Line 13: | Line 13: |
* We measured the keystone tilt at different points and the diferences are within 0.1[mm] | * We measured the keystone tilt at different points and the differences are within 0.1[mm] |
Line 27: | Line 27: |
* Hirata-san, Fujii-san and Tanioka-san checked the optimal load with and without cap. The optimal load changes about 250[g]. The cap didn't came out smoothly. * We measured the keystone tilt at different points, and the diferences are within 0.1[mm] (65.5, 65.5, 65.5, 65.4) |
* Hirata-san, Fujii-san and Tanioka-san checked the optimal load with and without cap. The optimal load changes about 250[g]. The cap didn't come out smoothly. * We measured the keystone tilt at different points, and the differences are within 0.1[mm] (65.5, 65.5, 65.5, 65.4) |
Line 32: | Line 32: |
* We measured the keystone tilt at different points, and the diferences are within 0.3[mm] (63.7, 63.5,63.8, 63.8) | * We measured the keystone tilt at different points, and the differences are within 0.3[mm] (63.7, 63.5,63.8, 63.8) |
Line 34: | Line 34: |
SR2/SR3/SRM: | SR3/SRM: |
Line 37: | Line 37: |
* Enzo prepared the SR3 and SRM rack in parallel (On going). | |
Line 38: | Line 39: |
* Enzo prepared the SR3 and SRM rack in parallel (On going). |
SR2: * Hirata-san tested the safety bars in the SR2 area. |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 3/26
BFs:
- BF No. 1:
- Fujii-san finished tuning. Optimal load: 52.15[kg]. Resonance frequency: 0.37[Hz]. Optimal height: 64.7[mm].
- We wired the LVDT, Picomotor and Steppermotor.
- We measured the keystone tilt at different points and the differences are within 0.1[mm]
- We added cable clamps to the base.
- BF No.7:
- Tanioka-san and Fujii-san replaced the blades corresponding to the BS for the SR type blades.
- The yoke position was corrected.
- The fishing rod was assembled.
- Compression tuning is ongoing.??
SFs:
- Hirata-san and Tanioka-san set up the frame to check the SFs.
- SF (B2-5):
- Hirata-san, Fujii-san and Tanioka-san checked the optimal load with and without cap. The optimal load changes about 250[g]. The cap didn't come out smoothly.
- We measured the keystone tilt at different points, and the differences are within 0.1[mm] (65.5, 65.5, 65.5, 65.4)
- SF (B2-6):
- Hirata-san, Fujii-san and Tanioka-san checked the optimal load with and without cap (On going?).
- We measured the keystone tilt at different points, and the differences are within 0.3[mm] (63.7, 63.5,63.8, 63.8)
SR3/SRM:
- Kozu-kun and Enzo finished the SR3 in-air cabling.
- Enzo prepared the SR3 and SRM rack in parallel (On going).
SR2:
- Hirata-san tested the safety bars in the SR2 area.
- We got new power supply for the SR2 Rack. Before, the power was coming from the BS rack.
BS:
- Kozu-kun and Enzo helped Enomoto-san troubleshooting the BS Oplev issue (On going).
Shipping:
- We received the LBB parts for SR2.
- We received the Payload parts (IM and IRM) this morning.
Plan for week of 4/2
- Mark at Mitaka Mon, Kamioka from Tue.
- Shoda-san at Mitaka
- Others at Kamioka
- --
- Finish BFs tasks (cabling +calibration)
- Finish SFs tasks (cabling +calibration)
- Add cable clamps to bases.
- Add cable clamps and Cu segments to caps (only if they fit well).
- Build 2xIM, 2xIRM
- Glue SR3 mirror?
Plan for week of 4/9
- Shoda-san at Mitaka
- Fujii-san at Mitaka
- Tanioka-san at Mitaka?
- Others at Kamioka
- --
- Finish IMs and IRMs
- Build 1xRM
- Glue SR3 mirror?
Plan for week of 4/16
- Shoda-san at Mitaka
- Fujii-san at Mitaka
- Tanioka-san at Mitaka?
- Others at Kamioka
- --
- Start SR3 Hang?
Plan for week of 4/23
- Shoda-san at Mitaka
- Fujii-san at Mitaka?
- Tanioka-san at Mitaka?
- Others at Kamioka
- --
- F0 blade prototype test
Plan for week of 4/30
- Golden Week!
To-Do Lists, Schedule
Vacation Info
- Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
- Fabian vacation, 3/26-4/27 (then gone).