Differences between revisions 28 and 339 (spanning 311 versions)
Revision 28 as of 2016-06-15 19:45:04
Size: 2200
Editor: MarkBarton
Comment:
Revision 339 as of 2018-10-28 19:16:53
Size: 4354
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary
  * There were multiple issues with the dummy BS flag/prism gluing [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1830 |klog]]. The sapphire prisms will need to be removed and reapplied. Hirose-san is going to organize this. He wants to try the cup that had been made for the PR2 on the actual PR2 and then see if a new cup is needed for the BS (considering the different radius).
  * Hirata-san added the optical layout information to the BS Inventor assembly. He requested tank information from Mirapro so he can continue to do SR2/3/M.
  * Fabian finished the IM assembly and started on the IRM and RM. Some of the IRM panels had been improperly wrapped and really should be re-cleaned. The MPC (multi-purpose cube) on the RM will need some rework.
  * Mark scheduled a review for Thursday 6/16.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
  * Feedthrough Adapters
   * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote.
  * Can we make SR wire breakers bigger?
   * Fukushima-san will start on machining test soon (as of 5/27).
  * Not enough crane height problem (Hirata, Saito) - no action since last week
  * Installation stuff
   * Crane scale - quote received
   * Work platforms - RECEIVED
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
  * Clean bag - RECEIVED.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
=== Type B (Mark) ===
==== Report for week of 10/22 ====
===== SRM =====
 * We borrowed the TM HPCDs from SR2 and SR3 so that SRM had HPCDs for IM-H, IM-V and GAS.
 * Fabian adjusted the last two OSEMs (IM-H2 and H3).
 * We closed the BF and weighed the BF/... section.
 * Fabian and Hirata-san routed all the BF/... cables via the BF cap (except for the four TM OSEM cables, where we're still waiting for extensions).
 * We built up the assembly frame and security structure to the SF level and craned in the SF.
 * We installed the SF-BF rod and flying saucer, and suspended the BF/... section. We will need about 600 g on the BF cap for balance and SF keystone height, which is as expected and not a problem.
 * Hirata-san collected a suitable CuBe spring and bracket parts from Type A. He ultrasonically cleaned the bracket and then installed the bracket and spring on the F0. The frequency increased from 0.5 Hz to 0.625 Hz, so he did another round of compression, from 30 mm to 31.3 mm.
 * Enzo soldered some short and/or broken cables to make longer cables that we need urgently. He got in touch with Yamamoto-san to arrange bringing them to Toyama University and ultrasonically cleaning them.
 * We pulled out cables running to the OMMT area that were used for the old OSEM/geophone testing setup and started a new geophone testing setup in the SR3 area using the optical table from the SR2 assembly frame.
 * Hirose-san reported results from his astigmatism test on the second SRM small optic and metal mass. With the tight shims (1.0 mm thickness, as used for the installed SRM) there was substantial astigmatism, but with the next looser available size (1.5 mm) there was no astigmatism but the optic is held very poorly and rattles. Hirose-san is ordering some intermediate thicknesses and will make a recommendation. However he will almost certainly suggest that we change the shims on the hanging SRM, so we need to think about whether that is feasible.

===== SR2 =====
 * Akutsu-san gathered the parts we will need for the SR2 OL so that Terrence can install it next week.
 * Hirata-san supervised the disassembly of the assembly frame. The pieces are now in the IMMT area, although we may need to move them again because they're a bit in the way.

==== Plan for week of 10/29 ====
 * Mark, Enzo, Hirata-san, Fabian and Terrence at Kamioka Mon-Fri.
===== SR2 =====
 * Set up OL.
 * Possibly do a measurement of how much torque is required on the F0 keystone to move the system in yaw. (This will help Sato-san choose a suitable stepper driver for the new design.)
 * Possibly add more arc weights, to get below 0.1 Hz.
===== SRM =====
 * Electronics
  * More cable soldering?
  * Get soldered cables ultrasonically cleaned.
  * Collect unused cables for return to AEL.
 * PI
  * Finalize tuning.
  * Add more cable clamps.
  * Prepare SF magnet ring.
 * Main sequence
  * Cable/test SF LVDT and FR.
  * Decide and install SF internal ballast mass (probably 1 Promec).
  * Reinstall SF cap.
  * Weigh SF/... section.
  * Install #353 poles
  * Move NB-03 jacks down.
  * Crane PI into AF.
  * Install F0-SF rod (#331) and flying saucer.
  * Route SF/... cables up to underside of F0.
  * Do vertical height budget.
  * Adjust SF trim mass for balance and keystone height.

