 * Type B Past Week Summary
  * There were multiple issues with the dummy BS flag/prism gluing [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1830 |klog]]. The sapphire prisms will need to be removed and reapplied. Hirose-san is going to organize this. He wants to try the cup that had been made for the PR2 on the actual PR2 and then see if a new cup is needed for the BS (considering the different radius).
  * Hirata-san added the optical layout information to the BS Inventor assembly. He requested tank information from Mirapro so he can continue to do SR2/3/M.
  * Fabian finished the IM assembly and started on the IRM and RM. Some of the IRM panels had been improperly wrapped and really should be re-cleaned. The MPC (multi-purpose cube) on the RM will need some rework.
  * Mark scheduled a review for Thursday 6/16.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
  * Feedthrough Adapters
   * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote.
  * Can we make SR wire breakers bigger?
   * Fukushima-san will start on machining test soon (as of 5/27).
  * Not enough crane height problem (Hirata, Saito) - no action since last week
  * Installation stuff
   * Crane scale - quote received
   * Work platforms - RECEIVED
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
  * Clean bag - RECEIVED.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
=== Type B (Mark) ===
==== Report for week of 1/15 ====
 * We swapped in the other available BF, and it was rather better: only 0.3 mm of keystone tilt rather than 1.3 mm. We will use it for the SR2 and then think about whether we want to use or rebuild the original one.
 * We finished the preparation of the second BF, setting the yoke, adding the new-style cable clamps etc.
 * We changed the 1.6 mm sockets on the BF LVDT cable to 1.0 mm ones to match the pins on the LVDT wires. The specification of the cable in D1503901 was apparently wrong. We will update it (today) before doing the cable order for the SR3 and SRM.
 * We updated the BS real-time model and screens, adding support for a damping filter common to both the OL-TM and OL-IM paths, per Izumi-san's suggestion in G1807653.
 * We set up the router for the SR2 rack and got the SR2_IM pico driver and both stepper motors on the network (the SR2_BF pico is still on order).
 * We did prep for the top filter test:
  * We received, unpacked and temporarily stored a shipment of weights and other parts.
  * We removed the top crossbars from the SR3 assembly frame.

 

==== Plan for week of 1/29 ====
 * Enzo at Mitaka 1/29 and most of 1/30, then vacation.
 * Kozu-kun away.
 * All others at Kamioka.
 * Make in-air pico adapter cables.
 * Test IM picos and BF yaw pico.
 * Test FR.
 * Calibrate LVDT.
 * Get screws for ballast mass from Takahashi-san.
 * Install ballast mass in BF.
 * Set up for F0 test.
  * Lower IM crossbars in SR3 assembly frame.
  * Open curtain on SR3 crane slot.
  * Set up dummy load (weight carrier, rods etc).
 * Do F0 test.
  * Bring in F0.
  * Hook up dummy load.
  * Adjust dummy load.

==== Plan for week of 2/5 ====
 * Enzo on vacation; all others at Kamioka.
 * Build IRM around IM.
 * Cable/test/adjust IM OSEMs.
 * Time permitting, do TFs from IM OSEMs to themselves and to optical sensor.

==== Plan for week of 2/12 ====
 * Enzo on vacation; all others at Kamioka.

==== Vacation Info ====
 * Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30)
 * Kozu-kun 1/29-2/2

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 1/15

  • We swapped in the other available BF, and it was rather better: only 0.3 mm of keystone tilt rather than 1.3 mm. We will use it for the SR2 and then think about whether we want to use or rebuild the original one.
  • We finished the preparation of the second BF, setting the yoke, adding the new-style cable clamps etc.
  • We changed the 1.6 mm sockets on the BF LVDT cable to 1.0 mm ones to match the pins on the LVDT wires. The specification of the cable in D1503901 was apparently wrong. We will update it (today) before doing the cable order for the SR3 and SRM.
  • We updated the BS real-time model and screens, adding support for a damping filter common to both the OL-TM and OL-IM paths, per Izumi-san's suggestion in G1807653.
  • We set up the router for the SR2 rack and got the SR2_IM pico driver and both stepper motors on the network (the SR2_BF pico is still on order).
  • We did prep for the top filter test:
    • We received, unpacked and temporarily stored a shipment of weights and other parts.
    • We removed the top crossbars from the SR3 assembly frame.

Plan for week of 1/29

  • Enzo at Mitaka 1/29 and most of 1/30, then vacation.
  • Kozu-kun away.
  • All others at Kamioka.
  • Make in-air pico adapter cables.
  • Test IM picos and BF yaw pico.
  • Test FR.
  • Calibrate LVDT.
  • Get screws for ballast mass from Takahashi-san.
  • Install ballast mass in BF.
  • Set up for F0 test.
    • Lower IM crossbars in SR3 assembly frame.
    • Open curtain on SR3 crane slot.
    • Set up dummy load (weight carrier, rods etc).
  • Do F0 test.
    • Bring in F0.
    • Hook up dummy load.
    • Adjust dummy load.

Plan for week of 2/5

  • Enzo on vacation; all others at Kamioka.
  • Build IRM around IM.
  • Cable/test/adjust IM OSEMs.
  • Time permitting, do TFs from IM OSEMs to themselves and to optical sensor.

Plan for week of 2/12

  • Enzo on vacation; all others at Kamioka.

Vacation Info

  • Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30)
  • Kozu-kun 1/29-2/2