Line 6: Line 6:
==== Report for week of 4/9 ====
 * Mark glued prisms and magnet/standoff assemblies on the SR3. The SR3 needed to be raised in the box by 0.7 mm to make the prisms go on at the right height, which was done using M4 washers under the PEEK feet.
 * Mark glued ferromagnetic disks on the last 5 IM flags. This completes 2 sets, for SR3 and SRM.
 * Mark configured two pico motor drivers ordered by Takahashi-san as SR3-IM and SRM-BF.
 * Enzo and Kozu-kun finished preparing and calibrating the SF and BF for SR3 and almost entirely finished with those for SRM.
 * Hirata-san worked on building two IMs for SR3 and SRM. The SR3 one just needs to have flags attached and to be weighed; the SRM needs another few hours work.
 * Shoda-san worked on the design of the metal SRM, on the LBB ballast mass, and on the plans for testing the BS in bKAGRA Phase 1.
==== Report for week of 4/23 ====
 * We hung the optic and set its pitch. The winch system had a lot of slop in it but the technique of relaxing the wires by lifting the optic on the EQ stops was effective in getting consistent results.
 * We tightened the clamps using a torque wrench, using settings of 5 N.m for the primary clamps and 20 N.m for the secondary.
 * We hung the RM and set its pitch. The RM winches were a lot more consistent.
 * However when tightening the clamps, the wire on the +Y side broke at the bottom edge of primary clamp. The wire on the -Y held, so the RM dropped a few mm onto the trolley on the +Y side.
 * We raised the RM trolley to support the RM and left the optic hanging inside it overnight as a safety test.
 * We then reversed the usual installation procedure to remove the RM and get the mirror box around the optic. We used clamp pieces as spacers to bridge the gaps created by the fact that the optic had been raised 3 mm during hanging and could not safely be lowered. We then cut the wires, leaving the op
 * Shoda-san made SRM model (Dropbox/Largefiles/Subsystems/VIS/Design/SR/Model/SRM-MetalMass_180426)
 * Shoda-san made 2D drawings of LBB ballast masses
 * Hirata-san washed parts.
==== Control Issues ====
 * Resonant frequency table is ready for BS ([[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/TypeB/BSdetail|BS suspension details]])
 * We found the inconsistency between local damping measurement and interferometer measurement. ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=4811|klog4811]])
  The TF gains from IML to TML, and from TML to TML are different from the interferometer measurement.
Line 14: Line 21:
==== Plan for week of 4/16 ====
 * Shoda-san at Mitaka
 * Tanioka-san at Kamioka Tue-Thu
 * Others at Kamioka full week
 * --
 * Move SF and BF for SRM out of the way.
 * Check results of gluing.
 * Build 1xRM
 * Calibrate OSEMs.
 * Start SR3 Hang
  * Reset assembly frame crossbars to correct heights.
  * Center the optical table.
  * Align the assembly frame vertically.
  * Install IM ring and IM.
  * Hang optic.
  * Hang RM.
  * Cable RM OSEMs.
  * I checked the TML gain, which are calculated from TMP and TMY measurements, and found EUL2COIL matrix was different from what I supposed.
   --> Fixed it and updated the state space model. Might be OK now for TF from TML to TML. (Komori-kun will check it.)
  * I checked the calibration gain of OSEMs and found that the measured values are not used. But it makes only small difference.
  * Compare the TFs from BFGAS to BFGAS and BFGAS to IMV, and they are inconsistent for BS and PR2. (No data found for PR3)([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=4807|klog4807]])
  * Comparing TFs from IMP to TMP and from IMY to TMY also helps to check the OSEM calibration by comparing OSEM signals and Oplev signals.
   Found the matrix to convert OSEM signals (um) to pitch (urad) is different from what I calculated. To be checked.
   The measurement will be done after phase-I.
Line 32: Line 29:
==== Plan for week of 4/23 ====
 * Shoda-san at Mitaka
 * Fujii-san at Mitaka?
 * Mark, Enzo at Kamioka
 * Hirata-san at Mitaka
 * Tanioka-san at Mitaka?
 * --
 * Clean parts (cable clamp bases, etc, etc).
 * Observe KAGRA Phase 1 operations, assist if problems arise.
 * Continue SR3 hang.
 * Constructing the tool to implement the current filterbank information to state space model.
Line 44: Line 32:
  * Golden Week!  * Shoda-san at Mitaka.
 * Mark, Enzo at Kamioka Mon-Wed or TBD.
 * Others having fun doing Golden Week stuff.
 * --
 * Observe KAGRA Phase 1 operations, assist if problems arise.
 * Do BF TFs.

