2433
Comment:
|
2751
|
Deletions are marked like this. | Additions are marked like this. |
Line 6: | Line 6: |
==== Report for week of 4/2 ==== | ==== Report for week of 5/28 ==== * Enzo tested the LVDT driver repaired by Tanaka-san - it was fine. * Fujii-kun and Enzo finished assembling a batch of 4 geophones and took test data. * Hirata-san modified some Promec masses (drilling out the threads on 2 of 4 holes) so we could use two layers of them inside the BF. * Hirata-san installed maraging rod receptacles in the LBB damper rings, and in the bottom of PIs #3 and #1 (for the SF damper rings). * After consulting with various people, Hirata-san installed the second half of the LBB top ring in the chamber, simply omitting the pillar and screw associated with the badly threaded hole. * Hirata-san took delivery of the screws for the LBB blade units, made up 9 blade units and installed 6 of them on PI #3 and #1 (for SR3 and SR2). * Hirata-san made up a set of PI cable clamps and installed them on PI #3 (for SR3). * Hirata-san removed the prototype blades from PI #3 to get ready for testing the final blades. * We located the #355 disk and #356 poles for the next level of the security structure up to the SF and installed the poles. * We installed ballast mass in the BF. After some trial and error we settled on 16 Promec masses (7.1 kg) inside the BF and 5 D1808104-4 and 3 D1808104-5 masses (540 g) on the cap. * Enzo and Fujii-kun did several rounds of TFs on the BF/... section of the suspension and debugged a problem with dewhitening filters not being installed in the OSEMINF filter bank. * Enzo installed damping filters for the IM OSEMs. |
Line 8: | Line 20: |
* We received the SR3 but found Hirose-san had applied the First Contact patterns on the wrong sides, so we took it to Yamamoto-san's lab and Toyama University and re-applied the FC properly. We also bounced a 1064 nm beam off it to verify that the HR and AR coatings were not also swapped (they were OK). * We made magnet-standoff assemblies for both SR3 and SRM, and set up for gluing the prisms and magnets. We will attach the prisms and magnet-standoffs on Monday. * Hirata-san did inventory of the SR3/SRM payload parts received last week and started on the inventory of screws. * Fujii-kun, Enzo and team finished the preparation, adjustment and calibration of the SFs and BFs. * Fujii-kun and Yamamoto-kun got the SR3 real time model running. * Enzo finished setting up the SR3 and SRM racks. (The SRM rack still lacks a front-end, and power and network connections, but the SR3 is now ready for testing.) * Shoda-san worked on getting quotes for the ballast masses, on design of the SRM metal mass, and on splitting the BS model to reduce the load on the front-end computer. |
==== Plan for week of 6/4 ==== * Mark, Enzo, Hirata-san, Kozu-kun at Kamioka Tue-Fri. (Mon is NAOJ medical checkup.) * -- * Cable and test BF cap picos. * Crane in security structure disk at SF level. * Crane in SF and remove cap. * Hook BF and adjust total ballast. * Route cables through SF-BF flying saucer up to bottom of SF. * Adjust BF trim mass. * Readjust payload. * Take TFs. * Characterize final F0 blades. |
Line 16: | Line 33: |
==== Plan for week of 4/9 ==== * Shoda-san at Mitaka * Fujii-san at Mitaka * Tanioka-san at Mitaka? * Others at Kamioka |
==== Plan for week of 6/11 ==== * Mark Enzo, Hirata-san, Kozu-kun at Kamioka Tue-Fri (Mon is compensation day for f2f.) |
Line 22: | Line 36: |
* Finish IMs and IRMs * Glue SR3 mirror ==== Plan for week of 4/16 ==== * Shoda-san at Mitaka * Fujii-san at Mitaka * Tanioka-san at Mitaka? * Others at Kamioka * -- * Build 1xRM * Start SR3 Hang * Align assembly frame. ==== Plan for week of 4/23 ==== * Shoda-san at Mitaka * Fujii-san at Mitaka? * Mark, Enzo at Kamioka * Hirata-san at Mitaka * Tanioka-san at Mitaka? * -- * Clean parts (cable clamp bases, etc, etc). * Observe KAGRA Phase 1 operations, assist if problems arise. ==== Plan for week of 4/30 ==== * Golden Week! |
* Any unfinished SR3 SF/... stuff. * Add budgeted ballast mass to SF and weigh SF/... section. * Cable, test SF LVDT and FR. * Rebuild F0 #3 for SR3. * Park F0 #1 (for SR2) in top of SR3 assembly frame. * Move F0 #3 behind SR3. |
Line 49: | Line 44: |
* [[KAGRA/Subgroups/VIS/TypeB/March2018]] * [[KAGRA/Subgroups/VIS/TypeB/April2018]] |
|
Line 56: | Line 49: |
* Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun) * Fabian vacation, 3/26-4/27 (then gone). |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 5/28
- Enzo tested the LVDT driver repaired by Tanaka-san - it was fine.
- Fujii-kun and Enzo finished assembling a batch of 4 geophones and took test data.
- Hirata-san modified some Promec masses (drilling out the threads on 2 of 4 holes) so we could use two layers of them inside the BF.
- Hirata-san installed maraging rod receptacles in the LBB damper rings, and in the bottom of PIs #3 and #1 (for the SF damper rings).
- After consulting with various people, Hirata-san installed the second half of the LBB top ring in the chamber, simply omitting the pillar and screw associated with the badly threaded hole.
- Hirata-san took delivery of the screws for the LBB blade units, made up 9 blade units and installed 6 of them on PI #3 and #1 (for SR3 and SR2).
- Hirata-san made up a set of PI cable clamps and installed them on PI #3 (for SR3).
- Hirata-san removed the prototype blades from PI #3 to get ready for testing the final blades.
- We located the #355 disk and #356 poles for the next level of the security structure up to the SF and installed the poles.
- We installed ballast mass in the BF. After some trial and error we settled on 16 Promec masses (7.1 kg) inside the BF and 5 D1808104-4 and 3 D1808104-5 masses (540 g) on the cap.
- Enzo and Fujii-kun did several rounds of TFs on the BF/... section of the suspension and debugged a problem with dewhitening filters not being installed in the OSEMINF filter bank.
- Enzo installed damping filters for the IM OSEMs.
Plan for week of 6/4
- Mark, Enzo, Hirata-san, Kozu-kun at Kamioka Tue-Fri. (Mon is NAOJ medical checkup.)
- --
- Cable and test BF cap picos.
- Crane in security structure disk at SF level.
- Crane in SF and remove cap.
- Hook BF and adjust total ballast.
- Route cables through SF-BF flying saucer up to bottom of SF.
- Adjust BF trim mass.
- Readjust payload.
- Take TFs.
- Characterize final F0 blades.
Plan for week of 6/11
- Mark Enzo, Hirata-san, Kozu-kun at Kamioka Tue-Fri (Mon is compensation day for f2f.)
- --
- Any unfinished SR3 SF/... stuff.
- Add budgeted ballast mass to SF and weigh SF/... section.
- Cable, test SF LVDT and FR.
- Rebuild F0 #3 for SR3.
- Park F0 #1 (for SR2) in top of SR3 assembly frame.
- Move F0 #3 behind SR3.
To-Do Lists, Schedule