Line 6: Line 6:
==== Report for week of 3/26 ==== ==== Report for week of 4/2 ====
Line 8: Line 8:
BFs:

 * BF No. 1:
  * Fujii-san finished tuning. Optimal load: 52.15[kg]. Resonance frequency: 0.37[Hz]. Optimal height: 64.7[mm].
  * We wired the LVDT, Picomotor and Steppermotor.
  * We measured the keystone tilt at different points and the differences are within 0.1[mm]
  * We added cable clamps to the base.

 * BF No.7:
  * Tanioka-san and Fujii-san replaced the blades corresponding to the BS for the SR type blades.
  * The yoke position was corrected.
  * The fishing rod was assembled.
  * Compression tuning is ongoing.??

SFs:

 * Hirata-san and Tanioka-san set up the frame to check the SFs.

 * SF (B2-5):
  * Hirata-san, Fujii-san and Tanioka-san checked the optimal load with and without cap. The optimal load changes about 250[g]. The cap didn't come out smoothly.
  * We measured the keystone tilt at different points, and the differences are within 0.1[mm] (65.5, 65.5, 65.5, 65.4)

 * SF (B2-6):
  * Hirata-san, Fujii-san and Tanioka-san checked the optimal load with and without cap (On going?).
  * We measured the keystone tilt at different points, and the differences are within 0.3[mm] (63.7, 63.5,63.8, 63.8)

SR3/SRM:

 * Kozu-kun and Enzo finished the SR3 in-air cabling.
 * Enzo prepared the SR3 and SRM rack in parallel (On going).


SR2:

 * Hirata-san tested the safety bars in the SR2 area.
 * We got new power supply for the SR2 Rack. Before, the power was coming from the BS rack.

BS:

 * Kozu-kun and Enzo helped Enomoto-san troubleshooting the BS Oplev issue (On going).

Shipping:

 * We received the LBB parts for SR2.
 * We received the Payload parts (IM and IRM) this morning.


==== Plan for week of 4/2 ====
 * Mark at Mitaka Mon, Kamioka from Tue.
 * Shoda-san at Mitaka
 * Others at Kamioka
 * --
 * Finish BFs tasks (cabling +calibration)
 * Finish SFs tasks (cabling +calibration)
 * Add cable clamps to bases.
 * Add cable clamps and Cu segments to caps (only if they fit well).
 * Build 2xIM, 2xIRM
 * Glue SR3 mirror?
 * We received the SR3 but found Hirose-san had applied the First Contact patterns on the wrong sides, so we took it to Yamamoto-san's lab and Toyama University and re-applied the FC properly. We also bounced a 1064 nm beam off it to verify that the HR and AR coatings were not also swapped (they were OK).
 * We made magnet-standoff assemblies for both SR3 and SRM, and set up for gluing the prisms and magnets. We will attach the prisms and magnet-standoffs on Monday.
 * Hirata-san did inventory of the SR3/SRM payload parts received last week and started on the inventory of screws.
 * Fujii-kun, Enzo and team finished the preparation, adjustment and calibration of the SFs and BFs.
 * Fujii-kun and Yamamoto-kun got the SR3 real time model running.
 * Enzo finished setting up the SR3 and SRM racks. (The SRM rack still lacks a front-end, and power and network connections, but the SR3 is now ready for testing.)
 * Shoda-san worked on getting quotes for the ballast masses, on design of the SRM metal mass, and on splitting the BS model to reduce the load on the front-end computer.
Line 74: Line 23:
 * Build 1xRM
* Glue SR3 mirror?
 * Glue SR3 mirror
Line 83: Line 31:
 * Start SR3 Hang?  * Build 1xRM
 * Start SR3 Hang
  * Align assembly frame.
Line 88: Line 38:
 * Mark, Enzo at Kamioka
 * Hirata-san at Mitaka
Line 89: Line 41:
 * Others at Kamioka
Line 91: Line 42:
 * F0 blade prototype test  * Clean parts (cable clamp bases, etc, etc).
 * Observe KAGRA Phase 1 operations, assist if problems arise.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 4/2

  • We received the SR3 but found Hirose-san had applied the First Contact patterns on the wrong sides, so we took it to Yamamoto-san's lab and Toyama University and re-applied the FC properly. We also bounced a 1064 nm beam off it to verify that the HR and AR coatings were not also swapped (they were OK).
  • We made magnet-standoff assemblies for both SR3 and SRM, and set up for gluing the prisms and magnets. We will attach the prisms and magnet-standoffs on Monday.
  • Hirata-san did inventory of the SR3/SRM payload parts received last week and started on the inventory of screws.
  • Fujii-kun, Enzo and team finished the preparation, adjustment and calibration of the SFs and BFs.
  • Fujii-kun and Yamamoto-kun got the SR3 real time model running.
  • Enzo finished setting up the SR3 and SRM racks. (The SRM rack still lacks a front-end, and power and network connections, but the SR3 is now ready for testing.)
  • Shoda-san worked on getting quotes for the ballast masses, on design of the SRM metal mass, and on splitting the BS model to reduce the load on the front-end computer.

Plan for week of 4/9

  • Shoda-san at Mitaka
  • Fujii-san at Mitaka
  • Tanioka-san at Mitaka?
  • Others at Kamioka
  • --
  • Finish IMs and IRMs
  • Glue SR3 mirror

Plan for week of 4/16

  • Shoda-san at Mitaka
  • Fujii-san at Mitaka
  • Tanioka-san at Mitaka?
  • Others at Kamioka
  • --
  • Build 1xRM
  • Start SR3 Hang
    • Align assembly frame.

Plan for week of 4/23

  • Shoda-san at Mitaka
  • Fujii-san at Mitaka?
  • Mark, Enzo at Kamioka
  • Hirata-san at Mitaka
  • Tanioka-san at Mitaka?
  • --
  • Clean parts (cable clamp bases, etc, etc).
  • Observe KAGRA Phase 1 operations, assist if problems arise.

Plan for week of 4/30

  • Golden Week!

To-Do Lists, Schedule

Vacation Info

  • Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
  • Fabian vacation, 3/26-4/27 (then gone).