Differences between revisions 27 and 347 (spanning 320 versions)
Revision 27 as of 2016-06-10 11:41:20
Size: 3001
Editor: MarkBarton
Comment:
Revision 347 as of 2018-11-16 11:07:58
Size: 2556
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary
  * Fabian finished dummy BS assembly.
  * Mark and Tatsumi-san glued magnets into both types of BS optic flags, and discs into BS IM flags. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1815 |klog]] Two optic flags had to be redone because the magnets moved while the glue was drying. Hirata-san helped remove the magnets with acetone in the ultrasonic cleaner. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1818|klog]]
  * Tatsumi-san, Fabian and Mark took the dummy BS to Kashiwa and glued the flags and prisms. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1821|klog]] We will check status on Mon 6/13.
  * Hirata-san moved in another filter for testing (but didn't get to measure it).
  * Hirata-san washed a batch of parts.
  * Hirata-san modified the design of the parts of the assembly frame supporting the BF and SF to include bushings for smoother movement.
  * Hirata-san researched and ordered a crane scale for use at the site. (We decided the 500-kg version of the 200-kg one used at TAMA. It is the same price and has the same 100-g resolution for the first 250 kg.)
  * Hirata-san worked on making some guide parts for the PI installation (Misumi parts with minor additional machining from ATC).
  * We finalized a design for simple SS mirror parts for the dummy BS with Akutsu-san. They will be made by ATC.
  * Mark worked on list of items for purchase in FY2016 and on the schedule.
  * Fabian did more work on the IM assembly. It is nearly done and he will start on the RM next week. There were some issues with crimping connectors to wires for making pico adapter cables.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
  * Feedthrough Adapters
   * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote.
  * Can we make SR wire breakers bigger?
   * Fukushima-san will start on machining test soon (as of 5/27).
  * Not enough crane height problem (Hirata, Saito) - no action since last week
  * Installation stuff
   * Crane scale - quote received
   * Work platforms - quote received
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
  * Clean bag - expected 6/8.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
=== Type B (Mark) ===
==== Report for week of 10/29 ====
 * SRM
  * Hirata-san and Mark craned the LBB ring sandwich to the ceiling of the lower half of the tank, and set the heights of the jacks on the upper half.
  * Fabian and Hirata-san finished the in-vacuum cabling.
  * Enzo ran DC power to the second SRM stepper driver and did the rest of the in-air cabling.
  * We're now ready for final tests of the SF/... items and initial tests of the PI items.
  * Enzo and Fujii-kun built three geophones for SRM.
  * Mark worked on the height budget.
 * SR2
  * Enzo experimented with [[http://www2.mpq.mpg.de/~ros/geo600_docu/soft/liso/manual.pdf|LISO]] (circuit analysis software which, among other functions, can fit measured TFs with a ZPK model) but then wrote his own fitting software in Python and used it to build Foton models of key TFs of the SR2. (These are in slots FM6-FM8 of the DAMP blocks and should not be accidentally enabled.)
 
==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]

==== Plan for week of 11/11 ====
 * Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.
===== SRM =====
 * Main sequence

==== Plan for week of 11/19 ====
 * Friday 11/23 is Labor Thanksgiving Day.
 * Mark, Enzo and Fabian at Kamioka Mon-Thu.
 * Hirata-san at Kamioka Tue-Thu (Mitaka on Mon for Engineering Promotion Office meeting).
===== SRM =====
 * Go/no-go test of all electronics items, especially SF/... section.
 * Finish vertical height check and adjust SF trim mass as required.
 * Unlock IP and center roughly.
 * Check/adjust alignment of SS.
 * Calibrate IP LVDTs.
 * Add arc weights and geophones.
 * Improve centering/tuning of IP and SS alignment.
 * Disconnect cables at feedthroughs, lock suspension.
 * Crane into tank.
===== SR2 =====
 * Assist MIF team with pico cables and LBB breadboard ballast.
 * Install SR2 OL pillar and shelf (with AOL supervision)?

==== Plan for week of 11/26 ====
 * Move SRM in-air cables over to tank.
 * Remove First Contact.
 * Unlock and align SRM.
 * Hook and roughly ballast LBB.

==== Plan for week of 12/3 ====
 * f2f Meeting at NAOJ - no Kamioka work.

==== Vacation/Event Info ====
 * Hirata-san at Mitaka, Mon 11/19 (Engineering Promotion Office meeting).

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 10/29

  • SRM
    • Hirata-san and Mark craned the LBB ring sandwich to the ceiling of the lower half of the tank, and set the heights of the jacks on the upper half.
    • Fabian and Hirata-san finished the in-vacuum cabling.
    • Enzo ran DC power to the second SRM stepper driver and did the rest of the in-air cabling.
    • We're now ready for final tests of the SF/... items and initial tests of the PI items.
    • Enzo and Fujii-kun built three geophones for SRM.
    • Mark worked on the height budget.
  • SR2
    • Enzo experimented with LISO (circuit analysis software which, among other functions, can fit measured TFs with a ZPK model) but then wrote his own fitting software in Python and used it to build Foton models of key TFs of the SR2. (These are in slots FM6-FM8 of the DAMP blocks and should not be accidentally enabled.)

To-Do Lists, Schedule

Plan for week of 11/11

  • Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.

SRM
  • Main sequence

Plan for week of 11/19

  • Friday 11/23 is Labor Thanksgiving Day.
  • Mark, Enzo and Fabian at Kamioka Mon-Thu.
  • Hirata-san at Kamioka Tue-Thu (Mitaka on Mon for Engineering Promotion Office meeting).

SRM
  • Go/no-go test of all electronics items, especially SF/... section.
  • Finish vertical height check and adjust SF trim mass as required.
  • Unlock IP and center roughly.
  • Check/adjust alignment of SS.
  • Calibrate IP LVDTs.
  • Add arc weights and geophones.
  • Improve centering/tuning of IP and SS alignment.
  • Disconnect cables at feedthroughs, lock suspension.
  • Crane into tank.

SR2
  • Assist MIF team with pico cables and LBB breadboard ballast.
  • Install SR2 OL pillar and shelf (with AOL supervision)?

Plan for week of 11/26

  • Move SRM in-air cables over to tank.
  • Remove First Contact.
  • Unlock and align SRM.
  • Hook and roughly ballast LBB.

Plan for week of 12/3

  • f2f Meeting at NAOJ - no Kamioka work.

Vacation/Event Info

  • Hirata-san at Mitaka, Mon 11/19 (Engineering Promotion Office meeting).

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)