Line 6: Line 6:
==== Report for week of 3/26 ==== ==== Report for week of 5/28 ====
 * Enzo tested the LVDT driver repaired by Tanaka-san - it was fine.
 * Fujii-kun and Enzo finished assembling a batch of 4 geophones and took test data.
 * Hirata-san modified some Promec masses (drilling out the threads on 2 of 4 holes) so we could use two layers of them inside the BF.
 * Hirata-san installed maraging rod receptacles in the LBB damper rings, and in the bottom of PIs #3 and #1 (for the SF damper rings).
 * After consulting with various people, Hirata-san installed the second half of the LBB top ring in the chamber, simply omitting the pillar and screw associated with the badly threaded hole.
 * Hirata-san took delivery of the screws for the LBB blade units, made up 9 blade units and installed 6 of them on PI #3 and #1 (for SR3 and SR2).
 * Hirata-san made up a set of PI cable clamps and installed them on PI #3 (for SR3).
 * Hirata-san removed the prototype blades from PI #3 to get ready for testing the final blades.
 * We located the #355 disk and #356 poles for the next level of the security structure up to the SF and installed the poles.
 * We installed ballast mass in the BF. After some trial and error we settled on 16 Promec masses (7.1 kg) inside the BF and 5 D1808104-4 and 3 D1808104-5 masses (540 g) on the cap.
 * Enzo and Fujii-kun did several rounds of TFs on the BF/... section of the suspension and debugged a problem with dewhitening filters not being installed in the OSEMINF filter bank.
 * Enzo installed damping filters for the IM OSEMs.
Line 8: Line 20:
BFs: ==== Plan for week of 6/4 ====
 * Mark, Enzo, Hirata-san, Kozu-kun at Kamioka Tue-Fri. (Mon is NAOJ medical checkup.)
 * --
 * Cable and test BF cap picos.
 * Crane in security structure disk at SF level.
 * Crane in SF and remove cap.
 * Hook BF and adjust total ballast.
 * Route cables through SF-BF flying saucer up to bottom of SF.
 * Adjust BF trim mass.
 * Readjust payload.
 * Take TFs.
 * Characterize final F0 blades.
Line 10: Line 33:
 * BF No. 1:
  * Fujii-san finished tuning. Optimal load: 52.15[kg]. Resonance frequency: 0.37[Hz]. Optimal height: 64.7[mm].
  * We wired the LVDT, Picomotor and Steppermotor.
  * We measured the keystone tilt at different points and the diferences are within 0.1[mm]
  * We added cable clamps to the base.

 * BF No.7:
  * Tanioka-san and Fujii-san replaced the blades corresponding to the BS for the SR type blades.
  * The yoke position was corrected.
  * The fishing rod was assembled.
  * Compression tuning is ongoing.??

SFs:

 * Hirata-san and Tanioka-san set up the frame to check the SFs.

 * SF (B2-5):
  * Hirata-san, Fujii-san and Tanioka-san checked the optimal load with and without cap. The optimal load changes about 250[g]. The cap didn't came out smoothly.
  * We measured the keystone tilt at different points, and the diferences are within 0.1[mm] (65.5, 65.5, 65.5, 65.4)

 * SF (B2-6):
  * Hirata-san, Fujii-san and Tanioka-san checked the optimal load with and without cap (On going?).
  * We measured the keystone tilt at different points, and the diferences are within 0.3[mm] (63.7, 63.5,63.8, 63.8)

SR3/SRM:

 * Kozu-kun and Enzo finished the SR3 in-air cabling.
 * Enzo prepared the SR3 and SRM rack in parallel (On going).


SR2:

 * Hirata-san tested the safety bars in the SR2 area.
 * We got new power supply for the SR2 Rack. Before, the power was coming from the BS rack.

BS:

 * Kozu-kun and Enzo helped Enomoto-san troubleshooting the BS Oplev issue (On going).

Shipping:

 * We received the LBB parts for SR2.
 * We received the Payload parts (IM and IRM) this morning.