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]

==== Plan for week of 10/29 ====
 * Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri (except Hirata-san to take compensation day Friday or Monday (TBD)).
===== SRM =====
 * Main sequence
  * Cable/test IP LVDTs.
  * Cable/test IP FRs.
  * Unlock IP and center roughly.
  * Calibrate IP LVDTs.
  * Check/adjust alignment of SS.
  * Add arc weights and geophones (or extra mass equivalent to geophones).
  * Cable/test geophones.
  * Improve centering/tuning of IP and SS alignment.
 * LBB
  * Move KOACH filters
  * Put LBB damper rings in tank.
  * Set tank jacks to nominal height.

==== Vacation/Visitor Info ====
 * Terrence: 10/29-11/2 at Kamioka.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 10/22

SRM
  • We borrowed the TM HPCDs from SR2 and SR3 so that SRM had HPCDs for IM-H, IM-V and GAS.
  • Fabian adjusted the last two OSEMs (IM-H2 and H3).
  • We closed the BF and weighed the BF/... section.
  • Fabian and Hirata-san routed all the BF/... cables via the BF cap (except for the four TM OSEM cables, where we're still waiting for extensions).
  • We built up the assembly frame and security structure to the SF level and craned in the SF.
  • We installed the SF-BF rod and flying saucer, and suspended the BF/... section. We will need about 600 g on the BF cap for balance and SF keystone height, which is as expected and not a problem.
  • Hirata-san collected a suitable CuBe spring and bracket parts from Type A. He ultrasonically cleaned the bracket and then installed the bracket and spring on the F0. The frequency increased from 0.5 Hz to 0.625 Hz, so he did another round of compression, from 30 mm to 31.3 mm.

  • Enzo soldered some short and/or broken cables to make longer cables that we need urgently. He got in touch with Yamamoto-san to arrange bringing them to Toyama University and ultrasonically cleaning them.
  • We pulled out cables running to the OMMT area that were used for the old OSEM/geophone testing setup and started a new geophone testing setup in the SR3 area using the optical table from the SR2 assembly frame.
  • Hirose-san reported results from his astigmatism test on the second SRM small optic and metal mass. With the tight shims (1.0 mm thickness, as used for the installed SRM) there was substantial astigmatism, but with the next looser available size (1.5 mm) there was no astigmatism but the optic is held very poorly and rattles. Hirose-san is ordering some intermediate thicknesses and will make a recommendation. However he will almost certainly suggest that we change the shims on the hanging SRM, so we need to think about whether that is feasible.

SR2
  • Akutsu-san gathered the parts we will need for the SR2 OL so that Terrence can install it next week.
  • Hirata-san supervised the disassembly of the assembly frame. The pieces are now in the IMMT area, although we may need to move them again because they're a bit in the way.

Plan for week of 10/29

  • Mark, Enzo, Hirata-san, Fabian and Terrence at Kamioka Mon-Fri.

SR2
  • Set up OL.
  • Possibly do a measurement of how much torque is required on the F0 keystone to move the system in yaw. (This will help Sato-san choose a suitable stepper driver for the new design.)
  • Possibly add more arc weights, to get below 0.1 Hz.

SRM
  • Electronics
    • More cable soldering?
    • Get soldered cables ultrasonically cleaned.
    • Collect unused cables for return to AEL.
  • PI
    • Finalize tuning.
    • Add more cable clamps.
    • Prepare SF magnet ring.
  • Main sequence
    • Cable/test SF LVDT and FR.
    • Decide and install SF internal ballast mass (probably 1 Promec).
    • Reinstall SF cap.
    • Weigh SF/... section.
    • Install #353 poles
    • Move NB-03 jacks down.
    • Crane PI into AF.
    • Install F0-SF rod (#331) and flying saucer.
    • Route SF/... cables up to underside of F0.
    • Do vertical height budget.
    • Adjust SF trim mass for balance and keystone height.

To-Do Lists, Schedule

Plan for week of 10/29

  • Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri (except Hirata-san to take compensation day Friday or Monday (TBD)).

SRM
  • Main sequence
    • Cable/test IP LVDTs.
    • Cable/test IP FRs.
    • Unlock IP and center roughly.
    • Calibrate IP LVDTs.
    • Check/adjust alignment of SS.
    • Add arc weights and geophones (or extra mass equivalent to geophones).
    • Cable/test geophones.
    • Improve centering/tuning of IP and SS alignment.
  • LBB
    • Move KOACH filters
    • Put LBB damper rings in tank.
    • Set tank jacks to nominal height.

Vacation/Visitor Info

  • Terrence: 10/29-11/2 at Kamioka.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)