Line 6: | Line 6: |
==== Report for week of 4/2 ==== * Fujii-kun and Yamamoto-kun got the SR3 real time model running. * We received the SR3. * However Mark and Tanioka-kun found Hirose-san had applied the First Contact patterns on the wrong sides, so we took it to Yamamoto-san's lab and Toyama University and re-applied the FC properly. We also bounced a 1064 nm beam off it to verify that the HR and AR coatings were not also swapped (they were OK). * We made magnet-standoff assemblies for both SR3 and SRM, and set up for gluing the prisms and magnets. We will attach the prisms and magnet-standoffs on Monday. * Hirata-san did inventory of the SR3/SRM payload parts received last week and started on the inventory of screws. * Fujii-kun, Enzo and team finished the preparation, adjustment of the SFs and BFs. * They calibrated one SF and BF. (The remaining one SF and BF will take about another day. Also, the FR stops need to be checked.) * Enzo and Kozu-kun finished setting up the SR3 and SRM racks. (The SRM rack still lacks a front-end, and power and network connections, but the SR3 is now ready for testing.) * Shoda-san worked on getting quotes for the ballast masses, on design of the SRM metal mass, and on splitting the BS model to reduce the load on the front-end computer. ==== Plan for week of 4/9 ==== * Shoda-san at Mitaka * Fujii-san at Mitaka * Tanioka-san at Kamioka, but possibly doing PEM stuff. * Others at Kamioka * -- * Finish SRM BF and SF calibration * Finish IMs and IRMs * Glue SR3 mirror ==== Plan for week of 4/16 ==== * Shoda-san at Mitaka * Fujii-san at Mitaka * Tanioka-san at Mitaka? * Others at Kamioka * -- * Build 1xRM * Start SR3 Hang * Align assembly frame. |
==== Report for week of 4/9 ==== * We packed away the SRM SF and BF. * After several failed attempts with one secondary prism, Mark finished the SR3 prism/magnet gluing. * Tanioka-kun built two IRMs (less OSEMs). * Enzo built an RM. * Kozu-kun and Enzo calibrated one set of 6 IM OSEMs for SR3. (6 OSEMs for SRM remain to be done.) * Hirata-san aligned the assembly frame, installed the interface bars and IM ring, and installed the IM. |
Line 39: | Line 15: |
* Shoda-san at Mitaka * Fujii-san at Mitaka? * Mark, Enzo at Kamioka * Hirata-san at Mitaka * Tanioka-san at Mitaka? |
* Hirata-san at Mitaka Mon-Tue, then Kamioka. * Tanioka-san at Kamioka Tue-Thu * Kozu-kun at Kamioka Wed-Fri (but working with PEM on Fri). * Others at Kamioka full week |
Line 45: | Line 20: |
* Clean parts (cable clamp bases, etc, etc). * Observe KAGRA Phase 1 operations, assist if problems arise. |
* Start SR3 Hang * Hang optic. * Hang RM. * Cable RM OSEMs. |
Line 49: | Line 26: |
* Golden Week! | * Shoda-san at Mitaka. * Mark, Enzo at Kamioka Mon-Wed or TBD. * Others doing Golden Week stuff. * -- * Observe KAGRA Phase 1 operations, assist if problems arise. * Do BF TFs. * Continue SR3 hang. |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 4/9
- We packed away the SRM SF and BF.
- After several failed attempts with one secondary prism, Mark finished the SR3 prism/magnet gluing.
- Tanioka-kun built two IRMs (less OSEMs).
- Enzo built an RM.
- Kozu-kun and Enzo calibrated one set of 6 IM OSEMs for SR3. (6 OSEMs for SRM remain to be done.)
- Hirata-san aligned the assembly frame, installed the interface bars and IM ring, and installed the IM.
Plan for week of 4/23
- Hirata-san at Mitaka Mon-Tue, then Kamioka.
- Tanioka-san at Kamioka Tue-Thu
- Kozu-kun at Kamioka Wed-Fri (but working with PEM on Fri).
- Others at Kamioka full week
- --
- Start SR3 Hang
- Hang optic.
- Hang RM.
- Cable RM OSEMs.
Plan for week of 4/30
- Shoda-san at Mitaka.
- Mark, Enzo at Kamioka Mon-Wed or TBD.
- Others doing Golden Week stuff.
- --
- Observe KAGRA Phase 1 operations, assist if problems arise.
- Do BF TFs.
- Continue SR3 hang.
To-Do Lists, Schedule
Vacation Info
- Fabian vacation, 3/26-4/27 (then gone).