Differences between revisions 27 and 308 (spanning 281 versions)
Revision 27 as of 2016-06-10 11:41:20
Size: 3001
Editor: MarkBarton
Comment:
Revision 308 as of 2018-08-03 16:02:31
Size: 2563
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary
  * Fabian finished dummy BS assembly.
  * Mark and Tatsumi-san glued magnets into both types of BS optic flags, and discs into BS IM flags. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1815 |klog]] Two optic flags had to be redone because the magnets moved while the glue was drying. Hirata-san helped remove the magnets with acetone in the ultrasonic cleaner. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1818|klog]]
  * Tatsumi-san, Fabian and Mark took the dummy BS to Kashiwa and glued the flags and prisms. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1821|klog]] We will check status on Mon 6/13.
  * Hirata-san moved in another filter for testing (but didn't get to measure it).
  * Hirata-san washed a batch of parts.
  * Hirata-san modified the design of the parts of the assembly frame supporting the BF and SF to include bushings for smoother movement.
  * Hirata-san researched and ordered a crane scale for use at the site. (We decided the 500-kg version of the 200-kg one used at TAMA. It is the same price and has the same 100-g resolution for the first 250 kg.)
  * Hirata-san worked on making some guide parts for the PI installation (Misumi parts with minor additional machining from ATC).
  * We finalized a design for simple SS mirror parts for the dummy BS with Akutsu-san. They will be made by ATC.
  * Mark worked on list of items for purchase in FY2016 and on the schedule.
  * Fabian did more work on the IM assembly. It is nearly done and he will start on the RM next week. There were some issues with crimping connectors to wires for making pico adapter cables.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
  * Feedthrough Adapters
   * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote.
  * Can we make SR wire breakers bigger?
   * Fukushima-san will start on machining test soon (as of 5/27).
  * Not enough crane height problem (Hirata, Saito) - no action since last week
  * Installation stuff
   * Crane scale - quote received
   * Work platforms - quote received
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
  * Clean bag - expected 6/8.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
=== Type B (Mark) ===
==== Report for week of 7/30 ====
 * We set up an OL outside the tank and checked the SR3 pitch - it was OK.
 * We ran power to the SR3 pico and stepper drivers and tested them.
 * We tried to offload a 700 µm discrepancy between the BF GAS zero position and the IM-V zero position but ended up scrambling the IRM-IM alignment, probably through sending a command to the wrong pico driver. We mostly fixed the BF/IRM pitch/roll, but we have some more work to do to fix the IM/RM/TM pitch/roll.
 * We debugged a problem with the SR2 alignment - the chain was offset by about 5 mm to +T, leading to fouling at the IM and RM levels. Some 2 mm of the offset was due to the F0 keystone being off center, apparently due to some combination of different-strength blades and the CuBe auxiliary spring, but the rest is a mystery.
 * We fixed a problem with the levelness of the PI due to the feet of the IP being set at uneven heights into the PI weldment, and it got the IP very closed to centered but it didn't fix the fouling problem.
 * We eventually fixed the fouling by setting the security structure at a slight angle so it remains slightly off at the SF level but is good at the bottom.
 * We installed the SR2 SF damper Cu segments and magnet ring.
 * Enzo and team debugged a malfunctioning bit in the SR3 IP BIO which turned out to be a defective 37-pin gender changer.

==== Plan for week of 8/6 ====
 * Mark, Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri.
 * Kozu-kun works at Mozumi Mon, Fri, and Thu afternoon.

===== SR3 =====
 * Finalize optic pitch, OSEM alignment.
 * Do TFs with temporary OL.
 * Install final OL.
 * Hook LBB, add ballast mass.
 * Tune IP.

===== SR2 =====
 * Do vertical height budget.
 * Choose F0 keystone height.
 * Add estimated final ballast mass.
 * Do PI cable routing.
 * Adjust ballast/trim mass, with reserve for cables.
 * Stage LBB damper rings in tank.
 
===== SRM =====
 * Assemble metal mass.
 * Glue prisms, flags.
 * Reconfigure, align assembly frame.

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]

==== Vacation Info ====
 * Terrence: 8/24-26 f2f, then returns to Hong Kong.
 * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 7/30

  • We set up an OL outside the tank and checked the SR3 pitch - it was OK.
  • We ran power to the SR3 pico and stepper drivers and tested them.
  • We tried to offload a 700 µm discrepancy between the BF GAS zero position and the IM-V zero position but ended up scrambling the IRM-IM alignment, probably through sending a command to the wrong pico driver. We mostly fixed the BF/IRM pitch/roll, but we have some more work to do to fix the IM/RM/TM pitch/roll.
  • We debugged a problem with the SR2 alignment - the chain was offset by about 5 mm to +T, leading to fouling at the IM and RM levels. Some 2 mm of the offset was due to the F0 keystone being off center, apparently due to some combination of different-strength blades and the CuBe auxiliary spring, but the rest is a mystery.

  • We fixed a problem with the levelness of the PI due to the feet of the IP being set at uneven heights into the PI weldment, and it got the IP very closed to centered but it didn't fix the fouling problem.
  • We eventually fixed the fouling by setting the security structure at a slight angle so it remains slightly off at the SF level but is good at the bottom.
  • We installed the SR2 SF damper Cu segments and magnet ring.
  • Enzo and team debugged a malfunctioning bit in the SR3 IP BIO which turned out to be a defective 37-pin gender changer.

Plan for week of 8/6

  • Mark, Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri.
  • Kozu-kun works at Mozumi Mon, Fri, and Thu afternoon.

SR3
  • Finalize optic pitch, OSEM alignment.
  • Do TFs with temporary OL.
  • Install final OL.
  • Hook LBB, add ballast mass.
  • Tune IP.

SR2
  • Do vertical height budget.
  • Choose F0 keystone height.
  • Add estimated final ballast mass.
  • Do PI cable routing.
  • Adjust ballast/trim mass, with reserve for cables.
  • Stage LBB damper rings in tank.

SRM
  • Assemble metal mass.
  • Glue prisms, flags.
  • Reconfigure, align assembly frame.

To-Do Lists, Schedule

Vacation Info

  • Terrence: 8/24-26 f2f, then returns to Hong Kong.
  • Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)