Differences between revisions 28 and 204 (spanning 176 versions)
Revision 28 as of 2016-06-15 19:45:04
Size: 2200
Editor: MarkBarton
Comment:
Revision 204 as of 2017-11-10 13:43:14
Size: 1581
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary
  * There were multiple issues with the dummy BS flag/prism gluing [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1830 |klog]]. The sapphire prisms will need to be removed and reapplied. Hirose-san is going to organize this. He wants to try the cup that had been made for the PR2 on the actual PR2 and then see if a new cup is needed for the BS (considering the different radius).
  * Hirata-san added the optical layout information to the BS Inventor assembly. He requested tank information from Mirapro so he can continue to do SR2/3/M.
  * Fabian finished the IM assembly and started on the IRM and RM. Some of the IRM panels had been improperly wrapped and really should be re-cleaned. The MPC (multi-purpose cube) on the RM will need some rework.
  * Mark scheduled a review for Thursday 6/16.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
  * Feedthrough Adapters
   * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote.
  * Can we make SR wire breakers bigger?
   * Fukushima-san will start on machining test soon (as of 5/27).
  * Not enough crane height problem (Hirata, Saito) - no action since last week
  * Installation stuff
   * Crane scale - quote received
   * Work platforms - RECEIVED
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
  * Clean bag - RECEIVED.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
=== Type B (Mark) ===
==== Past two weeks report ====
Kamioka (Mark, Enzo, Kozu-kun):
 * Supported IA team.
 * Replaced LPCDs for IM OSEMs with HPCDs for increased pitch/yaw range.
 * Re-zeroed OL after significant change of beam position during IA.
 * Re-laid-out OL to improve focus of lens to LEN QPD.
 * Offloaded the pitch/yaw actuation at the IM OSEMs using the IM pitch/yaw picos.
 * Enzo worked on design of control loops using the OL.
 * Kozu-kun worked on diagonalizing the OL.

Mitaka (Fabian, Hirata-san):
 * Fabian did mechanical design:
  * F0 FR
  * Cable clamps for the SR IP base.
  * New SR recoil ballast masses.
  * LBB ballast.
  * Update of BS 3D CAD with the as-built ballast.
 * Hirata-san
  * made and updated inventory list for SR.
  * made order list and asked some quotes.
  * Ordered some parts.
  * Talked with mirapro about SRM optical bench.
  * Made some drawings for SR preparation.

==== Plan for week of 11/13 ====

Enzo and Kozu-kun at Mitaka
 * Servos
 * Diagonalization of OL
 * TFs of BF
 * Documentation

Mark and Fabian at Kamioka.
 * Mark attends commissioning workshop at U Toyama.
 * Support BF characterization work.
 * Prepare for mirror gluing.
 * Prepare for IM assembly.

Hirata-san at Mitaka
 * SR procurement.
 * Get BS prism-gluing jigs reworked for use with PR/SR mirror box.

==== Plan for week of 11/20 ====
 * Holiday on Thu 3/23
 * Fabian at commissioning workshop
 *

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past two weeks report

Kamioka (Mark, Enzo, Kozu-kun):

  • Supported IA team.
  • Replaced LPCDs for IM OSEMs with HPCDs for increased pitch/yaw range.
  • Re-zeroed OL after significant change of beam position during IA.
  • Re-laid-out OL to improve focus of lens to LEN QPD.
  • Offloaded the pitch/yaw actuation at the IM OSEMs using the IM pitch/yaw picos.
  • Enzo worked on design of control loops using the OL.
  • Kozu-kun worked on diagonalizing the OL.

Mitaka (Fabian, Hirata-san):

  • Fabian did mechanical design:
    • F0 FR
    • Cable clamps for the SR IP base.
    • New SR recoil ballast masses.
    • LBB ballast.
    • Update of BS 3D CAD with the as-built ballast.
  • Hirata-san
    • made and updated inventory list for SR.
    • made order list and asked some quotes.
    • Ordered some parts.
    • Talked with mirapro about SRM optical bench.
    • Made some drawings for SR preparation.

Plan for week of 11/13

Enzo and Kozu-kun at Mitaka

  • Servos
  • Diagonalization of OL
  • TFs of BF
  • Documentation

Mark and Fabian at Kamioka.

  • Mark attends commissioning workshop at U Toyama.
  • Support BF characterization work.
  • Prepare for mirror gluing.
  • Prepare for IM assembly.

Hirata-san at Mitaka

  • SR procurement.
  • Get BS prism-gluing jigs reworked for use with PR/SR mirror box.

Plan for week of 11/20

  • Holiday on Thu 3/23
  • Fabian at commissioning workshop

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)