper magnet rings in tank.
 * Remove tank lid.
 *
 * Install suspension.

==== Vacation Info ====
Mark: 10/16-24

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):

  • We disconnected the SF/... section and reinstalled the F0-SF rod with the hex cable clamp attached.
  • We debugged an issue with the actuation (the real-time model needed rebooting).
  • We routed all the SF/... cables up to the bottom of the PI, and then to the feedthroughs.
  • We unlocked the F0 keystone and experimented to find the amount of mass needed on the SF (≈845 g).
  • We attached the SF trim mass, adjusting it laterally so that the SF was level in pitch and roll.
  • We corrected some errors on the MEDM screens (some broken links and Take/Restore Safe.snap buttons).
  • We cabled all the PI items through to the rack and did very basic testing.
  • We disconnected the security structure from the assembly frame and adjusted the PI till the SS was vertical.
  • We unlocked the IP and adjusted the PI jacks and FRs till the IP was centered.
  • We passed the halves of the LBB Cu damping ring (less the Cu) into the chamber and joined them.
  • We put the magnets on the LBB damper ring using the template.
  • We locked various combinations of keystones and measured the vertical resonance frequencies of the unlocked filters.
  • We spent time on getting the geophones working. The original descrambler adapters had gone missing, so Enzo created three new ones. We borrowed a cable to replace one that had broken. The geophone distributor (S1402167) failed (no power on the negative rail), and a replacement borrowed from SR3 (S1605513) kept switching off.

Plan for week of 9/13

Plan for week of 9/19

No work Mon 9/18 (敬老の日)
Mark, Fabian, Enzo, Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Thu, Fri), Kozu-kun

  • Install LBB damper magnet rings in tank.
  • Remove tank lid.
  • Install suspension.

Vacation Info

Mark: 10/16-24