Line 5: Line 5:
 * Type B Past Week Summary
  * There were multiple issues with the dummy BS flag/prism gluing [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1830 |klog]]. The sapphire prisms will need to be removed and reapplied. Hirose-san is going to organize this. He wants to try the cup that had been made for the PR2 on the actual PR2 and then see if a new cup is needed for the BS (considering the different radius).
  * Hirata-san added the optical layout information to the BS Inventor assembly. He requested tank information from Mirapro so he can continue to do SR2/3/M.
  * Fabian finished the IM assembly and started on the IRM and RM. Some of the IRM panels had been improperly wrapped and really should be re-cleaned. The MPC (multi-purpose cube) on the RM will need some rework.
  * Mark scheduled a review for Thursday 6/16.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
  * OSEMs
  * Feedthrough Adapters
   * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote.
  * Can we make SR wire breakers bigger?
   * Fukushima-san will start on machining test soon (as of 5/27).
  * Not enough crane height problem (Hirata, Saito) - no action since last week
  * Installation stuff
   * Crane scale - quote received
   * Work platforms - RECEIVED
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
  * Clean bag - RECEIVED.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
=== Type B (Mark) ===
==== Report for week of 11/19 ====
 * SRM
  * We locked the suspension and craned it into the tank. This is the last Type B tank installation!
  * While inspecting the O-ring between the service ring and the lower section of the tank, Hirata-san found a small nick, so he replaced it. (This will hopefully be the last time that flange is closed, so it needs to be left ready for Mirapro to tighten.)
  * Hirata-san and Fabian removed the First Contact, but found that a tiny piece was left behind. With advice from Hirose-san, they managed to remove it via several rounds of dabbing with an acetone-soaked lens tissue.
  * They removed the IM-RM safety bar, unlocked the lower half of the suspension, and got it reasonably well aligned by eye.
  * They moved the vacuum feedthroughs and in-air cabling over, and reconnected nearly all the electronics. (The in-air cabling will need some tidying later, but
 * SR2
  * Enzo worked on diagonalizing the IP and modeling of the whole suspension. He created Foton filters representing the response of the system in slots FM6-8 of the various filter banks.
  * Enzo and Mark set up the the SR2 OL. We may need to steal the LED back temporarily to do pitch setting on SRM, but we can take some interesting TFs on SR2 over the weekend.
 * SR3
  * Enzo configured a new stepper driver for SR3_IP and returned the one that had been borrowed from SRM. (The original SR3_IP had been used to replace a water-damaged unit on the BS.)
 * Etc
  * Mark got three more MPCDs (M = "medium" or "modified") from AEL and moved coil drivers around until all Type B suspensions had a driver in every position, with MPCDs for IM-H and HPCDs everywhere else. He returned the unused LPCDs.
  * Mark did an inventory of all the Type B electronics and got the various JGW Doc electronic items lists up to date - see [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7276|E1707276]]. This included opening all the LVDT drivers to check that they had the original cards - BS, SR3 and SRM did, but SR2 had both input cards new. We let AEL know.
  * Hirata-san helped Furuta-san with floor repair.
  * Fabian changed the PR3 thermometer battery.
  * Mirapro installed a bellows on the -Y side of SR3.
==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]

==== Plan for week of 12/17 ====
 * Final alignment of SRM payload, plus BF and SF GAS.
 * (Time permitting) unlocking/centering/tuning of IP.
 * Installation of Enomoto-kun's beam target on SRM (if available).
 * Installation/testing of F0 steppers on SR2, SR3, SRM, and (hopefully) final vertical height adjustment.
 * Installation of viewports on SRM.

==== Plan for week of 12/24 ====
 * Most of team on holidays - no Kamioka work.

==== Vacation/Etc Info ====
 * Mark: 12/24 - 1/4.
 * Hirata-san: 12/24 - 1/4.
 * Fabian: TBD but similar.
 * Enzo: TBD but similar.
 * Mark and Enzo: KAGRA International Workshop in Perugia, 2/14-16.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 11/19

  • SRM
    • We locked the suspension and craned it into the tank. This is the last Type B tank installation!
    • While inspecting the O-ring between the service ring and the lower section of the tank, Hirata-san found a small nick, so he replaced it. (This will hopefully be the last time that flange is closed, so it needs to be left ready for Mirapro to tighten.)
    • Hirata-san and Fabian removed the First Contact, but found that a tiny piece was left behind. With advice from Hirose-san, they managed to remove it via several rounds of dabbing with an acetone-soaked lens tissue.
    • They removed the IM-RM safety bar, unlocked the lower half of the suspension, and got it reasonably well aligned by eye.
    • They moved the vacuum feedthroughs and in-air cabling over, and reconnected nearly all the electronics. (The in-air cabling will need some tidying later, but
  • SR2
    • Enzo worked on diagonalizing the IP and modeling of the whole suspension. He created Foton filters representing the response of the system in slots FM6-8 of the various filter banks.
    • Enzo and Mark set up the the SR2 OL. We may need to steal the LED back temporarily to do pitch setting on SRM, but we can take some interesting TFs on SR2 over the weekend.
  • SR3
    • Enzo configured a new stepper driver for SR3_IP and returned the one that had been borrowed from SRM. (The original SR3_IP had been used to replace a water-damaged unit on the BS.)
  • Etc
    • Mark got three more MPCDs (M = "medium" or "modified") from AEL and moved coil drivers around until all Type B suspensions had a driver in every position, with MPCDs for IM-H and HPCDs everywhere else. He returned the unused LPCDs.
    • Mark did an inventory of all the Type B electronics and got the various JGW Doc electronic items lists up to date - see E1707276. This included opening all the LVDT drivers to check that they had the original cards - BS, SR3 and SRM did, but SR2 had both input cards new. We let AEL know.

    • Hirata-san helped Furuta-san with floor repair.
    • Fabian changed the PR3 thermometer battery.
    • Mirapro installed a bellows on the -Y side of SR3.

To-Do Lists, Schedule

Plan for week of 12/17

  • Final alignment of SRM payload, plus BF and SF GAS.
  • (Time permitting) unlocking/centering/tuning of IP.
  • Installation of Enomoto-kun's beam target on SRM (if available).
  • Installation/testing of F0 steppers on SR2, SR3, SRM, and (hopefully) final vertical height adjustment.
  • Installation of viewports on SRM.

Plan for week of 12/24

  • Most of team on holidays - no Kamioka work.

Vacation/Etc Info

  • Mark: 12/24 - 1/4.
  • Hirata-san: 12/24 - 1/4.
  • Fabian: TBD but similar.
  • Enzo: TBD but similar.
  • Mark and Enzo: KAGRA International Workshop in Perugia, 2/14-16.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)