Differences between revisions 276 and 298 (spanning 22 versions)
Revision 276 as of 2018-04-13 12:54:35
Size: 2006
Editor: MarkBarton
Comment:
Revision 298 as of 2018-06-22 13:35:18
Size: 3497
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 6: Line 6:
==== Report for week of 4/9 ====
 * Mark glued prisms and magnet/standoff assemblies on the SR3. The SR3 needed to be raised in the box by 0.7 mm to make the prisms go on at the right height, which was done using M4 washers under the PEEK feet.
 * Mark glued ferromagnetic disks on the last 5 IM flags. This completes 2 sets, for SR3 and SRM.
 * Mark configured two pico motor drivers ordered by Takahashi-san as SR3-IM and SRM-BF.
 * Enzo and Kozu-kun finished preparing and calibrating the SF and BF for SR3 and almost entirely finished with those for SRM.
 * Hirata-san built two IMs for SR3 and SRM, and tested the pitch and roll adjustment by running each mass to both limits of its range with the pico driver.
 * Shoda-san worked on the design of the metal SRM.
==== Report for week of 6/18 ====
 * Mark checked the health of the suspensions after an earthquake on Monday morning. The BS watchdog tripped and there was a few µrad change in the pointing, but otherwise it was fine. SR3 and SR2 were also fine.
 * Mark, Enzo and Terrence finalized the trim mass on the BF to set the SF keystone height and BF pitch/roll.
 * They weighed the SF/... section. With no internal trim mass in the SF but with the flying saucer and rod, but with 2 Promec masses for rough balance, it was 255.4 kg, so allowing 1 kg for cables and fine trim mass, we would like a PI load capacity of 256.4 kg.
 * Enzo and Terrence cabled and tested the SF fishing rod, and reversed the connections on the SF LVDT actuation to bring it to standard polarity.
 * Mark and Enzo made many improvements to the Type B MEDM screens.
 * Enzo and Mark measured the BF and SF bounce frequencies (with the other keystone locked).
 * Enzo replaced a HPCD that seemed to have failed during the bounce test (but had just had a watchdog trip), and then replaced the replacement, which really did fail. It turns out we need to avoid applying more than about 25000 counts of GAS actuation.
 * Enzo offloaded the BF LVDT actuator with the BF FR to remove the need for a 10000 ct offset.
 * Hirata-san and Kozu-kun struggled to tune the top filter for SR3 - see klogs 5310, 5324, 5337, xxxx. At first the results were somewhat unrepeatable, with high frequency and low load capacity. This was improved by using a torque wrench (set to 50 N.m) to tighten the blade base clamp screws, retightening the blade tip screws (which had worked loose) and tightening the collar on the end of the shaft of the magic wand. Eventually we decided on a compression of 30 mm, which should give a frequency of around 0.5 Hz if we remove one Cu damper segment from the SF. Hirata-san applied the 30 mm compression but we skipped another round of testing with the dummy load and will go straight to hanging the SF/... section on the assembly frame.
 * We wrapped PI #1 (for SR2) and craned it from behind SR3 to behind SRM. We can now wrap PI #3 (for SR3) and crane it straight to the assembly frame.
 
==== Plan for week of 6/25 ====
 * Mark, Enzo, Hirata-san, Terrence at Kamioka Mon-Fri.
 * Kozu-kun at Kamioka except Thu.
 * --
 * Shutdown Type B controls (as far as possible) in preparation for risk of accidental power outage during electrical work on 6/26.
 * Prepare SF damper magnet ring and rods.
 * Install PI #3 in SR3 AF.
 * Suspend SF/... section.
 * Lots of cable routing and testing.
 * Move PI #1 (for SR2) over SRM tank to work area, install blades and tune.
Line 14: Line 29:
==== Plan for week of 4/16 ====
 * Shoda-san at Mitaka
 * Tanioka-san at Kamioka Tue-Thu
 * Oth
ers at Kamioka full week
==== Plan for week of 7/2 ====
 * Mark, Hirata-san, Terrence at Kamioka Mon-Fri.
 * Enzo at Kamioka Mon-Wed.
 * Kozu-ku
n at Kamioka except Wed.
Line 19: Line 34:
 * Move SF and BF for SRM out of the way.
 * Check results of gluing.
 * Build 1xRM
 * Start SR3 Hang
  * Reset assembly frame crossbars to correct heights.
  * Center the optical table.
  * Align the assembly frame vertically.

