 * Type B Past Week Summary
  * There were multiple issues with the dummy BS flag/prism gluing [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1830 |klog]]. The sapphire prisms will need to be removed and reapplied. Hirose-san is going to organize this. He wants to try the cup that had been made for the PR2 on the actual PR2 and then see if a new cup is needed for the BS (considering the different radius).
  * Hirata-san added the optical layout information to the BS Inventor assembly. He requested tank information from Mirapro so he can continue to do SR2/3/M.
  * Fabian finished the IM assembly and started on the IRM and RM. Some of the IRM panels had been improperly wrapped and really should be re-cleaned. The MPC (multi-purpose cube) on the RM will need some rework.
  * Mark scheduled a review for Thursday 6/16.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
  * Feedthrough Adapters
   * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote.
  * Can we make SR wire breakers bigger?
   * Fukushima-san will start on machining test soon (as of 5/27).
  * Not enough crane height problem (Hirata, Saito) - no action since last week
  * Installation stuff
   * Crane scale - quote received
   * Work platforms - RECEIVED
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
  * Clean bag - RECEIVED.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
=== Type B (Mark) ===
==== Report for week of 10/8 ====
 * This was Panwei's last week (for now at least) - thanks for all the help!
 * Thanks also to Terrence for visiting again for the week.
===== SR3 =====
 * Terrence and Mark finished setting up the LEN half of the OL (Simon had roughly placed the components). They ran a new cable for LEN in the cable tray and relaid the cable for TILT to get it off the floor.
 * Terrence worked on diagonalizing the LEN OL. A report is forthcoming.
===== SRM =====
 * Mark installed a pair of power supplies in the SRM and copied settings across to the SRM real-time model.
 * Fabian did lots of rack cabling, including installing and connecting BIO cards.
 * Mark and Hirata-san checked and adjusted the pitch of the BF (with a bubble level) and the IM/... section (with the OL).
 * Mark and Panwei installed the sides of the IRM and the IM OSEMs.
 * Hirata-san hung the dummy load from the F0 and started compressing the blade. There was a significant lateral offset (≈2-3 mm towards the blade at 5:30) at first but Takahashi-san advised that it would probably improve with compression, and it did.
 * Mark and Hirata-san cleared off most of two optical tables and a set of shelves in the OMMT area that Type B had been using but were now required by Somiya-san and Ohishi-san. We still need to remove the geophone and OSEM testing setups.

===== SR2 =====
 * Mark, Enzo and Hirata-san all inspected the lower section of the SR2 to see if there were any interference points that might explain some unexpected peaks in the TFs (especially the RM pitch made appearing in longitudinal) that weren't present before installation. There were no stops touching, but some TM OSEM cables were rubbing against each other, which we fixed. The problem turned out to be swapped cables in the coil actuation.
 * We removed the tank lid, and Enzo and Panwei inspected the cabling that had been done during Enzo's vacation and installed some new cables that had arrived. They also unlocked the IP.

==== Plan for week of 10/15 ====
 * Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.
===== SR2 =====
 * Continue shakedown of PI section.
===== SRM =====
 * Align IRM with IM.
 * Suspend/weigh/balance the BF/... section.
 * Build up the AF and SS to the SF level.
 * Install the SF.

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]

==== Vacation/Visitor Info ====
 * Terrence: 10/29-11/2 at Kamioka.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 10/8

  • This was Panwei's last week (for now at least) - thanks for all the help!
  • Thanks also to Terrence for visiting again for the week.

SR3
  • Terrence and Mark finished setting up the LEN half of the OL (Simon had roughly placed the components). They ran a new cable for LEN in the cable tray and relaid the cable for TILT to get it off the floor.
  • Terrence worked on diagonalizing the LEN OL. A report is forthcoming.

SRM
  • Mark installed a pair of power supplies in the SRM and copied settings across to the SRM real-time model.
  • Fabian did lots of rack cabling, including installing and connecting BIO cards.
  • Mark and Hirata-san checked and adjusted the pitch of the BF (with a bubble level) and the IM/... section (with the OL).
  • Mark and Panwei installed the sides of the IRM and the IM OSEMs.
  • Hirata-san hung the dummy load from the F0 and started compressing the blade. There was a significant lateral offset (≈2-3 mm towards the blade at 5:30) at first but Takahashi-san advised that it would probably improve with compression, and it did.
  • Mark and Hirata-san cleared off most of two optical tables and a set of shelves in the OMMT area that Type B had been using but were now required by Somiya-san and Ohishi-san. We still need to remove the geophone and OSEM testing setups.

SR2
  • Mark, Enzo and Hirata-san all inspected the lower section of the SR2 to see if there were any interference points that might explain some unexpected peaks in the TFs (especially the RM pitch made appearing in longitudinal) that weren't present before installation. There were no stops touching, but some TM OSEM cables were rubbing against each other, which we fixed. The problem turned out to be swapped cables in the coil actuation.
  • We removed the tank lid, and Enzo and Panwei inspected the cabling that had been done during Enzo's vacation and installed some new cables that had arrived. They also unlocked the IP.

Plan for week of 10/15

  • Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.

SR2
  • Continue shakedown of PI section.

SRM
  • Align IRM with IM.
  • Suspend/weigh/balance the BF/... section.
  • Build up the AF and SS to the SF level.
  • Install the SF.

To-Do Lists, Schedule

Vacation/Visitor Info

  • Terrence: 10/29-11/2 at Kamioka.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)