==== Plan for week of 5/7 ====
 * Shoda-san at Mitaka.
 * Enzo at Kamioka from Tue.
 * Mark, Hirata-san at Kamioka full week.
 * Kozu-kun at Kamioka??
 * Tanioka-kun at Kamioka Mon, Tue.
 * --
 * Continue SR3 Hang
  * Inspect clamps and decide whether to reuse or swap in clamps from SRM IM.
  * Rehang optic.
  * Rehang RM.
  * Cable RM OSEMs.
 * Prepare for filter testing
  * Remove cracked blades from F0 #1 and #3.
  * Remove floor panel in SR3 area.
  * Set up filter building trolley with crossbars, jacks and F0 test masses.
 
 * Etc
  * Test prototype SR3 safety bar, and set up second safety bar.
  * Negotiate with Mirapro to get SRM mushroom installed, avoiding 5/15.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 4/23

  • We hung the optic and set its pitch. The winch system had a lot of slop in it but the technique of relaxing the wires by lifting the optic on the EQ stops was effective in getting consistent results.
  • We tightened the clamps using a torque wrench, using settings of 5 N.m for the primary clamps and 20 N.m for the secondary.
  • We hung the RM and set its pitch. The RM winches were a lot more consistent.
  • However when tightening the clamps, the wire on the +Y side broke at the bottom edge of primary clamp. The wire on the -Y held, so the RM dropped a few mm onto the trolley on the +Y side.
  • We raised the RM trolley to support the RM and left the optic hanging inside it overnight as a safety test.
  • We then reversed the usual installation procedure to remove the RM and get the mirror box around the optic. We used clamp pieces as spacers to bridge the gaps created by the fact that the optic had been raised 3 mm during hanging and could not safely be lowered. We then cut the wires, leaving the op
  • Shoda-san made SRM model (Dropbox/Largefiles/Subsystems/VIS/Design/SR/Model/SRM-MetalMass_180426)

  • Shoda-san made 2D drawings of LBB ballast masses
  • Hirata-san washed parts.

Control Issues

  • Resonant frequency table is ready for BS (BS suspension details)

  • We found the inconsistency between local damping measurement and interferometer measurement. (klog4811)

    • The TF gains from IML to TML, and from TML to TML are different from the interferometer measurement.
    • I checked the TML gain, which are calculated from TMP and TMY measurements, and found EUL2COIL matrix was different from what I supposed.
      • --> Fixed it and updated the state space model. Might be OK now for TF from TML to TML. (Komori-kun will check it.)

    • I checked the calibration gain of OSEMs and found that the measured values are not used. But it makes only small difference.
    • Compare the TFs from BFGAS to BFGAS and BFGAS to IMV, and they are inconsistent for BS and PR2. (No data found for PR3)(klog4807)

    • Comparing TFs from IMP to TMP and from IMY to TMY also helps to check the OSEM calibration by comparing OSEM signals and Oplev signals.
      • Found the matrix to convert OSEM signals (um) to pitch (urad) is different from what I calculated. To be checked. The measurement will be done after phase-I.
  • Constructing the tool to implement the current filterbank information to state space model.

Plan for week of 4/30

  • Shoda-san at Mitaka.
  • Mark, Enzo at Kamioka Mon-Wed or TBD.
  • Others having fun doing Golden Week stuff.
  • --
  • Observe KAGRA Phase 1 operations, assist if problems arise.
  • Do BF TFs.

Plan for week of 5/7

  • Shoda-san at Mitaka.
  • Enzo at Kamioka from Tue.
  • Mark, Hirata-san at Kamioka full week.
  • Kozu-kun at Kamioka??
  • Tanioka-kun at Kamioka Mon, Tue.
  • --
  • Continue SR3 Hang
    • Inspect clamps and decide whether to reuse or swap in clamps from SRM IM.
    • Rehang optic.
    • Rehang RM.
    • Cable RM OSEMs.
  • Prepare for filter testing
    • Remove cracked blades from F0 #1 and #3.
    • Remove floor panel in SR3 area.
    • Set up filter building trolley with crossbars, jacks and F0 test masses.
  • Etc
    • Test prototype SR3 safety bar, and set up second safety bar.
    • Negotiate with Mirapro to get SRM mushroom installed, avoiding 5/15.