==== Plan for week of 4/23 ====
 * Shoda-san at Mitaka
 * Fujii-san at Mitaka?
 * Mark, Enzo at Kamioka
 * Hirata-san at Mitaka
 * Tanioka-san at Mitaka?
 * --
 * Clean parts (cable clamp bases, etc, etc).
 * Observe KAGRA Phase 1 operations, assist if problems arise.

==== Plan for week of 4/30 ====
  * Golden Week!
 * Lock suspension.
 * Remove tank lid and raise LBB damper rings.
 * Crane suspension into tank.
Line 41: Line 39:
 * [[KAGRA/Subgroups/VIS/TypeB/March2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/April2018]]
Line 45: Line 41:
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]  * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]
Line 48: Line 44:
 * Fabian vacation, 3/26-4/27 (then gone).  * Kozu-kun: 7/4 Tokyo.
 * Enzo: 7/5-6 NAOJ Party, Mitaka.
 * Terrence: 8/24-26 f2f, then returns to Hong Kong.
 * Enzo: 9/14 JPS, 9/15 through 10/18 vacation in Chile.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 6/18

  • Mark checked the health of the suspensions after an earthquake on Monday morning. The BS watchdog tripped and there was a few µrad change in the pointing, but otherwise it was fine. SR3 and SR2 were also fine.
  • Mark, Enzo and Terrence finalized the trim mass on the BF to set the SF keystone height and BF pitch/roll.
  • They weighed the SF/... section. With no internal trim mass in the SF but with the flying saucer and rod, but with 2 Promec masses for rough balance, it was 255.4 kg, so allowing 1 kg for cables and fine trim mass, we would like a PI load capacity of 256.4 kg.
  • Enzo and Terrence cabled and tested the SF fishing rod, and reversed the connections on the SF LVDT actuation to bring it to standard polarity.
  • Mark and Enzo made many improvements to the Type B MEDM screens.
  • Enzo and Mark measured the BF and SF bounce frequencies (with the other keystone locked).
  • Enzo replaced a HPCD that seemed to have failed during the bounce test (but had just had a watchdog trip), and then replaced the replacement, which really did fail. It turns out we need to avoid applying more than about 25000 counts of GAS actuation.
  • Enzo offloaded the BF LVDT actuator with the BF FR to remove the need for a 10000 ct offset.
  • Hirata-san and Kozu-kun struggled to tune the top filter for SR3 - see klogs 5310, 5324, 5337, xxxx. At first the results were somewhat unrepeatable, with high frequency and low load capacity. This was improved by using a torque wrench (set to 50 N.m) to tighten the blade base clamp screws, retightening the blade tip screws (which had worked loose) and tightening the collar on the end of the shaft of the magic wand. Eventually we decided on a compression of 30 mm, which should give a frequency of around 0.5 Hz if we remove one Cu damper segment from the SF. Hirata-san applied the 30 mm compression but we skipped another round of testing with the dummy load and will go straight to hanging the SF/... section on the assembly frame.
  • We wrapped PI #1 (for SR2) and craned it from behind SR3 to behind SRM. We can now wrap PI #3 (for SR3) and crane it straight to the assembly frame.

Plan for week of 6/25

  • Mark, Enzo, Hirata-san, Terrence at Kamioka Mon-Fri.
  • Kozu-kun at Kamioka except Thu.
  • --
  • Shutdown Type B controls (as far as possible) in preparation for risk of accidental power outage during electrical work on 6/26.
  • Prepare SF damper magnet ring and rods.
  • Install PI #3 in SR3 AF.
  • Suspend SF/... section.
  • Lots of cable routing and testing.
  • Move PI #1 (for SR2) over SRM tank to work area, install blades and tune.

Plan for week of 7/2

  • Mark, Hirata-san, Terrence at Kamioka Mon-Fri.
  • Enzo at Kamioka Mon-Wed.
  • Kozu-kun at Kamioka except Wed.
  • --
  • Lock suspension.
  • Remove tank lid and raise LBB damper rings.
  • Crane suspension into tank.

To-Do Lists, Schedule

Vacation Info

  • Kozu-kun: 7/4 Tokyo.
  • Enzo: 7/5-6 NAOJ Party, Mitaka.
  • Terrence: 8/24-26 f2f, then returns to Hong Kong.
  • Enzo: 9/14 JPS, 9/15 through 10/18 vacation in Chile.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)