==== Plan for week of 4/2 ====
 * Mark at Mitaka Mon, Kamioka from Tue.
 * Shoda-san at Mitaka
 * Others at Kamioka
==== Plan for week of 6/11 ====
 * Mark Enzo, Hirata-san, Kozu-kun at Kamioka Tue-Fri (Mon is compensation day for f2f.)
Line 60: Line 36:
 * Finish BFs tasks (cabling +calibration)
 * Finish SFs tasks (cabling +calibration)
 * Add cable clamps to bases.
 * Add cable clamps and Cu segments to caps (only if they fit well).
 * Build 2xIM, 2xIRM
 * Glue SR3 mirror?

==== Plan for week of 4/9 ====
 * Shoda-san at Mitaka
 * Fujii-san at Mitaka
 * Tanioka-san at Mitaka?
 * Others at Kamioka
 * --
 * Finish IMs and IRMs
 * Build 1xRM
 * Glue SR3 mirror?

==== Plan for week of 4/16 ====
 * Shoda-san at Mitaka
 * Fujii-san at Mitaka
 * Tanioka-san at Mitaka?
 * Others at Kamioka
 * --
 * Start SR3 Hang?

==== Plan for week of 4/23 ====
 * Shoda-san at Mitaka
 * Fujii-san at Mitaka?
 * Tanioka-san at Mitaka?
 * Others at Kamioka
 * --
 * F0 blade prototype test

==== Plan for week of 4/30 ====
  * Golden Week!
 * Any unfinished SR3 SF/... stuff.
 * Add budgeted ballast mass to SF and weigh SF/... section.
 * Cable, test SF LVDT and FR.
 * Rebuild F0 #3 for SR3.
 * Park F0 #1 (for SR2) in top of SR3 assembly frame.
 * Move F0 #3 behind SR3.
Line 97: Line 44:
 * [[KAGRA/Subgroups/VIS/TypeB/March2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/April2018]]
Line 104: Line 49:
 * Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
 * Fabian vacation, 3/26-4/27 (then gone).

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 5/28

  • Enzo tested the LVDT driver repaired by Tanaka-san - it was fine.
  • Fujii-kun and Enzo finished assembling a batch of 4 geophones and took test data.
  • Hirata-san modified some Promec masses (drilling out the threads on 2 of 4 holes) so we could use two layers of them inside the BF.
  • Hirata-san installed maraging rod receptacles in the LBB damper rings, and in the bottom of PIs #3 and #1 (for the SF damper rings).
  • After consulting with various people, Hirata-san installed the second half of the LBB top ring in the chamber, simply omitting the pillar and screw associated with the badly threaded hole.
  • Hirata-san took delivery of the screws for the LBB blade units, made up 9 blade units and installed 6 of them on PI #3 and #1 (for SR3 and SR2).
  • Hirata-san made up a set of PI cable clamps and installed them on PI #3 (for SR3).
  • Hirata-san removed the prototype blades from PI #3 to get ready for testing the final blades.
  • We located the #355 disk and #356 poles for the next level of the security structure up to the SF and installed the poles.
  • We installed ballast mass in the BF. After some trial and error we settled on 16 Promec masses (7.1 kg) inside the BF and 5 D1808104-4 and 3 D1808104-5 masses (540 g) on the cap.
  • Enzo and Fujii-kun did several rounds of TFs on the BF/... section of the suspension and debugged a problem with dewhitening filters not being installed in the OSEMINF filter bank.
  • Enzo installed damping filters for the IM OSEMs.

Plan for week of 6/4

  • Mark, Enzo, Hirata-san, Kozu-kun at Kamioka Tue-Fri. (Mon is NAOJ medical checkup.)
  • --
  • Cable and test BF cap picos.
  • Crane in security structure disk at SF level.
  • Crane in SF and remove cap.
  • Hook BF and adjust total ballast.
  • Route cables through SF-BF flying saucer up to bottom of SF.
  • Adjust BF trim mass.
  • Readjust payload.
  • Take TFs.
  • Characterize final F0 blades.

Plan for week of 6/11

  • Mark Enzo, Hirata-san, Kozu-kun at Kamioka Tue-Fri (Mon is compensation day for f2f.)
  • --
  • Any unfinished SR3 SF/... stuff.
  • Add budgeted ballast mass to SF and weigh SF/... section.
  • Cable, test SF LVDT and FR.
  • Rebuild F0 #3 for SR3.
  • Park F0 #1 (for SR2) in top of SR3 assembly frame.
  • Move F0 #3 behind SR3.

To-Do Lists, Schedule