 * Type B Past Week Summary
  * There were multiple issues with the dummy BS flag/prism gluing [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1830 |klog]]. The sapphire prisms will need to be removed and reapplied. Hirose-san is going to organize this. He wants to try the cup that had been made for the PR2 on the actual PR2 and then see if a new cup is needed for the BS (considering the different radius).
  * Hirata-san added the optical layout information to the BS Inventor assembly. He requested tank information from Mirapro so he can continue to do SR2/3/M.
  * Fabian finished the IM assembly and started on the IRM and RM. Some of the IRM panels had been improperly wrapped and really should be re-cleaned. The MPC (multi-purpose cube) on the RM will need some rework.
  * Mark scheduled a review for Thursday 6/16.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
  * Feedthrough Adapters
   * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote.
  * Can we make SR wire breakers bigger?
   * Fukushima-san will start on machining test soon (as of 5/27).
  * Not enough crane height problem (Hirata, Saito) - no action since last week
  * Installation stuff
   * Crane scale - quote received
   * Work platforms - RECEIVED
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
  * Clean bag - RECEIVED.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
=== Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Ohishi-san, Enzo, Yoshioka-kun, Kozu-kun):
 * We finished installing the RM OSEMs and installed the new Type5-2.2 and 5-2.4 OSEM cables.
 * We hung the RM and set its pitch.
 * We doubled-checked the BS and RM pitch, tightened the clamps and removed the winch system.
 * We installed the bottom section of the security structure to protect the RM/BS.
 * We lifted the IM/RM/BS section and weighed it. It was about 1.25 kg too heavy for the new BF, so we improvised a lighter set of ballast masses.
 * We installed the section of the security structure up to the BF ring, and the BF crossbars and jacks of the assembly frame.
 * We brought in the new BF.
 * We installed the BF-IRM rods and IRM top plate.
 * We reinstalled the IM flags and other items that had been taken off to use the winch system.
 * We hooked the BF-IM rod (with hex cable clamp). (We did not unlock the BF keystone.)
 * We cabled and tested the IM-PIT, IM-ROL and IM-YAW picos and the BF FR stepper (but not, yet, the BF LVDT).

==== Plan for week of 8/14 ====
Site closure: Mon, Tue<<BR>>
Vacation: Fabian (Mon-Fri)<<BR>>
Kamioka: Mark (Wed-Fri), Enzo (Wed-Fri), Yoshioka-kun (Wed, Fri), Ohishi (Thu-Fri).<<BR>>
 * Remove LBB blade units from PI, then remove blades and send for remachining.
 * Remove LBB rings from chamber and send for recleaning.
 * Unlock BF, adjust ballast masses on IM/RM/BS to correct pitch/roll/vertical.
 * Test, calibrate BF LVDT.
Mitaka: Hirata-san (Mon-Fri)<<BR>>
 * SR Stuff

==== Plan for week of 8/21 ====
Vacation: Fabian (Mon)<<BR>>
Kamioka: Mark, Ohishi, Fabian (Tue-Fri), Enzo, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun.

Vacation Info:
Fabian: Fri 8/4 through Mon 8/21
Mark: TBD Mid-Oct

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Ohishi-san, Enzo, Yoshioka-kun, Kozu-kun):

  • We finished installing the RM OSEMs and installed the new Type5-2.2 and 5-2.4 OSEM cables.
  • We hung the RM and set its pitch.
  • We doubled-checked the BS and RM pitch, tightened the clamps and removed the winch system.
  • We installed the bottom section of the security structure to protect the RM/BS.
  • We lifted the IM/RM/BS section and weighed it. It was about 1.25 kg too heavy for the new BF, so we improvised a lighter set of ballast masses.
  • We installed the section of the security structure up to the BF ring, and the BF crossbars and jacks of the assembly frame.
  • We brought in the new BF.
  • We installed the BF-IRM rods and IRM top plate.
  • We reinstalled the IM flags and other items that had been taken off to use the winch system.
  • We hooked the BF-IM rod (with hex cable clamp). (We did not unlock the BF keystone.)
  • We cabled and tested the IM-PIT, IM-ROL and IM-YAW picos and the BF FR stepper (but not, yet, the BF LVDT).

Plan for week of 8/14

Site closure: Mon, Tue
Vacation: Fabian (Mon-Fri)
Kamioka: Mark (Wed-Fri), Enzo (Wed-Fri), Yoshioka-kun (Wed, Fri), Ohishi (Thu-Fri).

  • Remove LBB blade units from PI, then remove blades and send for remachining.
  • Remove LBB rings from chamber and send for recleaning.
  • Unlock BF, adjust ballast masses on IM/RM/BS to correct pitch/roll/vertical.
  • Test, calibrate BF LVDT.

Mitaka: Hirata-san (Mon-Fri)

  • SR Stuff

Plan for week of 8/21

Vacation: Fabian (Mon)
Kamioka: Mark, Ohishi, Fabian (Tue-Fri), Enzo, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun.

Vacation Info: Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct