Differences between revisions 28 and 112 (spanning 84 versions)
Revision 28 as of 2016-06-15 19:45:04
Size: 2200
Editor: MarkBarton
Comment:
Revision 112 as of 2016-12-22 13:34:03
Size: 2022
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary
  * There were multiple issues with the dummy BS flag/prism gluing [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1830 |klog]]. The sapphire prisms will need to be removed and reapplied. Hirose-san is going to organize this. He wants to try the cup that had been made for the PR2 on the actual PR2 and then see if a new cup is needed for the BS (considering the different radius).
  * Hirata-san added the optical layout information to the BS Inventor assembly. He requested tank information from Mirapro so he can continue to do SR2/3/M.
  * Fabian finished the IM assembly and started on the IRM and RM. Some of the IRM panels had been improperly wrapped and really should be re-cleaned. The MPC (multi-purpose cube) on the RM will need some rework.
  * Mark scheduled a review for Thursday 6/16.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
  * Feedthrough Adapters
   * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote.
  * Can we make SR wire breakers bigger?
   * Fukushima-san will start on machining test soon (as of 5/27).
  * Not enough crane height problem (Hirata, Saito) - no action since last week
  * Installation stuff
   * Crane scale - quote received
   * Work platforms - RECEIVED
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
  * Clean bag - RECEIVED.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * Activity report for week of 12/19
  * Hirata-san made (and Fabian and Mark checked) drawings and parts/fastener lists for the SRM/PRM order and various others: [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5964| D1605964]], [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5965| D1605965]], [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5956| D1605956]], [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5963| D1605963]], [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5977|D1605977]], etc.
  * Fabian designed a simple two-piece hold-down device to immobilize the SRx IMs during the optic and RM hanging. It avoids having to remachine all the IM support bars to allow for hold-down screws. The Type Bp team might also want to use it.
  * Aso-san and Mark discussed the [[KAGRA/Subgroups/VIS/VISMinutes20161216#BFIssue|BF issue]] from last week.
   * It was decided to ask Takahashi-san to take a look at the BF while he's at Kamioka this week.
   * It was decided to have the BS bottom filter moved to Mitaka for tuneup and adjustment as soon as possible in the new year.
  * Raffaele, Aso-san, Mark and Fabian discussed having much smaller/shorter BS and SR stub flags plus longer, coil-only OSEMs.
   * Aso-san volunteered to do the OSEM design.
   * Hirata-san made Pack'n'Go archives of the existing designs as a baseline for Aso-san.
  * Hirata-san searched for missing PR mirror box parts.
  * Miyakawa-san finished recabling the PR2 rack and got the BS real-time model running again. (The problem had been a new requirement for a safe.snap file to be provided in the burt directory, which was imposed by RCG2.9.7.) The model still needs lots of work, but it has the OSEM functionality needed for the next test-hang stage, plus Okutomi-san's improvements.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Activity report for week of 12/19
    • Hirata-san made (and Fabian and Mark checked) drawings and parts/fastener lists for the SRM/PRM order and various others: D1605964, D1605965, D1605956, D1605963, D1605977, etc.

    • Fabian designed a simple two-piece hold-down device to immobilize the SRx IMs during the optic and RM hanging. It avoids having to remachine all the IM support bars to allow for hold-down screws. The Type Bp team might also want to use it.
    • Aso-san and Mark discussed the BF issue from last week.

      • It was decided to ask Takahashi-san to take a look at the BF while he's at Kamioka this week.
      • It was decided to have the BS bottom filter moved to Mitaka for tuneup and adjustment as soon as possible in the new year.
    • Raffaele, Aso-san, Mark and Fabian discussed having much smaller/shorter BS and SR stub flags plus longer, coil-only OSEMs.
      • Aso-san volunteered to do the OSEM design.
      • Hirata-san made Pack'n'Go archives of the existing designs as a baseline for Aso-san.
    • Hirata-san searched for missing PR mirror box parts.
    • Miyakawa-san finished recabling the PR2 rack and got the BS real-time model running again. (The problem had been a new requirement for a safe.snap file to be provided in the burt directory, which was imposed by RCG2.9.7.) The model still needs lots of work, but it has the OSEM functionality needed for the next test-hang stage, plus Okutomi-san's improvements.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)