Line 5: Line 5:
 * Type B Past Week Summary
  * There were multiple issues with the dummy BS flag/prism gluing [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1830 |klog]]. The sapphire prisms will need to be removed and reapplied. Hirose-san is going to organize this. He wants to try the cup that had been made for the PR2 on the actual PR2 and then see if a new cup is needed for the BS (considering the different radius).
  * Hirata-san added the optical layout information to the BS Inventor assembly. He requested tank information from Mirapro so he can continue to do SR2/3/M.
  * Fabian finished the IM assembly and started on the IRM and RM. Some of the IRM panels had been improperly wrapped and really should be re-cleaned. The MPC (multi-purpose cube) on the RM will need some rework.
  * Mark scheduled a review for Thursday 6/16.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
  * Feedthrough Adapters
   * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote.
  * Can we make SR wire breakers bigger?
   * Fukushima-san will start on machining test soon (as of 5/27).
  * Not enough crane height problem (Hirata, Saito) - no action since last week
  * Installation stuff
   * Crane scale - quote received
   * Work platforms - RECEIVED
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
  * Clean bag - RECEIVED.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
=== Type B (Mark) ===
==== Report for week of 2/19 ====
 * We did TFs from the IM OSEMs.
 * We secured the cables inside the BF, added the cap and anchored the cables from below the BF to the cap.
 * We lifted the BF/... section with the load gauge adapter and measured the weight, which was about as expected.
 * Based on the measured weight, Fabian prepared an 800 g set of masses for the top of the BF.
 * We added the AF crossbars and the section of the SS below the SF and craned in the SF.
 * We installed the SF-BF rod and flying saucer and suspended the BF/... section. With the 800 g placed temporarily on the BF, the SF keystone floated at about mid-range.

==== Plan for week of 2/26 ====
 * Shoda-san at Mitaka.
 * -
 * Enzo at Mitaka Mon 2/26.
 * '''Remove LBB temporary ballast masses from BS chamber.'''
 * Route cables up to under SF.
 * Check/adjust total mass and balance of BF/... section, especially IM OSEMs.
 * Cable and calibrate SF LVDT.
 * Add Cu segments to SF cap.
 * Install cap.
 * Lift SF/... section and check total mass and balance.

==== Plan for week of 3/5 ====
 * Shoda-san at Mitaka.
 * Hirata-san vacation Mon 3/5, then Kamioka
 * Others at Kamioka.
 * -
 * Get SRM tank mushroom section installed (Hirata-san, Kimura-san)
 * SR3 rack setup.
 * Other tasks TBD.

==== Plan for week of 3/12 ====
 * Shoda-san at Mitaka.
 * Mark at ASJ (Chiba) Fri 3/16.
 * Hirata-san vacation Mon 3/5, then Kamioka

==== Plan for week of 3/19 ====
 * Mark at LVC meeting
 * Shoda-san, Fabian at Mitaka

==== Plan for week of 3/26 ====
 * Mark vacation.
 * Others ???

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/March2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/April2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]

==== Vacation Info ====
 * Enzo Mitaka day 2/26
 * Hirata-san vacation 3/5
 * Hirata-san vacation Mon 3/5
 * Fabian 3/26-4/27 vacation (then gone).

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 2/19

  • We did TFs from the IM OSEMs.
  • We secured the cables inside the BF, added the cap and anchored the cables from below the BF to the cap.
  • We lifted the BF/... section with the load gauge adapter and measured the weight, which was about as expected.
  • Based on the measured weight, Fabian prepared an 800 g set of masses for the top of the BF.
  • We added the AF crossbars and the section of the SS below the SF and craned in the SF.
  • We installed the SF-BF rod and flying saucer and suspended the BF/... section. With the 800 g placed temporarily on the BF, the SF keystone floated at about mid-range.

Plan for week of 2/26

  • Shoda-san at Mitaka.
  • -
  • Enzo at Mitaka Mon 2/26.
  • Remove LBB temporary ballast masses from BS chamber.

  • Route cables up to under SF.
  • Check/adjust total mass and balance of BF/... section, especially IM OSEMs.
  • Cable and calibrate SF LVDT.
  • Add Cu segments to SF cap.
  • Install cap.
  • Lift SF/... section and check total mass and balance.

Plan for week of 3/5

  • Shoda-san at Mitaka.
  • Hirata-san vacation Mon 3/5, then Kamioka
  • Others at Kamioka.
  • -
  • Get SRM tank mushroom section installed (Hirata-san, Kimura-san)
  • SR3 rack setup.
  • Other tasks TBD.

Plan for week of 3/12

  • Shoda-san at Mitaka.
  • Mark at ASJ (Chiba) Fri 3/16.
  • Hirata-san vacation Mon 3/5, then Kamioka

Plan for week of 3/19

  • Mark at LVC meeting
  • Shoda-san, Fabian at Mitaka

Plan for week of 3/26

  • Mark vacation.
  • Others ???

To-Do Lists, Schedule

Vacation Info

  • Enzo Mitaka day 2/26
  • Hirata-san vacation 3/5
  • Hirata-san vacation Mon 3/5
  • Fabian 3/26-4/27 vacation (then gone).