Line 6: Line 6:
  * There were multiple issues with the dummy BS flag/prism gluing [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1830 |klog]]. The sapphire prisms will need to be removed and reapplied. Hirose-san is going to organize this. He wants to try the cup that had been made for the PR2 on the actual PR2 and then see if a new cup is needed for the BS (considering the different radius).
  * Hirata-san added the optical layout information to the BS Inventor assembly. He requested tank information from Mirapro so he can continue to do SR2/3/M.
  * Fabian finished the IM assembly and started on the IRM and RM. Some of the IRM panels had been improperly wrapped and really should be re-cleaned. The MPC (multi-purpose cube) on the RM will need some rework.
  * Mark scheduled a review for Thursday 6/16.
  * Mark, Fabian and Hirata-san cleaned glue off the dummy BS, attached Akutsu-san's new SS mirror plates, reglued the flags and prisms, and removed the gluing hardware, so the dummy BS is ready for shipping. Tatsumi-san's refinements to the tooling (especially the new flag holders) worked very smoothly. We were more generous with the glue and much more careful with the alignment of the prisms to the barrel, both during rehearsal and the final gluing.
  * Mark wrote up the gluing procedure as a new document [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5505| E1605505]]. (The original plan was to do an addendum to Tatsumi-san's PR gluing procedure JGW-E1504248, but there was too much material.)
  * Hirata-san organized with Takahashi-san to get the BS payload masses shipped to Kamioka. They will go in an air-ride truck on Wed 8/17 together with a load of Type A stuff, and will arrive early on Thu 8/17.
  * Hirata-san shipped the collection of Type B fasteners to Kamioka, to arrive Mon 8/15.
  * Hirata-san measured another standard filter and cleaned various parts for people.
  * Hirata-san worked on the SR2 Inventor assembly. He spotted a problem with the orientation: given the position of the pistons in the SR2 tank (according to the assembly from Mirapro), mating the standard Type B SR chain and the chamber in the natural way puts the optic at 90° to what it needs to be. A similar problem was found in the Type B Test at Mitaka, and it was eventually worked around, but with some difficulty. Hirata-san will investigate the best way of making a correction.
  * Fabian worked on the payload assembly procedure.
  * Komori-kun, Kuwahara-kun and Akutsu-san calibrated an initial batch of 7 wide-mouthed OSEMs. They will be shipped to Kamioka on Friday.
 
Line 11: Line 16:
  * Wires
   * Need to decide RM wire thickness and order BS and RM wires. Lead time is a few days from Nilaco.
Line 14: Line 17:
  * Feedthrough Adapters
   * Need large quantity of male and female D-Sub 9, IDC ribbon connectors - Takahashi-san is getting a quote.
  * Can we make SR wire breakers bigger?
   * Fukushima-san will start on machining test soon (as of 5/27).
  * Not enough crane height problem (Hirata, Saito) - no action since last week
  * Installation stuff
   * Crane scale - quote received
   * Work platforms - RECEIVED
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
   * First batch of 7 ready for shipping.
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
Line 26: Line 22:
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
  * Clean bag - RECEIVED.
Line 31: Line 24:
 * To-do list during Mark's vacation
  * Weigh IM/RM/IRM (Fabian, Hirata) - DONE
   * New trim mass - ORDERED.
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian) - READY TO SHIP.
  * Analyze geophone data (Fabian/Shoda) - DONE.
  * Remove glue from dummy BS face (Fabian) - DONE.
  * Reglue flags and prisms (Tatsumi, Fabian) - DONE.
  * Clean wire for BS and RM (Hirata) - DONE
  * Get new winch parts for new wire diameters - ORDERED, expected 8/5.
  * Do fit/function test of winches (Fabian/Hirata) - fit test DONE, function test from 8/8
  * Ship winches to Kamioka (Hirata/Fabian)
  * Work on BS simulation (Fabian)
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of main assembly procedure (Mark) - ONGOING
 * Longer term to-do list
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Type B Past Week Summary
    • Mark, Fabian and Hirata-san cleaned glue off the dummy BS, attached Akutsu-san's new SS mirror plates, reglued the flags and prisms, and removed the gluing hardware, so the dummy BS is ready for shipping. Tatsumi-san's refinements to the tooling (especially the new flag holders) worked very smoothly. We were more generous with the glue and much more careful with the alignment of the prisms to the barrel, both during rehearsal and the final gluing.
    • Mark wrote up the gluing procedure as a new document E1605505. (The original plan was to do an addendum to Tatsumi-san's PR gluing procedure JGW-E1504248, but there was too much material.)

    • Hirata-san organized with Takahashi-san to get the BS payload masses shipped to Kamioka. They will go in an air-ride truck on Wed 8/17 together with a load of Type A stuff, and will arrive early on Thu 8/17.
    • Hirata-san shipped the collection of Type B fasteners to Kamioka, to arrive Mon 8/15.
    • Hirata-san measured another standard filter and cleaned various parts for people.
    • Hirata-san worked on the SR2 Inventor assembly. He spotted a problem with the orientation: given the position of the pistons in the SR2 tank (according to the assembly from Mirapro), mating the standard Type B SR chain and the chamber in the natural way puts the optic at 90° to what it needs to be. A similar problem was found in the Type B Test at Mitaka, and it was eventually worked around, but with some difficulty. Hirata-san will investigate the best way of making a correction.
    • Fabian worked on the payload assembly procedure.
    • Komori-kun, Kuwahara-kun and Akutsu-san calibrated an initial batch of 7 wide-mouthed OSEMs. They will be shipped to Kamioka on Friday.
  • Type B ongoing issues
    • OSEMs
      • First batch of 7 ready for shipping.
    • Longer cables for BF->PI and SF->PI.

      • Connectors RECEIVED, cables being made.
    • Lower breadboard stuff
      • Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
    • Documents
  • To-do list during Mark's vacation
    • Weigh IM/RM/IRM (Fabian, Hirata) - DONE
      • New trim mass - ORDERED.
    • Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian) - READY TO SHIP.
    • Analyze geophone data (Fabian/Shoda) - DONE.
    • Remove glue from dummy BS face (Fabian) - DONE.
    • Reglue flags and prisms (Tatsumi, Fabian) - DONE.
    • Clean wire for BS and RM (Hirata) - DONE
    • Get new winch parts for new wire diameters - ORDERED, expected 8/5.
    • Do fit/function test of winches (Fabian/Hirata) - fit test DONE, function test from 8/8
    • Ship winches to Kamioka (Hirata/Fabian)
    • Work on BS simulation (Fabian)
    • Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
    • Write more of payload assembly procedure (Fabian) - ONGOING
    • Write more of main assembly procedure (Mark) - ONGOING
  • Longer term to-do list
    • Do BS Simulink model (Mark, Kokeyama)
    • Do 2D drawings of SR2 parts (Hirata)
    • Redesign SRx IM wire clamps for larger prisms, remachined RMs
    • Order SRM/PRM parts (Hirata/Shoda)
    • Order SRx fasteners (Hirata)