2200
Comment:
|
1532
|
Deletions are marked like this. | Additions are marked like this. |
Line 5: | Line 5: |
* Type B Past Week Summary * There were multiple issues with the dummy BS flag/prism gluing [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1830 |klog]]. The sapphire prisms will need to be removed and reapplied. Hirose-san is going to organize this. He wants to try the cup that had been made for the PR2 on the actual PR2 and then see if a new cup is needed for the BS (considering the different radius). * Hirata-san added the optical layout information to the BS Inventor assembly. He requested tank information from Mirapro so he can continue to do SR2/3/M. * Fabian finished the IM assembly and started on the IRM and RM. Some of the IRM panels had been improperly wrapped and really should be re-cleaned. The MPC (multi-purpose cube) on the RM will need some rework. * Mark scheduled a review for Thursday 6/16. * Type B ongoing issues * Wires * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco. * OSEMs * Feedthrough Adapters * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote. * Can we make SR wire breakers bigger? * Fukushima-san will start on machining test soon (as of 5/27). * Not enough crane height problem (Hirata, Saito) - no action since last week * Installation stuff * Crane scale - quote received * Work platforms - RECEIVED * Ballast masses for payload * Initial batch received - ordered extra smaller ones to allow for adjustments. * Lower breadboard stuff * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss. * Breadboard springs (in manufacture, expected end of July) * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order. * Clean bag - RECEIVED. * Documents * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] |
=== Type B (Mark) === ==== Past week report ==== * Mark analyzed the QPD data from Friday 12/1 and derived matrices to diagonalize the QPD, and calibrate output in µrad. In the process an error in the IM OSEM diagonalization was discovered: the P and Y gains were low by a factor 2. * Mark re-zeroed the QPD after noting the micrometer readings so we can do TFs over the weekend. * We prepared for the SR2 gluing: * We aligned the SR2 in the box with the wedge on the correct side. * We checked that the remachined BS prism holders fit on the PR2 mirror box. * We checked that with Tatsumi-san's support ring, the prisms would go on at the right height. * We checked the new magnet jigs. * We glued ferromagnetic disks in a large number of IM flag tips and flag bases, and in the SR magnet jigs. * We also glued SR magnets in the magnet bases. ==== Plan for week of 12/11 * Mark, Fabian, Enzo, Kozu-kun (Mon-Thu only), Hirata-san, Shoda-san at Kamioka. * Mirror gluing. * IM assembly and pico test. * Assembly frame alignment and optical table centering. * Move trolley system from SR3. * OL setup. ==== Plan for week of 12/18 ==== * Shoda-san vacation * Mark, Fabian, Enzo, Kozu-kun at Kamioka Mon-Wed. ==== Vacation Info ==== * Mark 12/22-1/3 * Enzo, 12/21-12/27 (but ''not'' 12/28) * Fabian 12/22-1/5 * Hirata-san 12/21-22 (conference) * Shoda-san 12/18-21 |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
- Mark analyzed the QPD data from Friday 12/1 and derived matrices to diagonalize the QPD, and calibrate output in µrad. In the process an error in the IM OSEM diagonalization was discovered: the P and Y gains were low by a factor 2.
- Mark re-zeroed the QPD after noting the micrometer readings so we can do TFs over the weekend.
- We prepared for the SR2 gluing:
- We aligned the SR2 in the box with the wedge on the correct side.
- We checked that the remachined BS prism holders fit on the PR2 mirror box.
- We checked that with Tatsumi-san's support ring, the prisms would go on at the right height.
- We checked the new magnet jigs.
- We glued ferromagnetic disks in a large number of IM flag tips and flag bases, and in the SR magnet jigs.
- We also glued SR magnets in the magnet bases.
==== Plan for week of 12/11
- Mark, Fabian, Enzo, Kozu-kun (Mon-Thu only), Hirata-san, Shoda-san at Kamioka.
- Mirror gluing.
- IM assembly and pico test.
- Assembly frame alignment and optical table centering.
- Move trolley system from SR3.
- OL setup.
Plan for week of 12/18
- Shoda-san vacation
- Mark, Fabian, Enzo, Kozu-kun at Kamioka Mon-Wed.
Vacation Info
- Mark 12/22-1/3
Enzo, 12/21-12/27 (but not 12/28)
- Fabian 12/22-1/5
- Hirata-san 12/21-22 (conference)
- Shoda-san 12/18-21