Line 6: Line 6:
==== Report for week of 4/9 ====
 * Mark glued prisms and magnet/standoff assemblies on the SR3. The SR3 needed to be raised in the box by 0.7 mm to make the prisms go on at the right height, which was done using M4 washers under the PEEK feet.
 * Mark glued ferromagnetic disks on the last 5 IM flags. This completes 2 sets, for SR3 and SRM.
 * Mark configured two pico motor drivers ordered by Takahashi-san as SR3-IM and SRM-BF.
 * Enzo and Kozu-kun finished preparing and calibrating the SF and BF for SR3 and almost entirely finished with those for SRM.
 * Hirata-san worked on building two IMs for SR3 and SRM. The SR3 one just needs to have flags attached and to be weighed; the SRM needs another few hours work.
 * Shoda-san worked on the design of the metal SRM, on the LBB ballast mass, and on the plans for testing the BS in bKAGRA Phase 1.

==== Plan for week of 4/16 ====
 * Shoda-san at Mitaka
 * Tanioka-san at Kamioka Tue-Thu
 * Others at Kamioka full week
 * --
 * Move SF and BF for SRM out of the way.
 * Check results of gluing.
 * Build 1xRM
 * Calibrate OSEMs.
 * Start SR3 Hang
  * Reset assembly frame crossbars to correct heights.
  * Center the optical table.
  * Align the assembly frame vertically.
  * Install IM ring and IM.
  * Hang optic.
  * Hang RM.
  * Cable RM OSEMs.

==== Plan for week of 4/23 ====
 * Shoda-san at Mitaka
 * Fujii-san at Mitaka?
 * Mark, Enzo at Kamioka
 * Hirata-san at Mitaka
 * Tanioka-san at Mitaka?
 * --
 * Clean parts (cable clamp bases, etc, etc).
 * Observe KAGRA Phase 1 operations, assist if problems arise.
 * Continue SR3 hang.

==== Plan for week of 4/30 ====
  * Golden Week!
==== Report for week of 11/12 ====
 * SRM
  * Hirata-san and Mark craned the LBB ring sandwich to the ceiling of the lower half of the tank, and set the heights of the jacks on the upper half.
  * Fabian and Hirata-san finished the in-vacuum cabling.
  * Enzo ran DC power to the second SRM stepper driver and did the rest of the in-air cabling.
  * We're now ready for final tests of the SF/... items and initial tests of the PI items.
  * Enzo and Fujii-kun built three geophones for SRM.
  * Mark worked on the height budget.
 * SR2
  * Enzo experimented with [[http://www2.mpq.mpg.de/~ros/geo600_docu/soft/liso/manual.pdf|LISO]] (circuit analysis software which, among other functions, can fit measured TFs with a ZPK model) but then wrote his own fitting software in Python and used it to build Foton models of key TFs of the SR2. (These are in slots FM6-FM8 of the DAMP blocks and should not be accidentally enabled.)
 
Line 47: Line 18:
 * [[KAGRA/Subgroups/VIS/TypeB/March2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/April2018]]
Line 51: Line 20:
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]  * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]
Line 53: Line 22:
==== Vacation Info ====
 * Fabian vacation, 3/26-4/27 (then gone).
==== Plan for week of 11/19 ====
 * Friday 11/23 is Labor Thanksgiving Day.
 * Mark, Enzo and Fabian at Kamioka Mon-Thu.
 * Hirata-san at Kamioka Tue-Thu (Mitaka on Mon for Engineering Promotion Office meeting).
===== SRM =====
 * Go/no-go test of all electronics items, especially SF/... section.
 * Finish vertical height check and adjust SF trim mass as required.
 * Unlock IP and center roughly.
 * Check/adjust alignment of SS.
 * Calibrate IP LVDTs.
 * Add arc weights and geophones.
 * Improve centering/tuning of IP and SS alignment.
 * Disconnect cables at feedthroughs, lock suspension.
 * Crane into tank.
===== SR2 =====
 * Assist MIF team with pico cables and LBB breadboard ballast.
 * Install SR2 OL pillar and shelf (with AOL supervision)?

==== Plan for week of 11/26 ====
 * Move SRM in-air cables over to tank.
 * Remove First Contact.
 * Unlock and align SRM.
 * Hook and roughly ballast LBB.

==== Plan for week of 12/3 ====
 * f2f Meeting at NAOJ - no Kamioka work.

==== Vacation/Event Info ====
 * Hirata-san at Mitaka, Mon 11/19 (Engineering Promotion Office meeting).

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 11/12

  • SRM
    • Hirata-san and Mark craned the LBB ring sandwich to the ceiling of the lower half of the tank, and set the heights of the jacks on the upper half.
    • Fabian and Hirata-san finished the in-vacuum cabling.
    • Enzo ran DC power to the second SRM stepper driver and did the rest of the in-air cabling.
    • We're now ready for final tests of the SF/... items and initial tests of the PI items.
    • Enzo and Fujii-kun built three geophones for SRM.
    • Mark worked on the height budget.
  • SR2
    • Enzo experimented with LISO (circuit analysis software which, among other functions, can fit measured TFs with a ZPK model) but then wrote his own fitting software in Python and used it to build Foton models of key TFs of the SR2. (These are in slots FM6-FM8 of the DAMP blocks and should not be accidentally enabled.)

To-Do Lists, Schedule

Plan for week of 11/19

  • Friday 11/23 is Labor Thanksgiving Day.
  • Mark, Enzo and Fabian at Kamioka Mon-Thu.
  • Hirata-san at Kamioka Tue-Thu (Mitaka on Mon for Engineering Promotion Office meeting).

SRM
  • Go/no-go test of all electronics items, especially SF/... section.
  • Finish vertical height check and adjust SF trim mass as required.
  • Unlock IP and center roughly.
  • Check/adjust alignment of SS.
  • Calibrate IP LVDTs.
  • Add arc weights and geophones.
  • Improve centering/tuning of IP and SS alignment.
  • Disconnect cables at feedthroughs, lock suspension.
  • Crane into tank.

SR2
  • Assist MIF team with pico cables and LBB breadboard ballast.
  • Install SR2 OL pillar and shelf (with AOL supervision)?

Plan for week of 11/26

  • Move SRM in-air cables over to tank.
  • Remove First Contact.
  • Unlock and align SRM.
  • Hook and roughly ballast LBB.

Plan for week of 12/3

  • f2f Meeting at NAOJ - no Kamioka work.