Differences between revisions 27 and 79 (spanning 52 versions)
Revision 27 as of 2016-06-10 11:41:20
Size: 3001
Editor: MarkBarton
Comment:
Revision 79 as of 2016-10-27 12:56:30
Size: 781
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 6: Line 6:
  * Fabian finished dummy BS assembly.
  * Mark and Tatsumi-san glued magnets into both types of BS optic flags, and discs into BS IM flags. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1815 |klog]] Two optic flags had to be redone because the magnets moved while the glue was drying. Hirata-san helped remove the magnets with acetone in the ultrasonic cleaner. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1818|klog]]
  * Tatsumi-san, Fabian and Mark took the dummy BS to Kashiwa and glued the flags and prisms. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1821|klog]] We will check status on Mon 6/13.
  * Hirata-san moved in another filter for testing (but didn't get to measure it).
  * Hirata-san washed a batch of parts.
  * Hirata-san modified the design of the parts of the assembly frame supporting the BF and SF to include bushings for smoother movement.
  * Hirata-san researched and ordered a crane scale for use at the site. (We decided the 500-kg version of the 200-kg one used at TAMA. It is the same price and has the same 100-g resolution for the first 250 kg.)
  * Hirata-san worked on making some guide parts for the PI installation (Misumi parts with minor additional machining from ATC).
  * We finalized a design for simple SS mirror parts for the dummy BS with Akutsu-san. They will be made by ATC.
  * Mark worked on list of items for purchase in FY2016 and on the schedule.
  * Fabian did more work on the IM assembly. It is nearly done and he will start on the RM next week. There were some issues with crimping connectors to wires for making pico adapter cables.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
  * Feedthrough Adapters
   * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote.
  * Can we make SR wire breakers bigger?
   * Fukushima-san will start on machining test soon (as of 5/27).
  * Not enough crane height problem (Hirata, Saito) - no action since last week
  * Installation stuff
   * Crane scale - quote received
   * Work platforms - quote received
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
  * Clean bag - expected 6/8.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
  * Fabian, Mark and Liu-kun did BS installation at Kamioka:
   * Debugged the issue with the BF keystone being tilted enough to cause rubbing on the yoke for the magnets. It was solved by moving the yoke ≈1 mm taking advantage of the oversized holes.
   * Measured the height of the payload as a function of trim mass. The BF spring seems to have a slightly lower load capacity and a rather higher spring constant than when it was remeasured by Hirata-san.
   * Removed IM trim mass to set the average height of the keystone to the CAD value.
   * Moved IM trim mass around to set the pitch of the dummy BS.
  * Hirata-san
   * TBD.
 

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Type B Past Week Summary
    • Fabian, Mark and Liu-kun did BS installation at Kamioka:
      • Debugged the issue with the BF keystone being tilted enough to cause rubbing on the yoke for the magnets. It was solved by moving the yoke ≈1 mm taking advantage of the oversized holes.
      • Measured the height of the payload as a function of trim mass. The BF spring seems to have a slightly lower load capacity and a rather higher spring constant than when it was remeasured by Hirata-san.
      • Removed IM trim mass to set the average height of the keystone to the CAD value.
      • Moved IM trim mass around to set the pitch of the dummy BS.
    • Hirata-san
      • TBD.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)