==== Report for week of 3/26 ==== ==== Report for week of 7/9 ====
 * We cleaned up after the heavy rain. There was no significant damage but some cardboard boxes of parts got wet and the contents needed to be moved to other containers and the boxes discarded. Water collected on the SR2 crane slot cover and had to be vacuumed away before the cover could be opened. A new section of corrugated roof was installed to minimize the problem for the future.
 * Enzo and team got all of the in-vacuum and in-air cables for the SF/... and PI properly routed and tested except (so far) for the geophones.
 * Hirata-san and team finished tuning of the F0 for SR2 and moved the PI into the SR2 cleanbooth. It turns out to be about 8 kg weaker than for SR3, whereas the SR2 chain is only 3 kg lighter, so we will have to do some combination of decompression, removing Cu segments and using a stronger CuBe spring (e.g., a Type A F0 FR blade instead of the F2 one in SR3). We closed the floor in the SRM area for safety, but we will probably reopen it as soon as next week for the SRM F0 build.
 * Hirata-san opened the SR3 tank, craned the LBB damper ring sandwich up to the top of the tank and suspended it.
 * Enzo and team corrected a lot of flipped connections on the SR3 PI LVDTs (primary<->secondary on the horizontal, primary<->actuation on the F0).
 * We added the arc weights and geophones and re-centered the IP. It seems stable and very soft, which is good.
Line 8: Line 14:
BFs: ==== Plan for week of 7/9 ====
==== Plan for week of 7/16 ====
 * Monday 7/16 is Sea Day.
 * Mark, Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Tue-Fri.
===== Main Sequence =====
 * Check/restore alignment of payload, especially optic pitch.
 * Testing, TFs.
 * Lock suspension.
 * Crane into tank.
 * Unlock suspension.
 * Rearrange cables.
 * Test.
Line 10: Line 27:
 * BF No. 1:
  * Fujii-san finished tuning. Optimal load: 52.15[kg]. Resonance frequency: 0.37[Hz]. Optimal height: 64.7[mm].
  * We wired the LVDT, Picomotor and Steppermotor.
  * We measured the keystone tilt at different points and the differences are within 0.1[mm]
  * We added cable clamps to the base.

 * BF No.7:
  * Tanioka-san and Fujii-san replaced the blades corresponding to the BS for the SR type blades.
  * The yoke position was corrected.
  * The fishing rod was assembled.
  * Compression tuning is ongoing.??

SFs:

 * Hirata-san and Tanioka-san set up the frame to check the SFs.

 * SF (B2-5):
  * Hirata-san, Fujii-san and Tanioka-san checked the optimal load with and without cap. The optimal load changes about 250[g]. The cap didn't come out smoothly.
  * We measured the keystone tilt at different points, and the differences are within 0.1[mm] (65.5, 65.5, 65.5, 65.4)

 * SF (B2-6):
  * Hirata-san, Fujii-san and Tanioka-san checked the optimal load with and without cap (On going?).
  * We measured the keystone tilt at different points, and the differences are within 0.3[mm] (63.7, 63.5,63.8, 63.8)

SR3/SRM:

 * Kozu-kun and Enzo finished the SR3 in-air cabling.
 * Enzo prepared the SR3 and SRM rack in parallel (On going).


SR2:

 * Hirata-san tested the safety bars in the SR2 area.
 * We got new power supply for the SR2 Rack. Before, the power was coming from the BS rack.

BS:

 * Kozu-kun and Enzo helped Enomoto-san troubleshooting the BS Oplev issue (On going).

Shipping:

 * We received the LBB parts for SR2.
 * We received the Payload parts (IM and IRM) this morning.


==== Plan for week of 4/2 ====
 * Mark at Mitaka Mon, Kamioka from Tue.
 * Shoda-san at Mitaka
 * Others at Kamioka
 * --
 * Finish BFs tasks (cabling +calibration)
 * Finish SFs tasks (cabling +calibration)
 * Add cable clamps to bases.
 * Add cable clamps and Cu segments to caps (only if they fit well).
 * Build 2xIM, 2xIRM
 * Glue SR3 mirror?

==== Plan for week of 4/9 ====
 * Shoda-san at Mitaka
 * Fujii-san at Mitaka
 * Tanioka-san at Mitaka?
 * Others at Kamioka
 * --
 * Finish IMs and IRMs
 * Build 1xRM
 * Glue SR3 mirror?

==== Plan for week of 4/16 ====
 * Shoda-san at Mitaka
 * Fujii-san at Mitaka
 * Tanioka-san at Mitaka?
 * Others at Kamioka
 * --
 * Start SR3 Hang?

==== Plan for week of 4/23 ====
 * Shoda-san at Mitaka
 * Fujii-san at Mitaka?
 * Tanioka-san at Mitaka?
 * Others at Kamioka
 * --
 * F0 blade prototype test

==== Plan for week of 4/30 ====
  * Golden Week!
===== F0/LBB Stuff =====
 * Install correct IP in PI #2.
 * Crane PI #2 to second floor.
 * Rebuild top filter of PI #2.
Line 97: Line 33:
 * [[KAGRA/Subgroups/VIS/TypeB/March2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/April2018]]
Line 101: Line 35:
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]  * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]
Line 104: Line 38:
 * Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
 * Fabian vacation, 3/26-4/27 (then gone).
 * Terrence: 8/24-26 f2f, then returns to Hong Kong.
 * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 7/9

  • We cleaned up after the heavy rain. There was no significant damage but some cardboard boxes of parts got wet and the contents needed to be moved to other containers and the boxes discarded. Water collected on the SR2 crane slot cover and had to be vacuumed away before the cover could be opened. A new section of corrugated roof was installed to minimize the problem for the future.
  • Enzo and team got all of the in-vacuum and in-air cables for the SF/... and PI properly routed and tested except (so far) for the geophones.
  • Hirata-san and team finished tuning of the F0 for SR2 and moved the PI into the SR2 cleanbooth. It turns out to be about 8 kg weaker than for SR3, whereas the SR2 chain is only 3 kg lighter, so we will have to do some combination of decompression, removing Cu segments and using a stronger CuBe spring (e.g., a Type A F0 FR blade instead of the F2 one in SR3). We closed the floor in the SRM area for safety, but we will probably reopen it as soon as next week for the SRM F0 build.

  • Hirata-san opened the SR3 tank, craned the LBB damper ring sandwich up to the top of the tank and suspended it.
  • Enzo and team corrected a lot of flipped connections on the SR3 PI LVDTs (primary<->secondary on the horizontal, primary<->actuation on the F0).

  • We added the arc weights and geophones and re-centered the IP. It seems stable and very soft, which is good.

Plan for week of 7/9

Plan for week of 7/16

  • Monday 7/16 is Sea Day.
  • Mark, Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Tue-Fri.

Main Sequence
  • Check/restore alignment of payload, especially optic pitch.
  • Testing, TFs.
  • Lock suspension.
  • Crane into tank.
  • Unlock suspension.
  • Rearrange cables.
  • Test.

F0/LBB Stuff
  • Install correct IP in PI #2.
  • Crane PI #2 to second floor.
  • Rebuild top filter of PI #2.

To-Do Lists, Schedule

Vacation Info

  • Terrence: 8/24-26 f2f, then returns to Hong Kong.
  • Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.